7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking
Key Takeaways
A permit to pour should be issued only after falsework, formwork, edge protection, access, pump set-up and the pour sequence have been checked against the temporary works design.
Concrete pumps and truck mixers working near overhead lines must follow CDM 2024 regulation 27: divert, isolate and earth, or protect the line with barriers, warning notices and suspended protection, and observe the line owner's safe distance.
Wet cement is strongly alkaline and can cause chemical burns and dermatitis; occupational dermatitis appears in the Third Schedule of NADOPOD 2004 as a reportable occupational disease.
CDM 2024 regulation 37 requires suitable and sufficient lighting, including secondary lighting where failure of the main artificial lighting would create risk, which applies to night pours.
Formwork may be struck only when the engineer's criteria, such as concrete cube strength or age, are met; early stripping has caused slab and beam failures.
Why concrete work deserves its own plan
Concreting brings several high-risk activities together at one place and time:
- heavy trucks reversing and queuing
- a boom pump with outriggers on uncertain ground
- pipelines under pressure
- workers on newly loaded falsework at an open slab edge
- vibrators and power tools
- cement contact
- often night work or long hours in heat
Each element is covered elsewhere in this guide. A pour succeeds when they are coordinated through one plan and one permit.
Before the pour: inspection and permit to pour
The permit to pour, or permit to load, links the temporary works process (Section 7.2) to the day's operation. Do not issue it until:
| Check | What is confirmed |
|---|---|
| Falsework and formwork | Built to the drawings; inspected by the designated person or temporary works coordinator; defects closed |
| Edge protection and access | Guardrails at slab edges and openings; safe ladder or stair access; walk boards over reinforcement |
| Pump set-up | Firm, level location; outriggers fully extended on pads sized for the ground; outside the excavation's zone of influence; clear of overhead lines |
| Traffic plan | Truck route, waiting area inside the hoarding, washout point, banksman, pedestrian separation (CDM regulations 29 and 30) |
| Pour sequence | Order and rate of placing as the design requires; watcher appointed with authority to stop the pour |
| People and equipment | Crew briefed in a toolbox meeting; vibrators and electrical supply checked (RCD-protected); lighting for night work; first aid and emergency arrangements; drinking water |
| Weather | Rain or lightning forecast and the stop rules |
Signatories normally include the principal contractor's engineer, the temporary works coordinator and the SSS, with the consultant where the contract requires.
Delivery and pumping
Truck mixers
- Follow the traffic routes and avoid reversing. Where reversing is unavoidable, use a trained banksman (CDM regulation 30(2)).
- Keep trucks back from excavation edges and use stop blocks where they discharge near trenches (regulation 30(5)).
- Provide a washout area that contains the alkaline washwater and stops it entering drains.
Boom pumps
- Operate to the manufacturer's instructions by a trained operator. Use the outrigger pads and set-up the manufacturer specifies.
- The boom must never be used as a crane.
- Overhead lines: this is the main electrocution risk in concreting. Under CDM regulation 27(2) and (3), the line must be diverted or isolated and earthed. If neither is practicable, provide warning notices, barriers and suspended protection or equivalent measures, and keep to the safe distance set by the line owner, usually TNB. Plan the pump position so the boom cannot reach the line in any slew position. A spotter is not a substitute for planning.
- Delivery hose: keep people away from the end hose during priming and blockage clearing. Do not kink or stand on lines.
Line pumps and pipelines
- Secure pipelines independently of falsework unless the falsework design allows for them. Pumping surges can shake light props.
- Couplings need correct clamps and pins. Damaged pipes are replaced, because worn pipes can burst.
- Clearing blockages and cleaning with compressed air can fire debris and "sponge balls" out of the pipe at high speed. Release pressure first, follow the manufacturer's procedure, use catch cages and exclusion zones, and never uncouple a pressurised line.
Skips and crane pours
Skips and crane pours are lifting operations under Chapter 8:
- a lifting plan and a competent signaller
- a rated skip in good condition
- nobody under the load
- operators of tower and mobile cranes who are competent persons under the Plant Requiring Certificate of Fitness Regulations 2024
Placing and compacting
- Place evenly in layers as the pour sequence requires. Avoid heaping concrete in one place, which overloads part of the falsework (Section 7.2).
- Watch for distress signs: bulging forms, moving props, cracking noises, unexpected sag. Stop the pour if any appear.
- Edges: keep guardrails in place. Workers pulling hoses near edges are at risk of being pulled over.
- Poker vibrators:
- Electrical: use residual current device protection and reduced-voltage or battery tools where possible, with cables kept out of water and concrete (Chapter 9).
- Hand-arm vibration: rotate operators and maintain equipment (Section 10.1).
- Slips and trips: walk boards over reinforcement mesh; manage hoses and cables.
- Manual handling: concrete, hoses and skips are heavy. Use mechanical handling and team lifts (Section 10.2).
Cement and concrete health hazards
- Skin: wet cement is strongly alkaline. Prolonged contact, such as kneeling in wet concrete or concrete inside boots or gloves, can cause serious chemical burns. Repeated contact causes irritant and allergic dermatitis. Occupational dermatitis is listed in the NADOPOD Third Schedule, so diagnosed cases must be reported within 7 days on JKKP 7.
- Eyes: splashes can cause serious injury. Wear eye protection and keep an eyewash nearby.
- Dust: dry cement and cutting or grinding hardened concrete release dust, including respirable crystalline silica, which causes silicosis (Section 10.3).
- Chemicals: admixtures, release agents and curing compounds. Check the safety data sheets and labels (CLASS 2013) and include them in the USECHH chemical register and assessment.
Controls:
- waterproof gloves and boots with trousers worn outside the boots
- long sleeves
- washing facilities with clean water on site (CDM Second Schedule)
- prompt washing of skin contamination
- health surveillance where the chemical health risk assessment calls for it
Night pours, long pours and heat
- Lighting (CDM regulation 37): suitable and sufficient lighting on the deck, access routes and truck routes, with secondary (emergency) lighting where failure of the main lights would create danger. Coloured lighting must not change how safety signs look.
- Fatigue: long pours and back-to-back shifts lead to fatigue errors. Plan crew changes (Section 10.4).
- Heat: daytime pours on exposed decks drive heat stress. Provide water, shade and rest breaks as DOSH's heat stress guideline sets out (Section 10.1).
- Weather: rain changes slip risk and concrete quality, and lightning stops all deck and boom work.
Striking and back-propping
- Permit to strike: strike only when the designer's or engineer's criteria are met, such as minimum cube strength, age or curing conditions. The repealed BOWEC regulation 31 required the Professional Engineer's specification and approval before stripping.
- Order: follow the specified sequence. Vertical forms are usually struck earlier than slab and beam soffits, which carry load.
- Back-props and reshores: install and keep them as designed to carry loads from the floors above. Remove only on authority.
- During and after stripping: control the drop zone, lower formwork, clear stripped material promptly, and remove projecting nails and ties (CDM regulation 20).
Scenario: a night pour on Level 9
At 21:00 the boom pump is set up at the site entrance under an 11 kV line, with outriggers on unpadded fill. Floodlights cover the deck but not the stair access, and the falsework permit has not been signed. The SSS stops the start and:
- Relocates the pump to the pre-planned pad position away from the line. The line owner's safe distance and the barrier arrangement are confirmed in the lift and pour plan (CDM regulation 27).
- Has the outriggers set on the manufacturer's pads on firm ground, checked by the pump operator.
- Arranges extra lighting for the stairs and the truck route, with secondary lighting (regulation 37).
- Has the temporary works coordinator inspect and sign the permit to load before the first truck discharges.
- Briefs the crew on the stop signals and the watcher's role.
A concrete pipeline blocks during a pour, and the crew want to blow it clear with compressed air. Which precaution comes first?
Release the line pressure and set an exclusion zone before opening it
Increase the pump pressure to push the blockage through quickly
Have a worker hold the end hose firmly to direct the discharge
Uncouple the nearest joint at once while the pump is still running
A concreter develops an itchy, cracked rash on his hands after months of handling wet concrete, and a doctor diagnoses occupational dermatitis. What must the employer do under NADOPOD 2004?
Nothing, because skin conditions are not reportable
Report it only if the worker is off work for more than 4 days
Wait for the annual return before mentioning it to DOSH
Report it to the nearest DOSH office on form JKKP 7 within 7 days
Under CDM 2024 regulation 37, what lighting is required for a concrete pour that continues after dark?
Lighting only at the batching plant and in the concrete trucks' waiting area
Lighting only inside the site office and guard house
Lighting at the work area and routes, plus secondary lighting where needed
No requirement, provided every worker on the pour carries a torch or headlamp