Foundations, Concrete and Special Inspection
Key Takeaways
Compare footing bearing with approved soils information.
Check §1809.5 frost protection.
Measure cover before concrete placement.
Use the required special inspection schedule.
Special inspection does not replace ordinary inspection.
Inspect bearing and frost protection
Start with the approved footing layout and geotechnical requirements. At excavation, verify bearing material, depth, width and location. If you find unanticipated fill, groundwater or disturbed bearing soil, document the condition and request an approved correction rather than accepting a deeper excavation as a substitute for the design. IBC Chapter 18 distinguishes shallow and deep foundations.
Section 1809.5 gives three general frost-protection approaches: extend below the local frost line, design to ASCE 32, or bear on solid rock. Check the narrow exception for qualifying freestanding buildings. For a foundation wall, compare reinforcement, embedments and backfill restrictions with approved drawings before concrete or backfill conceals them.
Use the concrete and special inspection references
Chapter 19 applies ACI 318 with IBC modifications. ACI 318-19 Chapter 13 covers foundations and Chapter 26 covers construction documents and inspection. For concrete cast against and permanently in contact with ground, ACI lists 3 inches of specified reinforcement cover. Verify the actual exposure, approved cover and supports before placing concrete. A formed face may have a different cover condition.
Chapter 17 distinguishes regular inspection by the building official, special inspection by an approved agency, and structural observation by a registered design professional when required. Use the approved statement of special inspections to find the work, inspection frequency and required records. Coordinate the scheduled hold point with the responsible parties before the work is concealed.
Which is one listed frost protection method for permanent foundation supports?
Extend the support below the local frost line
Place it on frozen soil that thaws seasonally
Increase the footing reinforcing bar size alone
Use the roof snow load to set its depth
What cover does ACI 318-19 specify for concrete cast against and permanently in contact with ground?
3 inches
¾ inch
1½ inches
2 inches
Who generally retains the approved special inspection agency when required?
The owner or authorized agent other than the contractor
The contractor without owner involvement
The building official in every case
The concrete supplier for all project work