4.5 Houses in Multiple Occupation and Licensing

Key Takeaways

  • Count people and households, establish how the property is used and check the Housing Act 2004 tests and exemptions.

  • English mandatory licensing usually starts at five people in at least two households when the relevant statutory test applies. Wales normally also requires three qualifying storeys.

  • Check local additional and selective designations, actual licence occupancy conditions and applicable fire and management rules separately.

  • Separate property licensing from planning permission. The enforcement, rent repayment and possession consequences depend on the nation, offence and date.

Last updated: November 2026

Identify the HMO and the people living there

For a conventional shared house, apply the standard test in section 254(2) of the Housing Act 2004. It covers living accommodation outside self-contained flats. The occupiers form more than one household, use the accommodation solely for their occupation as their only or main home (or are treated as doing so), and at least one gives rent or other consideration. At least two households share a basic amenity, or the accommodation lacks one. The three basic amenities are a toilet, personal washing facilities and cooking facilities. Schedule 14 excludes certain buildings for purposes other than Part 1, including those occupied by just two people and qualifying owner-occupied buildings with no more than two other occupiers in addition to the owner's household. Check the statutory conditions and prescribed exemptions before deciding whether the usual three-person threshold is met. HMO tests · Schedule 14 · England regulation 6 · Wales regulation 6

Married couples, civil partners, people living together as a couple and relatives within the statutory definition can form one household. Four unrelated sharers normally form four households even if they sign one agreement. A cohabiting couple and two friends unrelated to the couple or each other form three households. Check prescribed relationships and cases treated as main residence, such as qualifying full-time students. Sections 258 and 259

Section 254 also has tests for self-contained flats and converted buildings. The converted building test requires a conversion containing at least one unit that is not a self-contained flat. A different route under section 257 covers a building converted into and consisting of self-contained flats where the conversion failed the applicable building standard, still fails it, and fewer than two-thirds of flats are owner-occupied. The applicable standard depends on the conversion, including the 1 June 1992 threshold and transitional rules. Consider both the building and any separately shared flat. Section 257

Select the property licensing regime

RegimeEnglandWales
Mandatory HMO, Part 2From 1 October 2018, five or more people in two or more households, meeting the standard, self-contained flat or converted building test. Storey count does not control. For the self-contained flat test, the Order excludes a purpose-built flat in a block of at least three self-contained flats. Section 257 blocks are outside the Order.Five or more people in two or more households in an HMO with at least three qualifying storeys. Check how the Order counts adapted basements and attics, some mezzanines and business floors above or below the living accommodation. Section 257 blocks are outside the Order.
Additional HMO, Part 2A local designation can include other HMOs within its defined area and description. A scheme may cover smaller shared houses, or section 257 blocks where specified.Apply the designation in the local authority area. It may cover properties smaller than the mandatory description or section 257 blocks where specified.
Selective, Part 3A local designation can cover other privately rented houses within its area. Check its conditions, statutory exemptions and whether Part 2 already requires a licence.Read the local designation, including coverage and exclusions. Check the separate requirements for registration and licensing through Rent Smart Wales.

Check the council designation, licence register and property address before letting or allowing an extra occupier. Check permitted household and person numbers, manager suitability and licence conditions. A Part 2 licence is property-specific and normally lasts up to five years. A temporary exemption notice or a management order in force can change the Part 2 requirement. English mandatory Order · Welsh mandatory Order · Parts 2 and 3 licensing · HMO licence guidance

Apply occupation limits and manage hazards

For covered English Part 2 licences, the statutory minimum usable sleeping room areas are 6.51 m² for one person aged over 10, 10.22 m² for two aged over 10 and 4.64 m² for one child aged under 10. A room under 4.64 m² cannot be used for sleeping under these licence conditions. Exclude areas with a ceiling below 1.5 m. If a room measures 7.1 m² overall and 0.9 m² falls below that height, the usable area is 6.2 m², below the minimum for one adult. Check actual licence conditions, higher local standards and any statutory exceptions for specified charity-managed accommodation. In Wales, check the Welsh amenities standards and council requirements for that licence. Also check the separate Housing Act 1985 Part 10 statutory room and space standards and the crowding hazard under HHSRS where relevant. English room size conditions · Welsh amenity standards · Statutory overcrowding

The English and Welsh 2006 management regulations apply to ordinary HMOs in their respective nations whether licensed or not. Section 257 blocks have their own 2007 regulations in each nation. Make the manager's contact information available and display it prominently. Maintain escape routes, applicable fire alarms and equipment, common areas, water and drainage, and provide appropriate waste facilities. The management rules require the latest gas appliance test certificate received by the manager to be supplied within seven days of a written council request. Separate gas safety rules set the landlord's annual safety check for covered appliances and flues. For an ordinary HMO in England use the current English electrical safety regulations for in-scope tenancies, since the former electrical testing paragraph in the 2006 English rules was removed. In Wales, and for section 257 blocks, check the separate applicable management rules, including the fixed electrical test interval and certificate duties. England 2006 · Wales 2006 · England section 257 · Wales section 257 · English electrical standards

Check enforcement and planning separately

Operating an unlicensed HMO where a licence is required, knowingly permitting occupation beyond authorisation, or breaching applicable licence or management conditions can lead to prosecution when the relevant offence is established. In England, qualifying section 249A offences committed from 1 May 2026 can attract a civil penalty of up to £40,000 instead of prosecution. For a qualifying unlicensed HMO offence under the current English rent repayment rules, the First-tier Tribunal can order up to 24 months' rent within the offending period. Check the application deadline and savings if the offence began before 1 May 2026. In Wales, use sections 73 and 74 for HMO rent repayment orders through the Residential Property Tribunal. A tenant applicant must show a conviction or a qualifying prior rent repayment order, and rent for periods outside the 12 months ending with the occupier's application is excluded. Housing Act licensing offences · English financial penalties · English RRO guidance

Check the specific possession route. The former English section 75 rule concerned section 21 notices for unlicensed HMOs, including where relevant under the transition. Current English private assured possessions use the applicable grounds. In Wales, section 75A bars specified notices for unlicensed HMOs on standard contracts, including a section 173 notice. English section 75 and savings · Welsh section 75A

A qualifying small HMO can be planning Class C4 for up to six residents. A larger HMO is generally outside that class. In England, Class L gives permitted development rights between C3 dwellinghouse and C4, subject to rules including any applicable condition or effective Article 4 direction withdrawing the right. In Wales, the national C4-to-C3 right does not provide the reverse C3-to-C4 route. Check the local planning position before a material change of use. English planning Order · Welsh development management manual, 3.5.13–14

For example, a landlord proposes to let an English two-storey house to four unrelated students in a ward whose additional licensing designation covers that type of HMO and whose effective Article 4 direction removes C3-to-C4 rights. The agent should confirm planning permission for the change, the applicable HMO licence and compliance with management duties before the letting proceeds.

Test Your Knowledge

A two-storey house in England is let on a joint tenancy to a cohabiting couple and two friends who are unrelated to the couple or each other. They pay rent, share one kitchen and bathroom and use the house solely as their main home. No statutory exemption applies. How should the manager classify it?

A

The house falls outside the HMO definition because it has only two storeys.

B

It is an HMO with three households, but HMO management duties apply only if the council issues a licence.

C

It is an HMO with four people in three households. The ordinary HMO management rules apply, and the manager should check for additional licensing.

D

It needs a mandatory HMO licence because it has three households.

Test Your Knowledge

What national minimum usable sleeping room area does Schedule 4 specify for one 24-year-old in a house covered by the ordinary English Part 2 room size conditions?

A

4.64 m²

B

5.50 m²

C

10.22 m²

D

6.51 m²

Test Your Knowledge

An effective Article 4 direction removes Class L C3-to-C4 permitted development rights for an English address. The owner proposes to change a family dwelling to a C4 HMO for four unrelated students. What should the manager advise?

A

Obtain planning permission for the proposed change of use and check property licensing separately.

B

Treat it as a larger HMO outside C4 because the direction changes the use class.

C

Treat the planning permission as an exemption from any additional licensing designation.

D

Treat planning consent as replacing the HMO management duties.