5.2 Lien Recording Deadlines (90/40 Days), Service & 6-Month Foreclosure

Key Takeaways

  • Under NRS 108.226(1), use 90 days from the latest qualifying event or 40 days from recording of a valid Notice of Completion recorded and served as required by NRS 108.228.

  • Proper service of the residential 15-day Notice of Intent extends the otherwise applicable recording period by 15 days.

  • NRS 108.227 requires service of the recorded notice on the owner within 30 days. A subcontractor also delivers a copy to the prime contractor under subsection 3.

  • Foreclosure generally must be commenced within six months of recording and after the initial 30-day waiting period. A written, recorded extension under NRS 108.233 can preserve the lien only as to signing interests and for no more than one year after original recording.

  • NRS 108.2457 provides four payment waiver forms. A recorded lien can be bonded off under NRS 108.2415(1) with a bond equal to 150% of the lienable amount in the notice.

Last updated: November 2026

Recording, Serving and Enforcing a Nevada Lien

A construction lien problem can involve several dates: completion, last furnishing, recording, service and filing suit. Write down each event before counting. The date that starts the recording period may differ from the date that starts the foreclosure period.

Calculate the Recording Deadline

Under Nevada Revised Statutes (NRS) 108.226(1), record a verified Notice of Lien in the county where all or part of the property is located. For the 90-day rule, take the latest of completion of the work of improvement, the claimant’s last material delivery or furnishing of equipment, and the claimant’s last work on that improvement. If there is a valid Notice of Completion recorded and served as required in NRS 108.228, the alternative recording period is 40 days from recording of that notice.

A Notice of Completion is recorded by the owner after completion. Within 10 days after recording, the owner delivers a copy by certified mail to each prime contractor with whom the owner contracted and each potential claimant who gave a Notice of Right to Lien or requested the Notice of Completion before recording. Failure to deliver a required copy on time and in the prescribed manner makes the shorter deadline ineffective as to the affected party. The owner’s recording date alone does not settle the question.

The claimant’s own Notice of Lien uses substantially the statutory form and gives the lienable amount after credits and offsets, the owner’s name if known, the identity of the hiring party or recipient of materials or equipment, payment terms, and a sufficient property description. It must be verified by oath. For a covered residential lien, proper service of the separate 15-day Notice of Intent extends the applicable recording period by 15 days, yielding a 105-day or 55-day period measured from its corresponding trigger.

Worked example. A homeowner records a valid Notice of Completion on June 5, after completion, and delivers the required copies by certified mail within ten days. Forty days from June 5 is July 15. A roofing subcontractor who properly serves the owner and reputed prime contractor with the residential Notice of Intent in person on June 28 adds 15 days to the recording period. July 13 is 15 days from June 28, and July 30 is 55 days from June 5. Those dates mark the end of the notice waiting period and the extended recording deadline in the example.

Serve the Recorded Notice, Then Track Any Foreclosure

NRS 108.227 requires service on the owner within 30 days after recording. Use personal delivery to the owner or registered agent, certified mail with return receipt requested, or the statutory posting, delivery and mailing procedure when the relevant addresses cannot be determined. A subcontractor also delivers a copy to the prime contractor under subsection 3. Omitting that copy is a ground for Board discipline. Subsection 3 has its own requirement, separate from the owner service rule and deadline in subsection 1.

NRS 108.233 generally limits how long the lien binds the property to six months from recording unless an enforcement proceeding starts or a qualifying extension is recorded. NRS 108.244 generally prohibits filing a foreclosure complaint until thirty days after recording have expired. File in a court of competent jurisdiction in the county where the work of improvement is located, file a notice of pendency when filing the complaint and issuing the summons, and arrange publication of the foreclosure notice under NRS 108.239. A written extension must be signed by the claimant and the affected interests, properly acknowledged and recorded within the initial six months. It affects only signing interests and may extend no later than one year from original recording. A second extension is unavailable.

Choose the Statutory Waiver or the Right Release Bond

An advance contract term that impairs lien rights is void under NRS 108.2457. For waivers in exchange for payment, match the statutory form to both the stage of billing and the payment status.

Billing stage and payment statusForm and effect
Progress payment is pending or a check has yet to be paid by the bankConditional progress. It takes effect on payment under the form and excludes specified items such as retainage and disputed claims.
Part or all of the progress bill has been paidUnconditional progress. Use it for the amount paid and the covered billing.
Final payment is pending or a check has yet to be paid by the bankConditional final. It becomes effective on payment and excludes identified disputed claims.
Final billing has been paidUnconditional final. It releases the listed rights as described in the form, except identified disputed claims.

NRS 108.2415(1) permits a surety bond of 1.5 times the lienable amount to release property from a recorded lien. A $40,000 lien calls for a $60,000 bond. For a bond covering all existing and prospective liens under a prime contract, subsection 2 instead uses 1.5 times the prime contract amount. Follow the applicable recording and service rules so the bond replaces the property as security. If a recorded lien is instead fully satisfied or discharged, NRS 108.2437 requires the claimant to record a discharge or release as soon as practicable and within ten days.

Nevada lien statutes, including NRS 108.226–.239 and 108.2415–.2457

Loading diagram...
Nevada Mechanics Lien Lifecycle: Recording to Foreclosure or Release
Test Your Knowledge

A commercial property owner records a Notice of Completion on October 1 but sends a copy by certified mail to a subcontractor on October 18. The subcontractor gave the owner a proper Notice of Right to Lien before October 1. Which recording period applies to that subcontractor?

A

The usual 90 days from the latest qualifying event in NRS 108.226(1)(a)

B

40 days from October 1, because recording the Notice of Completion always shortens the deadline

C

55 days from October 1, because late service grants an automatic 15-day extension

D

30 days from October 18, measured from the date the subcontractor received the mail

Test Your Knowledge
Ordering

A Nevada commercial subcontractor without a direct owner contract wants to preserve its lien on all furnished materials and, if unpaid, foreclose once the lien is perfected. Put these steps in order.

Arrange the items in the correct order

1

Record the verified Notice of Lien in the appropriate county within the applicable statutory period

2

After the 30-day waiting period and within six months of recording, commence foreclosure and file a notice of pendency if no extension applies

3

Serve the recorded notice on the owner within 30 days and give the prime contractor a copy

4

Give the owner a Notice of Right to Lien within 31 days of first furnishing and send the prime contractor an informational copy

Test Your Knowledge

A subcontractor records a valid Nevada lien for $64,000 against a commercial retail center. What is the bond amount under NRS 108.2415(1) to release the property from this particular lien?

A

$64,000 (100% of the lienable amount)

B

$80,000 (125% of the lienable amount)

C

$96,000 (150% of the lienable amount)

D

$128,000 (200% of the lienable amount)