10.1 Critical Path Scheduling, Early and Late Dates & Float
Key Takeaways
A Gantt chart presents activities as bars over time. A logic-linked Critical Path Method schedule uses relationships to calculate dates, identify driving paths and test the effect of changes.
In a simple finish-to-start network with no overriding constraints, a longest path drives the earliest finish and carries zero total float. Several paths may tie.
For the stated single-calendar example, total float equals Late Start minus Early Start or Late Finish minus Early Finish.
For finish-to-start links without lag, free float is the gap from the activity’s early finish to the earliest immediate successor’s early start.
Crashing adds resources to shorten driving work. Fast-tracking overlaps work where technically feasible. Recalculate the finish and check other driving paths after each change.
Bar Charts and Logic-Linked Schedules
A Gantt bar chart shows when a crew or delivery is scheduled, how long it lasts and which operations overlap. A simple chart without dependencies is useful for a field look-ahead. A scheduling application may display a logic-linked schedule in the same bar-chart view.
The Critical Path Method (CPM) uses activity durations, calendars and dependency relationships to identify the sequence driving a finish milestone. In an activity-on-node (AON) network, arrows show the dependencies between activities. A finish-to-start link lets a successor start after its predecessor finishes, with any specified lag. Start-to-start and finish-to-finish links have different timing rules. A little bar overlap alone cannot show which project milestone a delay will move.
Forward Pass, Backward Pass & The Critical Path
The calculation below uses Day 0, one shared calendar, finish-to-start links with zero lag, sufficient resources, one final milestone, and no outside date constraints. Calculate four dates for each activity.
- Early Start (): Earliest day an activity can begin once all predecessors finish: .
- Early Finish (): Earliest day an activity can finish: .
- Late Finish (): Latest day an activity can finish without delaying project completion: .
- Late Start (): Latest day an activity can begin without delaying project completion: .
How the Two Passes Work
- Forward Pass (Left to Right): Start at Day 0 and compute and for every node. Whenever two or more predecessor paths merge into one activity, take the largest (latest) among those predecessors as the new . The largest at the final activity establishes the minimum total project duration.
- Backward Pass (Right to Left): Set the final activity's equal to the project completion day and subtract durations back toward Day 0. Whenever an activity feeds multiple successors (a burst point), take the smallest (earliest) among those successors as the activity's .
In this network, the critical path is the longest sequence of dependent activities to the finish milestone. Its activities have zero total float. A one-day delay on this path moves the finish one day if no recovery or logic change occurs. A shorter path can tie when it uses all its float and can overtake the former longest path if it slips farther.
A live schedule can have multiple driving paths, and float depends on the milestone, calendars, dependencies and constraints. An imposed finish earlier than the calculated finish can produce negative total float. Use the driving logic to diagnose a delay before relying on a zero-float flag or treating the schedule alone as proof of responsibility.
Total Float vs. Free Float (Worked CPM Example)
Calculate two kinds of float in this simple finish-to-start network.
- Total Float (): The maximum number of days an activity can be delayed from its Early Start without delaying final project completion.
- Free Float (): The maximum number of days an activity can be delayed without delaying the Early Start of any immediate successor. In this unconstrained example, free float cannot exceed total float.
Worked Project Network: 25-Day Tenant Build-Out
Consider a five-activity commercial tenant build-out scheduled in continuous workdays starting at Day 0:
| Activity | Description | Predecessors | Duration | Total Float () | Critical? | ||||
|---|---|---|---|---|---|---|---|---|---|
| A | Mobilization & Permits | None | 4 days | 0 | 4 | 0 | 4 | 0 days | Yes |
| B | Underground & Slab | A | 6 days | 4 | 10 | 4 | 10 | 0 days | Yes |
| C | Framing & Mechanical, Electrical and Plumbing (MEP) Rough-In | B | 10 days | 10 | 20 | 10 | 20 | 0 days | Yes |
| D | Site Paving & Curb | B | 5 days | 10 | 15 | 15 | 20 | 5 days | No |
| E | Finishes & Final Inspection | C, D | 5 days | 20 | 25 | 20 | 25 | 0 days | Yes |
Tracing the two paths from Activity B to Activity E:
- Critical Path (): . Every activity on this path has , so .
- Activity D (Site Paving & Curb): Activity B finishes on Day 10, so D can start on Day 10 and finish on Day 15. E waits for C until Day 20, so D can finish as late as Day 20 and start as late as Day 15.
D can start as late as Day 15 without delaying the Day 25 finish. Because its immediate successor E has an early start of Day 20, D’s free float is also days.
Important
Why Free Float Often Differs from Total Float: Sequential activities can display the same shared margin. Spending float on one can leave less for the activities following it. Suppose two sequential non-critical tasks X () and Y () share 5 days of path float before rejoining the critical path at Day 17 (). Both X and Y show days, yet X's Free Float is . If X slips by 3 days, X delays Y's Early Start to Day 11 and leaves Y with only 2 days of remaining total float.
Schedule Compression: Crashing vs. Fast-Tracking
Schedule compression changes actual work plans. Confirm which paths drive the target milestone before spending money or overlapping activities.
- Crashing adds resources such as a second crew, extra equipment or an expedited delivery to reduce an activity’s duration. Compare incremental cost per day against the finish date actually gained. A cheaper activity on only one of two equally long paths may produce no improvement unless the other path is shortened as well.
- Fast-tracking overlaps activities that would otherwise be sequential. Releasing shop drawings and fabrication by independently approved zones can allow work in one area while another area is still under review. Check the dependencies and required approvals, and plan for trade interference, rework and coordination risk.
Update the network and look for the next driving path after either change.
In a finish-to-start CPM schedule with one calendar and no imposed finish constraint, an HVAC activity has Early Start Day 8, Early Finish Day 14, Late Start Day 13 and Late Finish Day 19. A backorder moves its start from Day 8 to Day 15 without changing its duration or any other inputs. How much later is overall completion?
7 days, because every delayed trade activity pushes the completion date day-for-day
5 days, equal to the activity's total float before the backorder occurred
2 days, because the first 5 days of delay consume total float and the remaining 2 days extend the critical path
0 days, because non-critical activities can never affect final project completion
Which statements accurately distinguish scheduling tools and compression techniques? (Select all that apply.)
Select all that apply
Crashing shortens driving activities by adding resources such as labor or equipment, typically increasing direct cost.
Crashing a non-critical activity with 8 days of total float shortens the total project duration
A standalone Gantt bar chart performs forward-pass and backward-pass math automatically without dependency logic
Fast-tracking overlaps normally sequential critical activities and increases the risk of coordination errors and rework
In a single-calendar CPM network, an activity has Early Start Day 12, duration five days and Late Finish Day 24. What is its total float in days? Enter a whole number.