11.1 Contract Types & Essential Construction Clauses
Key Takeaways
Check whether the parties agreed to definite material terms, exchanged consideration and had authority to enter a lawful agreement. Apply any writing or disclosure requirements for the specific job.
A bid or contract made without the license required by NRS 624.700 is void from the beginning. Sections 624.320 and 108.222 separately govern collection actions and liens.
Fixed price, unit price, cost reimbursement and time-and-materials clauses allocate risk differently. Read the scope, reimbursable costs, ceiling, changes and savings terms together.
A delay clause defines which dates and events can trigger liquidated damages. A punitive charge is subject to challenge under Nevada law.
Use the agreed dispute and changes procedures. Default and convenience termination have different triggers and contractual remedies.
Forming an Enforceable Construction Contract
Start by identifying the work, price basis, parties and acceptance. Nevada courts look for an offer and acceptance, agreement on material terms, and consideration. A representative must have authority to bind the entity, and the agreement must have a lawful object. Check capacity and any applicable writing, signature, or disclosure rules. For example, NRS 624.970 requires written terms for covered residential improvements even though some other construction agreements may be oral.
- Offer: A defined proposal that can be accepted. A bid may constitute an offer if its language shows commitment on stated terms. An invitation for bids is ordinarily a request for proposals, and a preliminary estimate alone may lack a commitment.
- Acceptance: Assent to the offer’s material terms. A response conditioned on a different completion date or price ordinarily proposes a counteroffer for a services contract. Keep a record showing which version the parties agreed to.
- Consideration: The parties exchange legal value. The contractor’s promise to provide the work in exchange for the owner’s promise to pay is the usual construction example.
Nevada licensure. NRS 624.700(1) prohibits contracting or bidding without an active license when one is required. Under subsection 4, a bid or contract made in violation is void from inception. NRS 624.320 separately requires a contractor seeking compensation in court to plead and prove due licensure at bid and throughout performance. NRS 108.222(2) makes the required licensure a condition of the lien right. The minor-work exception in NRS 624.031 has stated conditions and exclusions, including certain trade or permit work. NAC 624.640 separately addresses a licensee who bids or contracts outside its classification or monetary limit.
Pricing and Risk
| Price Structure | Payment Basis | Risk to Check |
|---|---|---|
| Stipulated sum | One agreed price for the defined scope, subject to contract adjustments | Contractor generally bears the cost of performing that scope. Verify exclusions and price adjustment clauses. |
| Unit price | Accepted measured quantities times the agreed rates | Quantity growth can increase the total. The contractor bears the cost of producing units at the agreed rate, subject to adjustment clauses. |
| Cost reimbursement | Defined allowable cost plus the agreed fee | Check disallowed costs, approvals, records and any ceiling. The federal acquisition rules bar cost-plus-a-percentage-of-cost contracting. |
| Cost plus fee with guaranteed maximum price (GMP) | Allowable cost and fee subject to the agreed cap and adjustments | Check approved changes, contingency treatment, cost overruns and any shared-savings clause. |
| Time and materials | Agreed labor rates and allowed material charges | Hours and purchases drive the charge. Check any ceiling, materials markup and required records. |
Worked GMP. A private agreement sets a $250,000 cap, $25,000 fixed fee and a contractor share of 30% of the difference between the cap and allowable costs plus the fixed fee. At $210,000 allowable cost, the fee and cost total $235,000 before incentive. The $15,000 difference yields a $4,500 incentive, a $29,500 total fee and $239,500 payable by the owner. If allowable cost is $235,000 with the same fee and there is no adjustment, the pre-cap sum is $260,000. The owner pays $250,000, so the contractor receives $10,000 less than the uncapped cost-plus-fee calculation. The savings split reflects the stated agreement.
Clauses That Control the Job
Scope and written changes. Read the work description together with the drawings, specifications, allowances and exclusions. Use the contract’s order of precedence when documents overlap, and seek a written interpretation of an unresolved conflict through its procedures. For example, FAR 52.236-21 specifies a procedure for a discrepancy in a federal contract containing that clause. A private contract may use a different hierarchy. Identify who can authorize changes, which notices are due, and how the work is priced or directed before price is settled. A field request alone does not establish authorization.
Time and delay. A time-of-the-essence clause makes the covered times material. Read the delay and extension provisions before applying a daily liquidated-damages rate. Nevada treats a liquidated-damages clause as presumptively valid, subject to challenge as a penalty. Relevant considerations include the difficulty of estimating loss at signing, the reasonableness of the forecast, and disproportionality to the actual loss. For example, if an applicable clause imposes $500 for each of four unexcused days after extensions, the contractual calculation is $2,000, subject to enforceability.
Defense, indemnity and insurance. Identify which claims a party must defend or bear, what conduct or work triggers that duty, and whether insurance is separately required. For Nevada residential construction defect proceedings governed by NRS 40.600–.695, NRS 40.693 limits shifting a controlling party’s own negligence or intentional conduct to a subcontractor, with distinct rules for claims related to the subcontractor’s scope and for work altered by others.
Dispute and termination procedures. Mediation helps parties negotiate a voluntary settlement. Binding arbitration can produce an award subject to the limited court review provided by applicable law. Litigation is a court proceeding. Check whether the agreement or governing law requires another step first. NRS 338.150 generally requires an alternative-dispute-resolution clause for public works specifications, with a Department of Transportation exception.
A default clause identifies grounds such as abandonment or an uncured performance failure and states notice, cure and remedies. A convenience clause may permit termination without proving default. Read its notice and compensation language. An agreement may allow payment for work performed, termination-related costs and an agreed fee, as AIA A201 illustrates. Recovery depends on the agreement and applicable law.
A person with no Nevada contractor license enters a $16,000 contract to perform a bathroom remodel requiring a license. No exemption applies. After partial performance, what may that person enforce against the owner under the stated facts?
The contract is enforceable unless the owner proves defective work.
A portion of the contract can be enforced up to the minor-work threshold.
A lien can be enforced for materials even though the work required a license.
The contract is void and the contractor cannot enforce a mechanics lien for this work.
A commercial GMP contract sets a $400,000 cap and a $40,000 fixed fee. If allowable costs plus the fixed fee are below the cap, the owner keeps 60% of the resulting savings and the contractor earns 40%. Allowable costs are $330,000. What total fee does the contractor earn, including its share of savings?
$52,000
$40,000
$58,000
$70,000
Match each construction contract type or clause to its defining risk or legal rule.
Match each item on the left with the correct item on the right
Unit-Price Contract
Liquidated Damages
Termination for Convenience
Mediation