9.3 Workers’ Compensation, Public Works Payroll & Wage Claims
Key Takeaways
NRS 624.256 requires acceptable evidence of industrial insurance or a qualifying signed affidavit for original and renewal licensing. A coverage lapse can trigger discipline and statutory notice.
The no-employee affidavit route does not cover a solo applicant who intends to bid on a job for a principal contractor or subcontractor.
Check the Nevada prevailing wage and reporting rules on covered public works with estimated cost of at least $100,000. Monthly payroll records must reach the awarding public body within 15 days after month-end.
For applicable public bidding, a contractor’s preference certificate and project affidavit are distinct. The project affidavit includes workforce, vehicle and payroll-record obligations.
Three substantiated wage claims within two years reported by the Labor Commissioner require the Board to order a surety bond or cash deposit.
Workers’ Compensation, Public Works Payroll, and Wage Claims
A Nevada contractor may need proof of workers’ compensation to hold its license and separate wage records to perform public work. Keep these records distinct. A certificate of insurance addresses coverage, while certified payroll documents what workers were paid.
Industrial Insurance and Nevada Licensure
NRS 616B.612 requires covered employers to secure compensation for job-related injuries. NRS 616A.210 generally deems subcontractors, independent contractors and their employees to be employees of the principal contractor for industrial insurance purposes, subject to statutory rules. The independent-enterprise exception in NRS 616B.603 does not apply to a principal contractor licensed under Chapter 624. A contractor’s employment-tax classification is a separate question.
For original issuance and renewal, NRS 624.256(1) requires proof of employee coverage for industrial insurance and occupational disease, an applicable self-insurance certificate, or a valid signed affidavit. The affidavit route requires that the applicant have no employees and meet its restrictions on subcontracting for a principal contractor and bidding on work for a principal contractor or subcontractor. A solo drywall business that intends to bid a subcontract for a general contractor cannot use the affidavit just because it has no employees.
A failure to file or maintain required coverage is a ground for Board discipline under subsection 3. Under the specific procedure in subsections 4–6, after the Board receives qualifying notice from the Division of Industrial Relations it must send notice to the contractor as soon as practicable, within three business days. If the contractor does not furnish proof of compliance within 30 days after the Board’s notice, the Board suspends the license and requires a list of unfulfilled projects covered by the statute. Suspension continues until proof of compliance and restricts bidding and starting new work. Under subsection 2 the Board also notifies the Fraud Control Unit when it learns a contractor has operated without legally required coverage.
Nevada Public Works Wages
Under NRS 338.020 and 338.080, ordinary covered Nevada public works with an estimated cost of $100,000 or more require applicable prevailing wages. Do not divide a project to bring the estimate below the threshold. Check the statutory exceptions, including the registered apprentice provision, and any separate federal requirements for federally assisted work.
Use the applicable region, craft and rate determination. For competitively bid projects, NRS 338.030 generally uses the rates in effect at bid opening through completion or termination or for 36 months after bid opening, whichever occurs first. Check the statutory rules for work extending past that point. Under NRS 338.020(3), daily and weekly overtime on covered public work can reach workers who earn above the private-job $18.00 threshold. Count hours worked for the same employer on other work when testing the eight-hour day and 40-hour week. Check the statutory 4×10 and qualifying collective-bargaining provisions.
Straight-time example. A hypothetical published wage package for a cement mason is $38.50 cash plus $14.50 fringe, totaling $53.00. The contractor has a valid, properly calculated $6.00 per hour fringe credit under NRS 338.035. The remaining $8.50 is payable in cash, so cash pay is $47.00 an hour, with $6.00 in qualifying benefits. In the actual payroll, confirm which reported benefits qualify and whether annualization applies.
Certified Payroll and Public Works Preference
| Step | Requirement |
|---|---|
| Record | Keep accurate payroll information and the separate identification record required by NRS 338.070. Report actual classification, wages, hours on that public work and applicable fringe details. Use hours on other jobs to test overtime where required, and keep them off this project’s certified payroll. The separate record with driver’s license or identification card numbers is confidential. |
| Certify | Include the signed Statement of Compliance with the certified payroll under NAC 338.094. |
| Submit | Ensure each monthly copy reaches the awarding public body within 15 days after month-end. A subcontractor can submit directly or route through the prime. The statutory through-prime route uses ten days after month-end or a date agreed upon, while the public body’s 15-day deadline still applies. |
| Report inactivity | If a contractor already engaged on the work employs no workers on it in a month, submit the required nonperformance report in place of certified payroll for that month. |
Failure to file a required public-work payroll or knowingly submitting false information in it is a disciplinary ground under NRS 624.3016(9)–(10). Public works forfeitures and Board discipline have separate statutory bases.
The Nevada preference in bidding on public works is separate from basic contractor licensure. For qualifying state or local best-bid procedures under NRS 338.1389 or 338.147, submit the Board’s valid certificate at bid and the signed NRS 338.0117 project affidavit within two hours after bid opening is complete. These state and local best-bid procedures generally apply to estimated public works costs above $250,000, subject to statutory exceptions. If the other conditions are met, the qualifying bid can be up to 5% higher than the lowest responsible and responsive bid missing either preference document. The ordinary certificate route requires a certified public accountant’s affidavit of at least $5,000 in qualifying Nevada taxes for each of five consecutive 12-month periods while licensed as required. Separate acquisition provisions also exist.
For a qualifying low non-preference bid of $420,000, the five-percent ceiling would be $441,000. A $439,000 preference bid could meet that price condition. The project affidavit requires at least 50% of workers, including subcontractor employees, to hold Nevada-issued driver’s licenses or identification cards over the project as a whole. It also addresses qualifying vehicle registration and payroll records available for inspection in Nevada. The distinct equal-qualification hiring preference under NRS 338.130 puts honorably discharged Nevada veterans first and other Nevada citizens second.
Wage Claims and the Original Contractor
NRS 624.270(6) requires the Board to order a surety bond or cash deposit after the Labor Commissioner reports three substantiated wage claims filed within two years. The Board sets the amount and term. A claim under NRS 607.165 is substantiated through the statutory determination process.
Under NRS 608.150, an original contractor can be responsible for labor indebtedness and industrial insurance obligations incurred by subcontractors on the contracted work. This is subject to the section’s limits and the notice rules of NRS 608.152. For example, when the original contractor sends a qualifying written request under NRS 608.152, the potential claimant has 90 days after receipt to provide the required written notice, basis and amount or the specified alternative information. A general contractor should check payroll records and actual coverage before treating a subcontractor’s payment or insurance issue as resolved.
A sole proprietor with no employees wants to bid for drywall work as a subcontractor to a licensed general contractor on a commercial tenant improvement. Can the sole proprietor use the exemption affidavit in NRS 624.256(1)(d) for that arrangement?
Yes, because having zero employees automatically qualifies any sole proprietor for the exemption.
No, because the NRS 624.256(1)(d) exemption affidavit is unavailable to contractors who act as or submit bids as subcontractors.
Yes, provided the general contractor signs a waiver assuming all workers' compensation liability.
Yes, as long as the subcontract value is under $10,000.
A subcontractor on a covered Nevada public work submits monthly payroll through the prime under the ordinary ten-day schedule, with no separate date agreed. Put the actions for its first month of work in order.
Arrange the items in the correct order
The subcontractor determines the applicable craft and prevailing wage before paying workers
The prime delivers the subcontractor’s complete certified payroll to the awarding public body, which must receive it within 15 days after month-end
The subcontractor sends the completed record to the prime within ten days after month-end
The subcontractor records actual hours, pay and fringe details and signs the Statement of Compliance
A licensed contractor was previously relieved of its ordinary license bond. The Labor Commissioner now reports three substantiated wage claims filed against it within two years. What must the Board do under NRS 624.270(6)?
Leave the relief in place so long as the contractor has no open workers’ compensation claim
Require security only if a fourth claim is filed within the same two-year period
Require a surety bond or cash deposit and set the amount and maintenance period
Require the firm to repay a fixed percentage of each project’s contract price instead of providing security
Sections you finish are checked off in the contents.