16.1 The Construction Team: Site Management, Trades & Site Visitors

Key Takeaways

  • The site management team in the Unit 210 range includes the architect, project manager or clerk of works, structural engineer, surveyor, building services engineer, quantity surveyor, buyer, estimator, contracts manager and construction manager.

  • The quantity surveyor measures and values work and variations, the estimator prices work for tenders and quotations, and the buyer orders materials.

  • Trades such as groundworkers, bricklayers, joiners, plasterers, tilers, heating and ventilating fitters, gas fitters and decorators must be coordinated with electrical first and second fix.

  • Site visitors include building control inspectors (Building Regulations), water inspectors, HSE inspectors and electrical services inspectors, and they must sign in and follow site rules.

Last updated: October 2026

16.1 The Construction Team: Site Management, Trades & Site Visitors

Unit 210 (Understand how to communicate with others within building services engineering) is a 20-question, 40-minute test. Learning outcome 1 (5 questions) asks you to identify the key roles of the site management team, the people who report to that team, and site visitors. Knowing who does what tells you whom to ask, whom to report to and whose work affects yours.


The Site Management Team

RoleWhat they doWhy it matters to the electrician
ArchitectDesigns the building's layout and appearance, prepares drawings and specifications, and may administer the building contractProduces the layout drawings; architect's instructions can change (vary) your work
Project managerPlans and controls the whole project: time, cost, quality and coordination of everyone involvedSets the programme and resolves clashes between trades
Clerk of worksThe client's on-site inspector, checking workmanship and materials against the drawings and specificationInspects your installation and records any defects for you to put right
Structural engineerDesigns foundations, frames, beams and other load-bearing parts of the buildingMust approve any cutting or drilling of structural members beyond normal limits
SurveyorMeasures and assesses land and buildings, sets out the site and reports on the condition of existing buildingsProvides surveys, levels and information on existing structures
Building services engineerDesigns the mechanical and electrical services: power, lighting, heating, ventilation and waterProduces the electrical drawings, schedules and specifications you install from
Quantity surveyorMeasures quantities, prepares bills of quantities, and manages costs, valuations and variationsValues the work you complete and agrees the cost of changes
BuyerOrders materials and equipment at the best price and arranges deliveriesMaterials must be ordered in time to keep to the programme
EstimatorCalculates the cost of a job (materials, labour and plant) to prepare a tender or quotationAccurate estimates make work profitable for your company
Contracts managerManages one or more contracts for the contractor, overseeing supervisors, budgets and programmes across sitesYour company's link between the site and the office
Construction (site) managerRuns the site day to day: safety, programme, trades, site rules and inductionsGives inductions, site rules and permits, and coordinates access to work areas

People Who Report to the Site Management Team

  • Sub-contractors: specialist firms employed by the main contractor, such as the electrical contractor, scaffolders and plasterers.
  • Site supervisor: manages the workforce on a site or part of it.
  • Trade supervisor: for example the electrical supervisor or chargehand, who allocates the electricians' work and checks its quality.
  • Trades: the skilled operatives listed below.
TradeWhat they doCoordination with the electrician
Ground workersExcavation, foundations, drainage and service trenchesLay ducts for incoming supplies and external cables before the ground is closed
BricklayerBuilds walls and blockworkCan build in boxes and conduits as walls go up, which saves chasing later
Joiner (carpenter)Floors, roofs, stud walls, doors and boxing-inCoordinate notching and drilling of joists and studs, and access traps
PlastererPlastering and dry-liningFirst fix must be complete (and buried cables checked) before boards and plaster cover them
TilerWall and floor tilingAgree box positions so accessories sit neatly within the tiling
ElectricianElectrical installation, inspection and testingCoordinates with all the others
Heating and ventilating (H&V) fitterHeating, ventilation and air conditioning systemsControls wiring, supplies to plant, and bonding where required
Gas fitterGas pipework and appliances (must be Gas Safe registered)Keep electrical services apart from gas pipes; main bonding of metallic gas pipes
DecoratorPainting and finishingSecond fix accessories are usually fitted after decorating, or must be protected

A typical sequence on a new building is shown below. Delays or mistakes by one trade affect every trade that follows, which is why the programme and good communication matter so much.

Loading diagram...
Typical Order of Trades on a New Building

Site Visitors

VisitorWhat they check
Building control inspector (local authority or registered approved inspector)That the work complies with the Building Regulations, including Part P electrical work where it has not been self-certified through a competent person scheme
Water inspector (from the water supplier)That plumbing and water fittings comply with the water fittings regulations, for example backflow prevention
HSE inspectorCompliance with health and safety law; they can investigate accidents and serve improvement or prohibition notices
Electrical services inspectorThe electrical work itself, for example an assessor from a certification body or competent person scheme, or an inspector acting for the client

All visitors must sign in, receive a site induction, wear the required PPE and normally be escorted. Treat them courteously, answer their questions accurately within your knowledge, and refer anything you cannot answer to your supervisor.


The Client and the Principal Contractor

The client commissions and pays for the project. Under CDM 2015 the client appoints a principal designer and a principal contractor on projects with more than one contractor (Section 2.1). The principal contractor plans, manages and coordinates the construction phase, and the electrical contractor usually works for the principal contractor as a sub-contractor.

Tip

Test questions often describe a task and ask which person does it. Remember: the quantity surveyor measures and values, the estimator prices, the buyer orders, the clerk of works inspects for the client, and building control checks the Building Regulations.

Test Your Knowledge

Which member of the site management team measures and values the work, including the cost of variations?

A

Quantity surveyor

B

Architect

C

Clerk of works

D

Buyer

Test Your Knowledge

Who prices a job by calculating the cost of materials, labour and plant before a tender or quotation is submitted?

A

Construction manager

B

Estimator

C

Plasterer

D

Water inspector

Test Your Knowledge

Which site visitor checks that building work complies with the Building Regulations?

A

HSE inspector (Health and Safety Executive)

B

Water inspector from the water supplier

C

Building control inspector

D

Buyer

Test Your Knowledge

Why should electrical first fix normally be complete, and buried cables checked, before the plasterer starts?

A

Plasterers need the permanent lights to work by

B

It is required by the water fittings regulations

C

So that the plasterer can sign the Electrical Installation Certificate

D

Because the plaster will conceal the cables and boxes, making later changes difficult and costly