11.3 Nevada Payment, Retainage, Changes & Work Stoppage
Key Takeaways
For covered owner-prime progress payments, use the written schedule or the 21-day default from submission. Retention requires authorization in the agreement.
For a covered private subcontract, use the earlier of the applicable scheduled or 30-day deadline and 10 days after receipt of payment covering the request.
Final payment on covered private work depends on actual use or supported availability. Public works separately recognize recorded completion as a trigger.
Public works generally use a 30-day progress clock from receipt and 5% retention through halfway. The statute sets different rules afterward.
Give the specified written notices before exercising a stop-work or termination right. A right to stop based on an unanswered change request does not itself allow the usual 15-day termination.
Identify the Payor, Payee and Project
Nevada’s payment rules distinguish covered private owner-prime agreements, covered subcontracts and public works. NRS 624.622(4) excludes from NRS 624.609–.622 an agreement between a prime and a natural person for qualified services on that person’s single-family residence, or between a public body and a prime for a public work. Use the applicable residential or public provisions for those agreements.
Covered Private Progress and Final Payments
| Payment | Ordinary Deadline |
|---|---|
| Owner to prime for progress, NRS 624.609 | By the written schedule. If the agreement is oral or has no written schedule, within 21 days after the prime submits a payment request. |
| Higher tier to lower tier, NRS 624.624 | Earlier of the written scheduled due date or 10 days after receiving payment for all or part of the requested work or supplies. With no written schedule, substitute 30 days after the subcontractor submits the request for the scheduled date. |
| Owner to prime for remaining balance, NRS 624.620 | Within 30 days after actual occupancy or use by the owner or an authorized person, or availability for intended use supported by timely written notice or provision of a certificate or temporary certificate of occupancy. Statutory withholding and partial-use rules can affect the amount. |
The 5% retention ceilings in NRS 624.609 and .624 apply if the agreement authorizes retention. Keep retention separate from other withholding. A payor may have statutory grounds for withholding the value of unperformed work or unfurnished materials, qualified repair costs to the extent above half the retention, or specified official claims. Check the details of the applicable subsection. For the specified non-retention withholding, give the required signed, written notice on or before the due date, identifying the amount and the reasons with the relevant contract or legal references. A higher-tier contractor must also give the copies required by NRS 624.624(3). NRS 624.622 and .628 address delivery methods and copies. At private closeout the statute permits withholding on specified grounds and sets a ten-day payment-or-objection response after the owner receives a qualifying written notice of correction under NRS 624.620(4).
Payment examples. A covered commercial owner-prime agreement has no schedule and does not authorize retention. A payment request includes $78,000, of which $5,000 concerns work not yet performed. Assume the agreement does not allow billing for it and the owner gives a proper, timely notice. The owner owes $73,000 by the 21-day deadline. For a covered subcontract with a scheduled due date of July 14, assume the higher tier receives the requested payment from above on July 9. Ten days from receipt is July 19. The earlier scheduled date, July 14, controls.
Nevada Public Works
Apply NRS 338.400–.645 when applicable. Chapter 408 contracts entered into by the Nevada Department of Transportation are excluded by NRS 338.480.
- Progress, NRS 338.515: The public body generally pays within 30 days after receiving the progress bill, or sooner if the contract requires. It pays 95% and retains 5% until 50% of the work is performed. After halfway, it may stop taking additional retention and release prior amounts for satisfactory progress. If it continues to retain, the statute generally limits new retention to 2.5% and first requires release of half the earlier retention when there is no NRS 338.525 withholding. When that withholding applies, it can retain up to 5% and continue to hold earlier retention.
- Other withholding, NRS 338.525: On the grounds stated there, the public body sends signed, detailed written notice of the amount and reasons within 20 days after receiving the progress or retainage bill.
- Outstanding balance, NRS 338.520: Use the first statutory event, including occupancy or use, recorded notice of completion or partial building occupancy. Pay outstanding amounts, including applicable retainage and interest, within 30 days, proportionate to the value where only part is used or occupied.
- Subcontractors and suppliers: NRS 338.550 generally requires proportional disbursement within ten days after receipt of the public body’s money. NRS 338.555 gives a separate retention schedule for subcontracts. NRS 338.560 provides grounds and notice deadlines for other subcontract withholding.
Covered Private Work Stoppage and Changes
Under NRS 624.610 and .626, specified late payment, deficient withholding notice or good-faith written dispute with reasonable cause can allow stopping work after at least ten days’ written notice. For the designated payment or withholding grounds, the contractor or subcontractor can then give a written termination notice after stopping, at least 15 days before termination. If the amount due is paid before termination, resume work. Check the qualifying statutory paragraph, delivery and copies before applying either deadline.
NRS 624.626(1)(b) also provides a distinct stop-work ground after 45 days from the 25th day of the month in which the subcontract request was submitted, even where the stated pay-if-paid or pay-when-paid conditions exist. That ground is not one of the paragraphs listed for termination under subsection 2.
The statutes give a 30-day response rule from submission of the covered written change request. Under NRS 624.610, the owner may issue the order or provide the reasons for unreasonableness or explain the need for information and time in the cases specified. NRS 624.626 states its own requirements for the higher-tier contractor. Qualifying nonresponse can allow stopping on ten days’ notice and can trigger the statutory price and time adjustment and billing with the next payment. The unanswered change route does not by itself qualify for the ordinary 15-day termination procedure. Statutory protections against delay liability require a reasonable basis and compliance. Recovery and any attorney-fee award depend on the applicable provisions and findings.
A Nevada commercial owner and prime have a covered agreement with no written payment schedule. It expressly authorizes 5% retention. The prime submits an undisputed $86,000 request with no other withholding. What is the ordinary deadline and amount payable?
30 days from receipt and $81,700
21 days from submission and $81,700
21 days from submission and $77,400
10 days from submission and $86,000
Which statements correctly identify Nevada payment or notice triggers? Select all that apply.
Select all that apply
On a covered private prime contract, actual use by the owner can start the 30-day final-payment period under NRS 624.620.
For a covered private subcontract, the scheduled due date controls if it is earlier than ten days after the higher tier receives payment for the requested work.
A public body can withhold under NRS 338.525 for a statutory reason without giving a signed written notice.
NRS 338.525 requires written notice of withholding within 20 days after the public body receives the progress or retainage bill.
Put the events in order for a covered private subcontract where the higher tier misses a payment due under NRS 624.624(1). Assume the amount remains unpaid, all required notices are valid, and the lower tier exercises its rights under NRS 624.626(1)(a) and (2).
Arrange the items in the correct order
Higher tier misses the applicable payment deadline
After stopping work, lower tier gives written notice at least 15 days before the intended termination
Lower tier stops work after giving at least ten days’ written notice
Lower tier submits the payment request
Lower tier gives written notice that it will stop work