11.2 Nevada Residential-Improvement Contract Mandates (NRS 624.970)
Key Takeaways
NRS 624.970 applies to covered improvement work on a completed single-family residence occupied by its owner. Pools, spas, residential photovoltaic work and new-home construction have separate rules.
The deposit limit is the lesser of $1,000 or 10% of the price, subject to the filed $100,000 consumer-protection bond or Board-granted relief under NRS 624.270(5).
A full payment-and-performance bond included in the project price is a separate exception to the progress schedule and earned-value rule.
The residential contractor obtains required permits and furnishes legible copies of signed documents and a signed receipt for money paid at signing.
Document scope and price changes in an owner-accepted written change order. Chapter 624 rights and duties cannot be waived by the contract.
Identify Which Residential Contract Rule Applies
NRS 624.970 applies from October 1, 2023 to contracts between a residential contractor and the occupying owner of a completed single-family residence for covered construction, remodeling, repairs, improvement or supervision. A kitchen addition or roof repair can come within the statute. Residential pool and spa work follows NRS 624.900–.965, and covered residential photovoltaic work follows NRS 624.830–.895. A licensee completing a new single-family home has a purchaser-disclosure and warranty duty under NRS 624.602. Identify the work and owner before relying on any payment exception.
Required Contract Terms and Signing
| Topic | What the Covered Written Contract Contains |
|---|---|
| Contractor, owner and property | Contractor name, address, license number and monetary limit; owner name and mailing address; property address or legal description |
| Dates and work | Execution date, estimated completion date for all work, and a description of the work |
| Money | Total price including applicable taxes, applicable deposit terms, and each required progress payment in dollars and cents tied to a construction stage |
| Notices and changes | Statement that the NRS 624.520 notice and NRS 624.600 form have been provided, and that scope or price changes require written agreement and incorporation as change orders |
| New work or salesperson commission | Required plan, scale drawing and construction details for a project of new work, and the pro rata payment statement if a salesperson’s commission is paid from the contract price |
NRS 624.970(2)(j) exempts projects consisting exclusively of repairs to existing work from the specified plans, drawings, equipment specifications and lists. Use NAC 624.012 and .013 to identify new work and repairs. A kitchen remodel changing cabinets and plumbing can be new work even though the house already exists. A repair-only contract still needs a work description and the other applicable terms.
The contract must allow the owner to initial provisions to show they were read and understood. Near the signatures, include the statutory notice about contacting the Board or an attorney, requesting a payment-and-performance bond when applicable, and asking for a contract in the language used to explain it. At signing, furnish legible copies of all signed documents and a written, signed receipt for money paid. Written contract information must be in at least ten-point bold type. The documents and receipt may be delivered electronically.
Disclosures. NRS 624.520 covers the Residential Recovery Fund notice. Under NRS 624.600, a general building contractor provides the required contact and license details for all contracted subcontractors and persons furnishing at least $500 in materials, plus the statutory lien notice and Board form. The $500 threshold in this section applies to material furnishers.
Deposit and Progress Payments
| Rule | Ordinary Limit | Exception Under NRS 624.970 |
|---|---|---|
| Initial deposit paid or promised before work starts, subsection (2)(g) | Lesser of $1,000 or 10% of aggregate contract price | A $100,000 bond filed with the Board solely to protect consumers, or Board-granted relief under NRS 624.270(5) |
| Progress schedule and receipts, subsection (2)(k) | No more than 100% of the value of work performed, excluding financing charges and the initial deposit | Full contract payment-and-performance bond furnished, with its cost included in the project price |
A payment-and-performance bond under subsection (2)(k) does not by itself remove the deposit cap in subsection (2)(g). A contractor with Board-granted bond relief still checks the progress-payment rule separately.
Deposit example. For a covered $7,250 repair, 10% is $725 and the limit is $725. For a covered $26,000 remodel, 10% is $2,600 and the $1,000 cap controls, assuming no deposit exception.
Progress example. A $46,000 covered addition has a lawful $1,000 deposit. The contractor has performed $16,000 of work and already received $6,000 in later progress payments. With no subsection (2)(k) exception or finance charges, cumulative receipts may be at most $17,000 including the deposit. The current progress draw therefore cannot exceed $10,000 under the statutory ceiling. The amount actually due can be lower under the agreed schedule.
Permits, Changes and Enforcement
The contractor must apply for and obtain all necessary permits. Under NRS 624.510(2)(d), a claimant who applied for and obtained a permit for the residence at issue, or constructed that residence as owner-builder, is excluded from Recovery Fund payment. The statutory exclusions and the contractor’s permit duty are separate.
A change order for scope or price must state all changes in scope and price, be agreed to in writing, and be accepted by the owner to be enforceable against them. Incorporate it in the original contract’s change-order record. A waiver of statutory protections or a term relieving a duty imposed by Chapter 624 or its regulations is void. A noncompliant deposit term makes the contract voidable by the owner under subsection (1)(b). For other subsection (2) deficiencies and applicable Board regulations, subsection (1)(a) allows the owner to bring the contract into compliance by reasonable modification enforceable against the contractor.
An occupying owner signs a covered $8,400 bath remodel contract. The contractor has a full payment-and-performance bond included in the project price, but has neither the filed consumer-protection bond nor Board-granted relief. What is the maximum initial deposit in dollars? Enter digits only.
Type your answer below
On a covered $52,000 residential addition, the owner paid a lawful $1,000 deposit and $5,000 in prior progress payments. Completed work is now worth $14,500. Assuming no finance charges or progress-payment exception, what is the maximum additional progress draw under the statutory ceiling?
$14,500
$10,500
$9,500
$15,500
Which statements apply to covered NRS 624.970 improvements or the related Recovery Fund eligibility rule? Select all that apply.
Select all that apply
At signing the contractor furnishes legible copies of all signed documents and a written, signed receipt for money paid.
An initialed provision can waive any of the owner’s Chapter 624 protections.
A claimant who applied for and obtained a building permit for the residence at issue is excluded from the Recovery Fund under NRS 624.510(2)(d).
A change order must set out the scope and price changes and be accepted by the owner, with changes agreed in writing.