When is initial verification of electrical work carried out?
Before new work is put into service. Inspection and testing establish whether the work meets the applicable requirements and provide evidence for certification.
Filter by Topic
Jump to Card
About These City & Guilds 2391-52 Flashcards
These 50 flashcards are designed to help you memorize key terms and definitions for the City & Guilds Level 3 Award in Initial and Periodic Inspection and Testing of Electrical Installations (2391-52). Each card shows a term on the front and its definition on the back—the classic flashcard format for vocabulary memorization. Use these alongside our practice questions to build both recall and comprehension.
Topics Covered
Complete Flashcard Reference
Review every term in this set. Open any term to reveal its definition.
When is initial verification of electrical work carried out?
Before new work is put into service. Inspection and testing establish whether the work meets the applicable requirements and provide evidence for certification.
What does periodic inspection and testing establish?
Whether an existing installation is satisfactory for continued service, within the stated scope. A change of use, damage or a scheduled review can prompt an Electrical Installation Condition Report (EICR).
How does BS 7671 differ from the Electricity at Work Regulations?
BS 7671 is a technical standard. The applicable Electricity at Work Regulations impose legal duties. Use the legislation for the nation where the work takes place.
Which document records initial verification when a new circuit is installed?
An Electrical Installation Certificate (EIC), with the applicable inspection and test schedules. Adding a new circuit is outside the scope of the minor works certificate.
Can a consumer unit replacement be certified on a minor works certificate?
No. The Minor Electrical Installation Works Certificate is for suitable minor work on an existing circuit, such as adding a socket. A consumer unit replacement needs an Electrical Installation Certificate.
What must the EICR record if an area could not be inspected?
Record the area and reason in the extent and limitations section. Agree foreseeable limits with the person ordering the work and record restrictions encountered on site as operational limitations.
What does a person signing an EIC take responsibility for?
The work covered by their declaration: design, construction, or inspection and testing. A person taking more than one role must be competent for each role they declare.
Who keeps the Electrical Installation Condition Report after issue?
The person who ordered the work receives the original, and the inspector keeps a duplicate. Keep the original and its schedules available for future inspection or work.
Why review drawings and circuit details before verifying new work?
They identify the circuits, equipment and intended protective measures. This lets the inspector check what was actually installed against the design and plan the relevant tests.
What makes a sample useful during periodic inspection?
It represents the circuits and equipment within scope. If the sample exposes repeated defects or casts doubt on similar items, widen the checks to establish how far the problem extends.
How is the next periodic inspection date chosen for an EICR?
The inspector recommends a date and records the reason, taking account of the installation’s condition, use and maintenance. Check any shorter interval required by applicable law.
What must safe isolation achieve before proving dead?
Identify every supply that can energise the point of work, including alternative sources. Disconnect them at suitable points and secure the isolation against reconnection, using lock-off and warning notices as appropriate.
Why prove the voltage indicator both before and after checking for dead?
It confirms the indicator was working when it showed no voltage. Use a suitable two-pole indicator and proving unit, and prove all relevant conductors dead at the point of work.
When does Regulation 14 in Great Britain allow live testing that could give rise to danger?
Only if making the conductors dead is unreasonable in the circumstances, working on or near them live is reasonable, and suitable precautions are taken to prevent injury. All three conditions must hold.
Why inspect before carrying out electrical tests?
Inspection can reveal exposed live parts, damaged equipment or missing protection that would make testing unsafe. Deal with conditions that prevent safe testing before proceeding.
How should you handle signs of overheating on the distributor’s sealed service head during periodic inspection?
Record the finding and alert the person ordering the inspection immediately in writing so it can be referred to the distributor. Keep the check external; do not break seals or dismantle the service head.
What makes a metal service pipe a candidate for main protective bonding?
It can introduce a potential, usually Earth potential, from outside the electrical installation. Check whether it can do so; the fact that a pipe is metal does not establish the need for bonding.
What might a burnt smell at an enclosure tell an inspector?
It is a clue to overheating or arcing. Use it to direct a closer inspection under safe conditions; it does not establish the cause on its own.
How should a safety defect be handled in initial verification versus periodic inspection?
Correct an initial-verification defect before certifying affected new work and putting it into service. For periodic work, record the defect on the EICR and classify it by risk; act immediately if danger is present.
What do the two numerals in an enclosure’s IP code describe?
The first covers access to hazardous parts and ingress of solid objects. The second covers ingress of water. Assess each against the conditions at the installed location.
What is the difference between EICR codes C1 and C2?
C1 means danger is present and immediate action is needed. C2 means a condition is potentially dangerous and urgent remedial action is needed. Either code makes the overall EICR unsatisfactory.
When is an EICR observation classed as C3?
When improvement is recommended but the condition does not warrant C1 or C2. A C3 on its own does not make the report unsatisfactory.
When is an FI entry appropriate on an Amendment 4 EICR?
When inspection or testing points to a potential safety issue that cannot be classified within the agreed extent and limitations. Advise further investigation; FI alone does not make the report unsatisfactory under Amendment 4.
Why do the relevant dead tests come before energising new work?
They can uncover faults in continuity, insulation or wiring before energisation makes those faults hazardous. Follow the initial verification sequence and investigate failed results before proceeding.
Why is there no single fixed test sequence for periodic inspection?
The installation’s condition, earlier records, access and safety determine which tests are needed and the order in which they can be carried out safely. Record any limits on what could be verified.
How do GS38 probe features reduce risk during low voltage testing?
Finger guards help keep hands clear of live parts. Insulation close to the probe tip helps prevent accidental bridging between conductors. Leads and probes must also suit the instrument and measurement category.
Why null the leads of a low-resistance tester before measuring continuity?
So the resistance of the leads is not included in the circuit reading. Check the zero again if you change the leads or attachments.
What is a circuit protective conductor continuity test meant to confirm?
That the intended protective path is electrically continuous. Compare the measured resistance with what is reasonable for the conductor’s material, size and length.
How can a parallel metallic path mislead a continuity test?
Test current can return through the parallel path, giving a deceptively low reading even if the conductor under test is defective. Use a test method that distinguishes the intended conductor from other return paths.
What do r1, rn and r2 denote in a ring final circuit continuity test?
The separate end-to-end resistances of the line, neutral and circuit protective conductors. An open reading on any conductor calls for investigation before relying on the ring.
A uniform ring has 0.44 Ω end to end on both line and neutral. After cross-connecting opposite ends, what line-to-neutral reading is expected on the ring?
About 0.22 Ω: (r1 + rn) ÷ 4. The two paths are in parallel. This shortcut assumes matched line and neutral conductors and applies at points on the ring itself.
Why might sound line-to-earth readings vary around a ring final circuit?
If the line and protective conductors have substantially different resistances, cross-connected readings can vary with position. Judge the pattern against the conductor sizes and ring layout before calling it a defect.
What insulation resistance test voltage and minimum apply to an ordinary 230 V circuit?
Normally 500 V DC and at least 1 MΩ under BS 7671 Table 64, with equipment that could affect the result or be damaged disconnected where practicable.
What is the insulation resistance allowance if a fixed SPD cannot reasonably be disconnected?
For the affected circuit the test voltage may be reduced to 250 V DC. The minimum is still 1 MΩ; the lower voltage does not lower the acceptance threshold.
What must insulation testing confirm for a circuit protected by electrical separation?
That the separated circuit’s live parts are insulated from Earth and from live parts of other circuits. A good reading between the separated circuit’s own conductors alone does not verify the protective separation.
Why check that a single-pole light switch interrupts the line conductor?
If it interrupts the neutral instead, the light may go out while parts of the fitting remain at line potential. Check polarity before energising the circuit.
How does the incoming supply polarity check differ from a dead circuit polarity check?
Incoming polarity is checked at the origin with the supply live but before energising the installation. A dead circuit polarity check verifies connections within the isolated installation.
What does the fall-of-potential test use to measure earth electrode resistance?
A current probe provides a test-current path through the ground; a separate potential probe measures voltage. A stable region as the potential probe is moved supports a valid resistance reading.
For ordinary TT fault protection by an RCD, what does the product RA × IΔn need to satisfy?
It must be no more than 50 V. RA includes the earth electrode and the protective conductor to exposed conductive parts; use amperes for IΔn. The condition does not replace verification of RCD operation.
How does Ze differ from Zs?
Ze is the external part of the earth fault loop at the origin. Zs is the impedance of the complete earth fault loop at the point being assessed, including the installation’s part of the path.
On a TN circuit, estimate Zs if Ze is 0.27 Ω and R1 + R2 is 0.48 Ω.
About 0.75 Ω on the stated values: Ze + (R1 + R2). Apply any temperature allowance required for the comparison with the permitted maximum.
Why allow for conductor temperature when comparing a Zs reading to a tabulated maximum?
A cold conductor has less resistance than it may have in service. Use an appropriate temperature correction or a published limit for measured values for the actual device and required disconnection time.
If PSCC is 2.8 kA and PEFC is 1.9 kA at the same point, what prospective fault current goes on the report?
2.8 kA, the larger value. PSCC is prospective short-circuit current and PEFC is prospective earth fault current; they describe separate fault paths.
What must be checked if prospective fault current exceeds a breaker’s own breaking capacity?
Check whether the exact assembly has a verified conditional rating with the specified upstream protective device. Without suitable coordination, the breaker’s own breaking capacity is insufficient.
What operating time is acceptable for a general non-delay RCD on the AC test at IΔn?
No more than 300 ms for this installation verification check. Compare time-delayed devices with their own criteria.
What does 30 mA mean on an RCD marked 40 A / 30 mA?
It is the rated residual operating current (IΔn), used to select the current for the verification test. The 40 A marking is the rated load current.
What can affect an RCD test result even if the device itself is working?
Leakage from connected equipment or capacitance downstream can influence the recorded trip time. Consider the connected circuit and the test method before deciding the RCD is faulty.
How does a phase-sequence check differ from a live phase-rotation check?
For phase sequence, check with the installation dead that the identified line conductors go to the correct terminals throughout. A rotation indicator measures the order of the energised phases at its connection point.
What does pressing an RCD’s built-in test button demonstrate?
That the built-in test facility makes the device operate. This functional check does not measure disconnection time; the timed instrument test is separate.
A single-phase circuit has a line-plus-neutral resistance of 0.30 Ω at operating temperature. What is the approximate resistive voltage drop at 18 A?
5.4 V: design current × the resistance of the outgoing and return load conductors. The protective conductor is not the normal return path used for this calculation.
Frequently Asked Questions
How does 2391-52 differ from 2391-50 and 2391-51?
2391-52 is the combined Level 3 Award. It covers initial verification of new work and periodic inspection and testing of existing installations. The 2391-50 route covers initial verification; 2391-51 covers periodic inspection and testing.
How is City & Guilds 2391-52 assessed?
Candidates must pass the open-book, invigilated 2391-052 test on e-volve and complete the 2391-502 assignment successfully. The online test has 60 multiple-choice questions in 120 minutes, with a pass mark of approximately 75% that City & Guilds may adjust. The assignment includes visual inspection, practical work and a short-answer paper.
How do the 50 cards map to the online test?
City & Guilds lists 13 questions on requirements, 3 on safety management, 11 on inspection and 33 on testing. Scaled to 50 cards, those counts give 11, 3, 9 and 27 cards, with the rounding tie assigned to safety. The practical performance outcome has no online questions and is assessed in the mandatory assignment.
Which references can candidates bring to 2391-052?
City & Guilds lists BS 7671, the IET On-Site Guide and IET Guidance Note 3 for the online test. Use paper copies that meet its publication and annotation rules. Electronic copies are not allowed for this externally marked test. The practical assignment has separate rules for each task.
Which edition of BS 7671 should I revise with?
BS 7671:2018+A4:2026 is the current UK standard, and IET Guidance Note 3, 10th edition, is aligned to it. The previous edition with the Amendment 3 update reached the end of its transition on 15 October 2026. Ask your centre to confirm which edition applies to your sitting: City & Guilds describes alignment of written and practical assessment tasks separately on its qualification page.
Who is 2391-52 intended for?
Practising electricians aged 18 or older with relevant Level 3 electrotechnical training or similar and enough experience to inspect and test safely. The centre assesses readiness before enrolment; this award is unsuitable for people new to the industry.
How soon can I resit a 2391-52 assessment?
City & Guilds does not publish a fixed 2391-52 wait or a separate interval after three failures in its public qualification documents. Ask your approved centre about the next available sitting and the arrangements for the component you need to resit.
Explore More City & Guilds UK Trade Qualifications
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.