5.1 Notice of Right to Lien (NRS 108.245) & 15-Day Residential Notice of Intent

Key Takeaways

  • NRS 108.222 makes required licensure a condition of a mechanic’s lien and generally bases the lien on the unpaid agreed price or, where no price or pricing method was agreed, fair market value.

  • Under NRS 108.245, a claimant required to give a Notice of Right to Lien serves the owner in person or by certified mail. A subcontractor or equipment or material supplier giving notice also sends an informational copy to the prime contractor.

  • A subcontractor that omits the prime contractor copy can face Board discipline. The omission does not invalidate the notice to the owner.

  • NRS 108.245 protects covered work, materials and equipment from the 31 days preceding notice and through later furnishing on the work of improvement.

  • NRS 108.226(6) generally requires residential lien claimants, except laborers, to give a 15-day Notice of Intent to Lien to the owner and reputed prime contractor. Proper service extends the recording period by 15 days.

Last updated: November 2026

Nevada Notices Before Recording a Construction Lien

Work a lien problem in order. First ask whether the claimant qualifies. Then identify the notice it must give, who gets it, and what the notice does to the claim. The Notice of Right to Lien and the residential Notice of Intent to Lien have different purposes and time rules.

Establish a Lienable Claim and Amount

Under Nevada Revised Statutes (NRS) 108.222, a mechanic’s lien can attach to the property and improvements for covered work, materials or equipment furnished at the instance of the owner or the owner’s agent. NRS 108.2214 defines a lien claimant as someone providing at least $500 in qualifying work, materials or equipment for the improvement. It can also reach an applicable construction disbursement account. A contractor or professional who must hold a license for that work only has the lien if licensed to perform it. A claimant that acted without a required contractor license also faces the separate void-contract rule in NRS 624.700.

When the parties agreed on a specific price or a way to determine it, start with the unpaid balance of that agreed price for the covered work, materials or equipment. In the absence of an agreement on price or a pricing method, the statute uses fair market value, including a reasonable allowance for overhead and profit. Check what was supplied, what was paid, and whether the notice timing cuts off an earlier delivery before relying on an invoice balance.

Give the Notice of Right to Lien to the Owner

NRS 108.245 requires most eligible lien claimants without a direct owner contract to give the property owner a Notice of Right to Lien after first furnishing. The statute excepts a person who performs only labor or is a potential claimant under NRS 608.150. A prime contractor or other person who contracts directly with the owner, or a person selling materials directly to the owner, is exempt from this notice. A material supplier selling to a subcontractor on credit normally gives notice to the property owner.

  • Give the owner the notice in person or by certified mail. Identify the property, the contracting party, the general nature of what you furnished, and the possibility of a later lien, using substantially the statutory form.
  • A subcontractor or equipment or material supplier that gives the owner notice also delivers a copy to the prime contractor in person or by certified mail. The copy is for information.
  • A subcontractor’s failure to give the prime contractor copy is a ground for Nevada State Contractors Board discipline. It does not invalidate the notice to the owner. The preliminary notice itself is neither a recorded lien nor a substitute for recording.

Calculate the 31-Day Lookback

Suppose a licensed heating and air-conditioning subcontractor first furnishes work March 1 and gives the property owner a proper notice in person on April 15. April 15 minus 31 days is March 15. Apply the statutory window to the work, assuming it is otherwise lienable and unpaid.

Work furnishedUnpaid amountIncluded in the lookback and later work?
March 1–14$14,000No. It predates March 15.
March 15–31$17,000Yes. It falls within the preceding 31 days.
April 1–30$24,000Yes. It falls within the lookback or after notice.

The notice preserves up to $41,000 in this example, before considering any other perfection requirements. An earlier notice within 31 days of the first covered work could have preserved the March 1–14 work as well. The 31-day limit concerns what the statutory lien can secure. It does not decide every possible contract claim between the subcontractor and its customer.

Use the Separate 15-Day Residential Notice Before Recording

On a work of improvement involving construction, alteration or repair of a single-family or multifamily residence, NRS 108.226(6) requires a lien claimant, except laborers, to serve a 15-day Notice of Intent to Lien. It includes substantially the same information as the Notice of Lien. Deliver it personally or by certified mail to the owner and reputed prime contractor. Give the required notice before recording, allow the 15-day period, and apply the 15-day extension to the otherwise applicable recording deadline under NRS 108.226(1). The exception from the Notice of Right to Lien for a prime contractor with a direct owner contract does not carry over to this residential requirement.

On a covered single-family project, the general building contractor’s written disclosures under NRS 624.600 are another distinct duty. They include the Board’s informational form, a lien warning, and details of the subcontractors it has contracted with and persons furnishing $500 or more in materials. The general contractor's written disclosures do not complete a claimant's notices.

Nevada lien statutes, including NRS 108.222, 108.226 and 108.245 · Nevada contractor licensing and residential disclosures

Loading diagram...
Nevada Pre-Lien Notice Decision Flow (NRS Chapter 108)
Test Your Knowledge

A licensed plumbing subcontractor first furnishes piping to a commercial project May 1. On June 16 it delivers a proper Notice of Right to Lien in person to the owner. What work can the notice cover if the other lien requirements are satisfied?

A

None of the work, because missing the 31-day window permanently forfeits all lien rights on the project

B

Otherwise lienable work and materials furnished from May 16 onward through completion

C

100% of the work back to May 1, provided the subcontractor records the lien within 90 days of completion

D

Only labor and materials furnished after June 16, because Nevada does not permit any retroactive look-back

Test Your Knowledge
Multi-Select

Which statements accurately describe the 15-Day Notice of Intent to Lien under NRS 108.226(6)? (Select all that apply.)

Select all that apply

The requirement applies to covered single-family or multifamily residential work, with laborers excepted.

Prime contractors who contracted directly with a residential owner are exempt from serving it

It must be served by personal delivery or certified mail on both the property owner and the reputed prime contractor

Serving the notice extends the statutory deadline for recording the Notice of Lien by 15 days

Test Your Knowledge

An electrical subcontractor serves a timely Notice of Right to Lien on the property owner by certified mail, but forgets to send an informational copy to the prime contractor. What is the legal consequence under Nevada law?

A

The subcontractor's lien is automatically void against the property owner and cannot be recorded

B

The subcontractor's 90-day recording window is shortened to 40 days

C

The subcontractor is protected for 100% of work with no legal or regulatory consequences

D

The owner’s notice remains valid, and the omission is grounds for Board discipline against the subcontractor.