Shaft Enclosures and Rated Horizontal Assemblies
Key Takeaways
Count connected stories, including basements.
Do not count mezzanines for shaft rating.
Check the penetrated floor rating.
Verify the opening protection separately.
Use the actual firestop listing.
Count the stories the shaft connects
Section 713.4 generally requires a 2-hour rating when a shaft connects at least four stories and 1 hour when it connects fewer than four. Include connected basements and exclude mezzanines for that count. The enclosure also must meet the rating of the floor penetrated up to the section's 2-hour cap, subject to the listed exceptions. Do not use the building’s total story count if the shaft does not connect all stories.
A vertical opening does not always have to be a shaft. Check §712 for openings permitted by other methods and whether the approved design actually meets their conditions. Do not classify a utility opening as an atrium or a permitted unenclosed stair opening merely because it is shown open in an architectural view.
Inspect the full separation
Horizontal assemblies may be rated because of Table 601 or because the code requires a particular separation. Compare the assembly listing with the installed deck, framing, ceiling membrane and supporting construction. Check the protection for penetrations, joints and openings before the underside is concealed.
At a four-story service shaft, start by identifying rated floor lines on the section and shaft-wall details. Check the access door assembly and each opening for its permitted function. A new cable that fits through an existing sleeve can still change the installed firestop system. Verify the tested configuration for the sleeve and cable, and document any missing protection with a detail or listing reference so the trade can correct it.
A shaft connects three stories above grade and one basement. What is the general minimum enclosure rating?
2 hours
½ hour
1 hour
3 hours
Which level is excluded from the §713.4 connected-story count?
A mezzanine
A basement
The first story above grade
An occupied fourth story
What should be checked before adding a cable through an existing rated-floor sleeve?
The tested system for that sleeve and cable combination
Only the floor finish specification
Only the shaft door label
The exterior wall opening limit