Field Scenarios: Floors, Walls, Roofs and Special Features
Key Takeaways
Check floor bearing and connections before cover.
Verify masonry reinforcement before grout.
Trace the exterior wall drainage path.
Refer roof truss alterations for written approval.
Check hazardous glazing and approved temporary egress.
Floors and walls before cover
At a framed floor, check member span, bearing, connectors, subfloor grade and fastening against the approved framing documents. If a joist is drilled or notched, identify the member type and check the applicable restriction rather than using a rule for sawn lumber on an engineered member. At a concrete slab, verify reinforcement, cover, supports and embedded items before placement, and check the specified testing and inspection schedule.
For a masonry wall, compare reinforcement, grout space, cleanouts and mortar requirements with the approved documents. A missing bar cannot be checked reliably after the cell has been grouted. At an exterior wall, verify continuity of the water-resistive barrier and flashing around openings and penetrations under Chapter 14. Coordinate veneer support and attachments with the approved detail.
Roofs, glazing and temporary work
At a roof, check truss bearing, permanent bracing, connectors, sheathing fastening, covering and drainage against approved details. Section 2303.4.5 requires written design professional concurrence and approval before altering a truss member or component. Chapter 15 addresses roof assembly classification; compare the specified covering and supporting assembly, not just a label on the shingle bundle.
For a glazed sidelight next to a door, check the hazardous-location criteria and exceptions in §2406.4.2, including distance from the door and height above the walking surface. Verify the required safety glazing identification. During occupied construction, also check that approved temporary egress remains available and clear. These checks depend on what was actually installed and what the approved plans require.
When is the best time to verify reinforcing bars and cleanouts in a grouted masonry wall?
Before placing grout
After the wall is painted
After concealing the wall with furring
At final inspection only
A roof truss member was cut in the field. What does §2303.4.5 require for the alteration?
Written concurrence and approval by a registered design professional
A verbal approval from the installer
A building owner acknowledgment alone
A change to the roofing classification
Which field measurements help determine whether glazing adjacent to a door is hazardous under §2406.4.2?
Distance from the door edge and height above the walking surface
Door label rating and wall thickness
Corridor occupant load and exterior grade
Roof slope and sill material