3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement
Key Takeaways
DOSH's Guidelines for Public Safety and Health at Construction Sites 2007 say site hoarding should be at least 1,800 mm high, continuous to the ground and built to the local authority's specification.
CDM 2024 regulation 29 requires traffic routes that are suitable, sufficient in number and size and suitably placed, with adequate separation between vehicles and pedestrians or other protection and warnings.
CDM 2024 regulation 30 requires measures to prevent unintended vehicle movement, warnings to people at risk, no riding except in places provided, and measures to stop vehicles falling into excavations or water.
Under CDM 2024 regulation 27, overhead power cables posing a risk must be diverted away from the work area or isolated and earthed; if neither is practicable, warning notices and barriers or suspended protection are required.
DOSH's 2015 excavation safety bulletin recommends highly visible barriers at least 6 metres horizontally from overhead lines, with red-and-white goalposts marking crossing points.
Why planning comes first
Part 4(A), Site Initial Planning, gets four hours in the NIOSH timetable, and Part 4(D), Vehicle and Plant Movement, gets three. Paper 2B lists "traffic management activities" as one of the ten presentation topics. Most site layout decisions are hard to change once hoarding is up and cranes are erected, so the safest layouts are fixed before mobilisation.
CDM 2024 makes this a legal sequence:
- The client provides pre-construction information (regulation 5).
- The principal contractor drafts the construction phase plan, including site rules, before the site is set up (regulation 13).
- The principal contractor makes sure unauthorised access is prevented (regulation 15(2)(e)).
- Each contractor must not start work until reasonable steps against unauthorised access have been taken (regulation 17(1)(g)).
The pre-mobilisation survey
Before the layout is drawn, the project team gathers:
- Ground and site information: site investigation results, slopes, flood history, fill and contamination, water table
- Services: underground cables, gas, water, sewers and telecoms; overhead lines and their voltages. Obtain the utility owners' records, then verify on site.
- Neighbours and public: schools, clinics, shophouses, footpaths, bus stops and traffic volumes on access roads
- Access constraints: road widths, turning radii for long vehicles, height limits, local authority conditions on working hours and road use
- Existing structures: foundations within the zone affected by excavation or piling, and whether they need monitoring or underpinning
Functional layout
A good layout separates activities so that high-risk operations do not cross routine movement:
| Zone | Contents | Planning points |
|---|---|---|
| Office and induction | Site office, induction room, security post | Near the pedestrian entrance, outside crane slew and vehicle routes |
| Welfare | Toilets, washing, drinking water, rest and changing areas, surau, first aid | Accessible on protected walkways, away from dust, fumes and traffic (Section 3.2) |
| Storage and laydown | Steel, timber, aggregates, chemical store, gas cylinder cage | Firm, level, drained ground within crane reach; flammables separated |
| Fabrication | Rebar bending, carpentry, welding bays | Guarded machines; electrical protection; fire precautions |
| Active work zones | Excavations, piling, structure | Controlled access, edge protection, exclusion zones |
| Traffic routes | Gates, haul roads, loading bays, parking | One-way loops where possible; pedestrian separation |
Hoarding and public protection
DOSH's Guidelines for Public Safety and Health at Construction Sites (first revision 2007) say:
- The worksite should be fully barricaded by protective hoarding, both to protect the public and to stop trespass (paragraph 11.1).
- Hoarding should be at least 1,800 mm high, continuous down to the ground, designed and built to the local authority's specification and kept in good condition (paragraph 11.2).
- An adequate safety distance should separate the work from the hoarding. Where falling materials could reach pedestrians or traffic, a gantry (covered walkway) is required (paragraphs 11.3 and 11.4).
- Entrances and exits should be sited to avoid danger and inconvenience to the public, and kept secure (paragraph 11.6).
- Warning signs should be posted at conspicuous positions; no bills other than warning signs; no parking or hawking along the hoarding during high-risk work (paragraphs 11.7 to 11.9).
- Materials should be stored and handled inside the hoarded area, and machinery sited so that its collapse would not affect the public (paragraphs 11.10 and 11.11).
CDM 2024 regulation 20(2) adds that, where the risk requires it, the site perimeter must be identified by suitable signs and fenced. Many local authorities set their own hoarding heights and designs, so always check the approval conditions.
Gates and wheel washing
- Gates should be of suitable design and adequate strength. Good practice is to make them open inwards or slide, so they never swing across a public footpath or road.
- Wheel-washing facilities and silt traps stop mud being carried onto public roads and silt entering drains. They are normally conditions of local authority or environmental approval, so follow the project's approved erosion and sediment control plan.
Safe access and good order: CDM regulations 19 and 20
- Provide safe and adequate access and egress to every workplace on the site (regulation 19(1)).
- Keep the site safe and without risk to health (regulation 19(2)).
- Guard every floor opening that could let a person fall (regulation 19(3)).
- Stop people using any access route that does not comply (regulation 19(4)).
- Allow adequate working space, taking into account the plant needed (regulation 19(5)).
- Keep the site in good order and work areas reasonably clean, and do not leave projecting nails or similar sharp objects (regulation 20).
Traffic routes: CDM regulation 29
The construction site must be organised so that people and vehicles can move without risk (regulation 29(1)). Each traffic route must be:
- suitable for the people or vehicles using it
- sufficient in number and size
- in a suitable position (regulation 29(2))
Where a route cannot fully meet that standard, regulation 29(3) requires:
- pedestrian doors and gates leading onto a traffic route to be separated enough for pedestrians to see approaching vehicles from a safe place
- adequate separation between vehicles and pedestrians, or, if that is not practicable, other protection for pedestrians and effective warnings to anyone who could be crushed or trapped
- at least one pedestrian exit from every loading bay
- a clearly marked, unobstructed pedestrian door next to vehicle gates where using the vehicle gate is unsafe for pedestrians
Routes must be signed where necessary, inspected regularly and maintained, and kept free of obstruction with enough space (regulation 29(4)).
Building a traffic management plan
| Control | Practical form |
|---|---|
| Segregation | Barriers between footpaths and haul roads (rigid or water-filled barriers on busy routes); covered walkways near structures |
| One-way systems | Entry and exit gates at opposite ends; turning loops to avoid reversing |
| Speed control | Site speed limit set in the site rules, enforced with signs and road humps |
| Reversing | Avoided by design; where unavoidable, a trained banksman or signaller, reversing alarms, cameras or mirrors |
| Visibility | Mirrors at blind corners; lighting at night; high-visibility clothing |
| Loading and unloading | Inside the hoarding at designated bays; drivers stay in safe zones |
| Deliveries | Scheduled arrival times to avoid queuing on public roads (DOSH public safety guideline paragraph 12.5) |
Vehicles and mobile plant: CDM regulation 30
- Take measures to prevent or control unintended movement of any vehicle, for example parking brakes, chocks and level parking (regulation 30(1)).
- The driver, operator or an assistant must give adequate warning to anyone at risk from the vehicle's movement (regulation 30(2)).
- Vehicles must be driven, operated, towed and loaded safely (regulation 30(3)).
- No riding on construction vehicles except in places provided for the purpose. Nobody may remain on a vehicle while loose material is loaded unless a safe place is provided (regulation 30(4)).
- Prevent vehicles falling into excavations, pits or water, or running over the edge of embankments or earthworks, for example with stop blocks and edge bunds (regulation 30(5)).
DOSH's public safety guideline adds that vehicles should be roadworthy and drivers must hold a licence for the class of vehicle (paragraphs 12.1 and 12.2).
Plant near excavations and overhead lines
- Keep plant and spoil out of the zone of influence of an excavation unless the support design allows for the extra load (CDM regulation 24(1)(e)). Chapter 6 gives the distances DOSH guidance uses.
- Overhead power lines (CDM regulation 27(2) and (3)): where a line poses a risk, the contractor must route it away from the risk area, or isolate and earth it. If neither is practicable, it must provide suitable warning notices together with barriers to exclude unnecessary plant, suspended protection where vehicles must pass beneath, or measures giving an equivalent level of safety.
- DOSH's 2015 Tapak Selamat excavation bulletin recommends highly visible barriers at least 6 metres horizontally from overhead lines, and clearly defined crossing points with red-and-white goalposts and signs.
- The line owner, usually TNB, sets the safe working distance and any outage or shrouding arrangements for its line. Obtain this in writing before cranes, piling rigs or tipper trucks work nearby.
Scenario: one gate, two-way traffic
A town-centre site has a single 6-metre gate used by concrete trucks, tippers and workers on foot. Workers walk in alongside reversing tippers.
The SSS's recommendations:
- Create a separate pedestrian gate with a barrier-protected walkway to the induction room (regulation 29(3)).
- Mark a turning loop so tippers drive forward through the site, with a trained banksman at the one unavoidable reversing point.
- Schedule concrete deliveries so trucks do not queue on the public road.
- Install a mirror at the blind corner and add the speed limit to the site rules.
- Record the changes in the construction phase plan and brief them at induction and toolbox meetings.
According to DOSH's Guidelines for Public Safety and Health at Construction Sites 2007, what is the minimum recommended height for site hoarding?
1,800 mm, continuous to the ground and built to the local authority's specification
1,200 mm, with gaps allowed between the panels for ventilation and public visibility
2,400 mm in every case, whatever the local authority specifies
No minimum height, provided warning tape marks the site boundary
A loading bay on a project has only a vehicle entrance. Which CDM 2024 requirement does this breach?
Regulation 22, written arrangements before any demolition or dismantling
Regulation 35, plant supplying fresh air must have a device warning of failure
Regulation 8, client notification for long projects
Regulation 29, which requires a pedestrian exit from every loading bay
A crane must work near an 11 kV overhead line that cannot be diverted. Under CDM 2024 regulation 27, what should be done if isolating and earthing the line is also not practicable?
Provide warning notices with barriers, suspended protection or equivalent measures
Continue the lift, with a trained banksman watching the boom's clearance at all times
Ask the crane operator to slew slowly while near the line
Rely on the crane's anti-two-block device to stop contact
Sections you finish are checked off in the contents.