Permits, Inspections and Certificates of Occupancy
Key Takeaways
Confirm permit scope and current plan revision.
Check before work is concealed.
Record the exact location and correction required.
Document alternatives and modifications separately.
Verify certificate conditions before occupancy.
Check the permit and approved work
Section 105 generally requires a permit before covered construction or alterations begin. Section 105.2 identifies exempt work; an exemption from a permit does not authorize code violations. Compare the scope, location and approved drawings with what is being built. On plans, check the sheet number, revision, detail callout and where the detail applies before comparing it with field work.
A proposed alternative and a modification are different administrative paths. In the 2024 IBC, §104.2.3 addresses alternatives and §104.2.4 modifications. In the 2021 IBC, those are §104.11 and §104.10, respectively. Do not substitute an informal field approval for the required review and documentation.
Record the inspection and close it out
Section 110 covers inspections and their sequence. Verify footing and foundation work before it is concealed; coordinate any required special inspections without treating them as a substitute for the building official's inspection. A correction notice should identify the location, approved plan or applicable provision, observed discrepancy and condition for reinspection. For example, document a missing hold-down by grid line and detail callout rather than writing only “framing incomplete.”
Section 111 governs certificates of occupancy. It generally requires approval before use or a change of occupancy, and permits temporary occupancy under specified conditions. Verify any limitations and outstanding conditions. Issuing a certificate does not authorize a violation.
Which 2024 section addresses approval of an alternative material or method?
§104.2.3
§104.2.4
§105.2
§111.3
What should an inspection correction identify?
The observed discrepancy, location and applicable requirement
Only the contractor’s contact information
Only the date of the first inspection
Only the material delivery date
Can a certificate of occupancy authorize a code violation?
No; issuance does not approve a violation
Yes, if the certificate is temporary
Yes, when the applicant signs a release
Yes, when the permit was issued before inspection