2.1 Contractor Classifications (A, B, C), Scopes & Monetary Limits

Key Takeaways

  • NRS 624.215 makes general engineering and general building separate branches. The Board offers a combined Class AB license under NAC 624.180.

  • Class B generally covers prime contracting on buildings requiring more than two unrelated trades. A B-2 structure may extend no more than three stories above ground and one below ground.

  • NRS 624.220 applies the monetary limit to one or more contracts on one construction or subdivision site for a single client. NAC 624.640 makes an out-of-scope or over-limit bid or contract void.

  • NAC 624.640 requires the license number and any monetary limit in every Nevada construction bid and contract. NRS 624.220 requires a single-project increase request at least five working days before the intended bid, with Board approval before bidding.

Last updated: November 2026

Contractor Classifications, Scopes and Monetary Limits

Read a Nevada bidding question as two checks. First, compare the work with the license classification and any subclassification. Then compare the total contract value with the monetary limit on the license. A company can have the right license for the work and still submit a void bid if it exceeds its limit. Licensing accounts for ten of the sixty scored CMS questions.

Find the Class That Authorizes the Work

Nevada Revised Statutes (NRS) 624.215 establishes three branches. The Nevada Administrative Code (NAC) provides the work authorized at the classification and subclassification level.

BranchTypical workBoundary to check
A, General EngineeringFixed works such as roads, bridges, water systems and other projects requiring specialized engineering knowledgeGeneral engineering and general building are separate branches. NAC 624.140 points to the fixed works in NRS 624.215(2).
B, General BuildingConstruction or remodeling of a building for support, shelter or enclosure, generally as prime contractor on work involving more than two unrelated tradesCheck who contracts with the owner, what the main project is, and which work requires a specialty license.
B-2, Residential and Small CommercialConstruction and remodeling of houses and other qualifying structuresNAC 624.170(2) limits the structure to three stories above ground and one story below. Count the stories of the structure when evaluating a ground-floor remodel.
C, Specialty ContractingWork requiring specialized trade skills, such as C-2 electrical or C-5 concreteRead the scope of the exact classification or subclassification. NRS 624.220(4)(a) allows incidental and supplemental work in other trades, subject to Board regulations.

The Board may issue a combined AB license when the applicant qualifies for both general branches. NRS 624.215(5) also allows a general engineering prime contractor to hire up to one general building contractor for qualifying general building work on a single project. The presence of a small building on a highway assignment is therefore a reason to check that rule and the actual work package before choosing a classification.

Identify the Prime Contractor and Check Specialty Work

General building scope ordinarily involves more than two unrelated trades. For example, a three-trade remodel can be a general building project if the building work is the main purpose and the licensee is acting as the prime contractor. NRS 624.215(6) separately permits qualifying general building contractors to provide management and counseling services for a fee if their active license carries the same classifications and subclassifications required of the prime contractor.

In an ordinary Class B project, a firm without the appropriate specialty license should subcontract plumbing, electrical, refrigeration and air-conditioning, and fire protection work to qualified licensees. NRS 624.215(3) ties that rule to the limited provisions of NRS 624.220(4). For an ordinary permitted rewiring package, check that the subcontractor has the required electrical classification and any subclassification. A person can hold a valid Nevada license for an entirely different trade.

Combine Contracts on the Same Site for the Same Client

The Board considers factors such as financial responsibility in setting the license limit. Under NRS 624.220(2), the monetary limit is the maximum value the contractor may undertake on one or more construction contracts on a single construction site or subdivision site for one client. Use the contract price, including the subcontracted work and any overhead or profit included in the price. Check proposed change orders against the revised total before signing.

Suppose Desert Ridge Builders has a B-2 license with a $250,000 limit. The company is asked to price a qualifying single-story retail build-out at $310,000. Two scopes of $155,000 each for the same client and site still total $310,000. An owner’s written consent does not alter the Board’s limit. The company is $60,000 over, and NAC 624.640(1) makes an over-limit bid or resulting contract void. NRS 624.3015(2) makes over-limit bidding or contracting grounds for Board discipline.

The same exposure arises mid-project. An original $240,000 contract fits the limit. A proposed $70,000 change order raises the project total to $310,000, so the contractor needs an adequate approved limit before undertaking the added work. If the firm knows before bidding that it needs a higher limit, NRS 624.220(3) provides two routes:

  • Permanent increase. Apply in writing under NAC 624.669 with the required financial statement, applicable fees and other requested information.
  • Single-project increase. Apply in writing with the required financial statement and supporting information under NAC 624.670. Submit the request at least five working days before you intend to bid. Obtain Board approval before submitting the bid. NAC 624.670 limits the licensee to five such applications in any 12-month period and allows the Board to require performance or payment bonds.

Verify and Disclose Before Submitting the Bid

NAC 624.640(5) requires the contractor's license number and any monetary limit on every bid and contract for construction work in Nevada. Subsection 6 also requires the licensee to check that each bidder it considers on the project is appropriately licensed. Put the classifications, bid values and checks in the project file. An out-of-scope bid and an over-limit bid each create a separate issue even when the estimate is otherwise correct.

Nevada contractor statutes, including NRS 624.215, 624.220 and 624.3015 · Nevada contractor regulations, including NAC 624.140, 624.160–.180, 624.640, and 624.669–.670

Test Your Knowledge

A Nevada Class B-2 contractor with a $250,000 monetary limit submits a $310,000 bid on a single-story commercial build-out without prior Board approval. Under NAC 624.640 and NRS 624.3015, what is the legal status of this bid and any resulting contract?

A

Valid if the property owner signs a written waiver acknowledging the $250,000 limit

B

Valid as long as the contractor splits the scope into two $155,000 contracts on the same site

C

Void from inception, exposing the contractor to NSCB disciplinary action and loss of contract enforceability

D

Valid unless the contractor exceeds $250,000 in direct material and labor costs excluding profit

Test Your Knowledge
Multi-Select

Which of the following actions violate Nevada contractor classification or disclosure rules under NRS 624.215 and NAC 624.640? (Select all that apply.)

Select all that apply

A Class B-2 licensee contracts to remodel a ground-floor lobby inside a 5-story office building

A Class B prime contractor subcontracts wiring to an active electrical licensee with the correct subclassification and an adequate monetary limit

A licensed contractor submits a formal bid proposal that lists the license number but omits the monetary limit

A Class B licensee with no plumbing classification uses its own crew to perform a permitted $8,000 rough-plumbing package

Test Your Knowledge
Matching

Match each Nevada contractor classification with its exact statutory scope or limitation under NRS 624.215 and NAC Chapter 624.

Match each item on the left with the correct item on the right

1

Class A (General Engineering)

2

Class B (General Building)

3

Class B-2 (Residential & Small Commercial)

4

Class C-21 (Refrigeration and Air Conditioning)

Sections you finish are checked off in the contents.