6.1 Accounting Methods & Classified Financial Statements

Key Takeaways

  • ASC 606 uses over-time revenue recognition when a performance obligation meets an over-time criterion. Use cost-to-cost as the measure only when it appropriately represents progress.

  • An earned amount still conditional on further performance is a contract asset. Amounts paid or unconditionally due before the work is transferred create a contract liability.

  • Equity equals total assets less total liabilities. A classified balance sheet separates current and noncurrent amounts.

  • Gross profit is contract revenue less its recognized cost. Operating income also deducts operating expenses outside that cost.

Last updated: November 2026

Accounting Methods & Classified Financial Statements

A contractor can perform work in November, send the bill in December, and receive cash in January. Those are different events. Use the statement and accounting basis named in the question to decide what to record at each date.

Cash, Accrual and Contract Revenue

ApproachWhat determines the timing?
Cash basisThe timing of receipt and payment generally controls reporting, subject to applicable tax and capitalization rules.
Accrual financial reportingRevenue is recognized as the applicable performance obligation is satisfied. Expense recognition depends on the nature of the cost and the period to which it belongs.
Over-time recognition under ASC 606For a performance obligation that qualifies, recognize revenue as the contractor transfers control. An input or output method can be used if it faithfully depicts progress.
Completed-contract tax methodFor eligible contracts using this method, report gross contract price and allocable costs in the completion year under the federal tax rules.

Consider a simple service contract with $90,000 in services performed and $45,000 in immediately expensed job costs paid in November. The customer pays in January. On a simplified cash basis, November has a $45,000 expense and January has a $90,000 receipt. On the stated accrual assumptions, November reflects earned revenue and job expense together, and the January payment collects the receivable. Sending an invoice alone does not establish that revenue was earned.

Recognize Revenue Over Time When the Criteria Apply

Under Financial Accounting Standards Board (FASB) Accounting Standards Codification ASC 606, recognition is over time if the customer receives and consumes the benefits as the contractor performs, if the customer controls the asset as it is created or enhanced, or if the asset has no alternative use to the contractor and the contractor has an enforceable right to payment for performance to date. Otherwise, recognize revenue when control transfers at a point in time.

A cost-to-cost measure can be appropriate when eligible costs depict performance. Estimate the total relevant cost, measure progress against that estimate, and update the estimate as circumstances change. For this simplified method:

Percent Complete=Costs Incurred to DateTotal Estimated Job Costs\text{Percent Complete} = \frac{\text{Costs Incurred to Date}}{\text{Total Estimated Job Costs}}

Suppose a Reno commercial contractor signs a fixed-price $600,000 tenant-improvement contract with $480,000 in total estimated contract costs (projecting $120,000 in gross profit, or a 20% gross margin). Assume the customer controls the asset as the work is performed and cost-to-cost fairly depicts progress. By year-end, $180,000 of eligible costs have been incurred:

  1. Calculate percent complete: $180,000$480,000=0.375\frac{\text{\textdollar}180,000}{\text{\textdollar}480,000} = 0.375 (37.5% complete).
  2. Calculate earned revenue: 0.375×$600,000=$225,0000.375 \times \text{\textdollar}600,000 = \text{\textdollar}225,000.
  3. Calculate gross profit earned: $225,000−$180,000=$45,000\text{\textdollar}225,000 - \text{\textdollar}180,000 = \text{\textdollar}45,000.

Separate Federal Tax Rules from Financial Reporting

Internal Revenue Code section 460 generally requires percentage of completion for long-term contracts within its scope, subject to exemptions that depend on contract type, taxpayer, and timing. The completed-contract method is one permitted method for exempt construction contracts. Determine completion under the tax rules. An available tax method does not change the ASC 606 financial-reporting analysis.

Earned Revenue, Billing and Collection

A work-in-progress (WIP) schedule can track contract price, cost to date, estimated total cost, earned revenue, and billings. Compare earned revenue with amounts billed and due, then record rights and obligations for the particular contract.

  • Underbilling: If earned revenue is $225,000 and billings are $195,000, the difference is $30,000. In this example, the right to the extra $30,000 still depends on a future milestone, so it is a contract asset. Once the right is unconditional, present it as a receivable.
  • Overbilling: If $250,000 has been billed and is unconditionally due against $225,000 earned, the $25,000 excess is a contract liability. This does not require collection of cash. An unpaid, unconditional billing is separately reflected in accounts receivable.

Classify these balances using the applicable current and noncurrent criteria. A billing schedule should reflect the contract and the actual status of work. Compare the WIP, receivables, and cash forecast to see how much cash is still needed to finish the work.

The Classified Balance Sheet

A Balance Sheet is a financial snapshot at a single point in time built on the fundamental accounting equation:

Assets=Liabilities+Equity (Net Worth)\text{Assets} = \text{Liabilities} + \text{Equity (Net Worth)}

Rearranged, Net Worth (also called Owner's Equity or Shareholders' Equity) equals Total Assets minus Total Liabilities. A classified Balance Sheet separates short-term from long-term items generally based on one year or the normal operating cycle, whichever is longer:

Balance Sheet CategoryClassificationTypical Nevada Contractor Accounts
Current AssetsExpected to be realized, sold or consumed in the current horizonCash, Accounts Receivable, Unconditional retainage receivable within the current horizon, Materials Inventory, Prepaid Insurance, Current portion of contract assets
Noncurrent / Fixed AssetsLong-term operating propertyService trucks, excavators, shop buildings, land, less Accumulated Depreciation
Current LiabilitiesObligations expected to be settled in the current horizonAccounts Payable, Accrued Payroll & Payroll Taxes, Short-Term Line of Credit, Current Portion of Long-Term Debt, Current portion of contract liabilities
Long-Term LiabilitiesPortion of obligations due after the current horizonMulti-year equipment notes, vehicle loans, commercial real estate mortgages
Equity / Net WorthResidual owner claimPaid-in Capital / Owner Contributions plus Retained Earnings

The Income Statement (Profit & Loss)

Unlike the Balance Sheet, an Income Statement measures financial performance over a period of time (a month, quarter, or fiscal year). Construction Income Statements separate job-site production costs from corporate overhead:

Contract Revenue−Cost of Contract Revenue=Gross Profit\text{Contract Revenue} - \text{Cost of Contract Revenue} = \text{Gross Profit} Gross Profit−Operating Expenses Outside Cost of Revenue=Operating Income\text{Gross Profit} - \text{Operating Expenses Outside Cost of Revenue} = \text{Operating Income}
  • Cost of contract revenue includes job costs recognized for the period, such as materials, field labor and subcontractor services. Its composition can include appropriate allocated job costs beyond the direct tasks.
  • General & Administrative (G&A) Overhead includes company support expenses such as: office rent, estimator and bookkeeper salaries, general liability insurance, office utilities, and marketing.

To compute gross profit in a statement exercise, use the stated cost of revenue. Deduct the operating expenses outside that cost to determine operating income. Net income can also reflect other income or expenses and taxes.

FASB Topic 606, paragraphs 25, 45, and 55 · IRS Revenue Procedure 2026-32 · 26 CFR 1.460-4 · Classified statements and working capital

Loading diagram...
How Construction Income Statements & WIP Adjustments Flow to the Balance Sheet
Test Your Knowledge

For one contract, $310,000 has been billed and is unconditionally due. The contractor has earned $275,000 under the over-time method. Assume the difference is expected to be settled within the operating cycle. How does the contractor classify the $35,000 excess billing?

A

Current contract liability (overbilling)

B

Current Asset as Costs and Estimated Earnings in Excess of Billings (Underbilling)

C

Noncurrent Asset as Deferred Contract Revenue

D

Direct Job Cost reduction on the Income Statement

Test Your Knowledge
Multi-Select

Which TWO of the following items are classified as Direct Job Costs (rather than General & Administrative overhead) when calculating Gross Profit on a construction Income Statement?

Select all that apply

Wages and payroll taxes for job-site framing carpenters

Monthly rent for the contractor's corporate headquarters office

Subcontractor invoices for electrical rough-in on a specific project

Annual salary of the company's full-time receptionist

Test Your Knowledge

A Henderson contractor has an $800,000 fixed-price contract with $640,000 in total estimated contract costs. The contract qualifies for over-time recognition with cost-to-cost as the progress measure. At year-end, $256,000 in eligible costs have been incurred. Using the percentage-of-completion cost-to-cost method, how much Gross Profit has been earned to date?

A

$160,000

B

$128,000

C

$96,000

D

$64,000