5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds
Key Takeaways
CDM 2024 regulation 21 requires temporary structures such as scaffolds to be designed, installed and maintained to withstand foreseeable loads and to be used only for the purpose for which they were designed.
DOSH's falls guideline limits the height-to-least-base ratio of tube-and-fitting towers to 4:1 for static internal, 3.5:1 for static external, 3.5:1 for mobile internal and 3:1 for mobile external towers.
DOSH's falls guideline recommends a maximum free-standing height of 9.6 metres for mobile towers and 12 metres for static towers.
DOSH's falls guideline requires tower platforms to be fully boarded and at least 635 mm wide, or 860 mm wide when materials are deposited, with 38 mm boards supported at least every 1.5 metres.
DOSH's falls guideline says mobile towers must be used only on hard, level surfaces with locked castors of at least 125 mm diameter, and moved only by pushing or pulling at the base with nobody on the platform.
Legal basis after BOWEC
Scaffolds used to be governed by Part X of the BOWEC Regulations 1986 (regulations 72 to 98), which were repealed on 1 June 2024. The current duties are:
- CDM 2024 regulation 21: supports, temporary supports and temporary structures must be designed, installed and maintained to withstand any foreseeable load, and used for the purpose for which they were designed. No structure may be loaded until it becomes unsafe.
- CDM 2024 regulation 19: safe access and egress, and guarded edges and openings.
- OSHA 1994 sections 15 and 18B: safe plant and systems of work, and a risk assessment that is acted on.
- DOSH Guidelines for the Prevention of Falls at Workplaces 2007, section 5: employers shall ensure all scaffolding is suitable and safe for employees to use (5.1). This section also contains detailed rules for standing, suspended, hung and tower scaffolds.
Main scaffold types
| Type | How it is supported | Typical use | Key controls |
|---|---|---|---|
| Independent tied | Two rows of standards linked by ledgers and transoms; stands on its own foundations, tied to the building for stability | Façade work, cladding, plastering | Ties at the designed spacing; ties must not be removed by other trades |
| Putlog (single) | One row of standards; putlogs bear on the wall being built | Traditional brickwork | Wall must be strong enough; not on weak or curtain walls |
| System (modular) | Proprietary standards with fixed connection nodes | Fast façade and internal access | Erect only to the manufacturer's instructions and permitted configurations |
| Birdcage | Grid of standards in both directions, full-area deck | Ceiling work in halls and atriums | Bracing in both directions; base on adequate floor |
| Tower (static or mobile) | Four standards, often proprietary aluminium | Short, light work | Height-to-base ratio, castors, bracing, internal access (see below) |
| Suspended (gondola, cradle) | Platform hung on wire ropes from roof outriggers | Façade glazing, cleaning, painting | Controls and emergency descent known to users; harness on an anchorage independent of the stage; safe working load not exceeded |
| Cantilever or truss-out | Built on needles or brackets projecting from the structure | Where ground support is impossible | Engineered design; anchorage of needles checked |
| Hung | Suspended from the structure by tubes, ropes or chains | Under bridges, soffits | Suspension points safety factor 3; wire ropes or chains safety factor 5; check clips on tube hangers (DOSH 5.4) |
DOSH's guideline (section 5.6) calls scaffolds not built to an accepted international standard, because of their construction, design or loads, special scaffolds. Expert advice from a professional engineer should be obtained before they are built and used, and every user must be told the maximum safe live load.
Components and what they do
Guardrail ─┐ ┌── Toe-board
Midrail ───┤ PLATFORM │
└── boards on transoms ──┘
Transom (across) Ledger (along) Brace (diagonal) Tie (to building)
Standard (vertical) ─ carries load down
Base plate ─ spreads load from standard
Sole board / sole plate ─ spreads load into ground
Firm, level, drained ground
- Standards are the vertical tubes that carry the load to the ground. They must be plumb and properly jointed; joints are staggered so they do not all fall in the same lift.
- Ledgers are horizontal tubes running along the scaffold. They tie standards together and carry transoms.
- Transoms are horizontal tubes across the scaffold that support the boards. Their spacing depends on board thickness and duty.
- Base plates are steel plates that spread each standard's load. Use adjustable base jacks within the manufacturer's maximum extension.
- Sole boards (sole plates) are timber or steel spread pieces under base plates on soil, fill or asphalt. DOSH's tower guidance requires metal base plates and timber sole plates unless the foundation is concrete or other solid material. Never use loose bricks, hollow blocks or offcuts.
- Couplers come in three load-bearing roles: right-angle couplers (ledgers to standards, transoms to ledgers), swivel couplers (bracing at angles) and sleeve couplers (joining tubes end to end). Putlog couplers only hold putlogs or transoms against movement; never use them where they must carry load.
- Bracing turns rectangles into triangles. Façade (longitudinal) bracing runs diagonally along the face, and ledger (transverse) bracing runs across. Without bracing a scaffold sways and can fold.
- Ties connect the scaffold to the permanent structure to resist wind and outward pull. Sheeting or netting greatly increases wind load, so the design must allow for it.
The standard steel scaffold tube is 48.3 mm outside diameter. Mixing tube types, or steel and aluminium, in one structure is unsafe unless the design permits it.
Working platforms
Platforms are where most scaffold falls start. From DOSH's guideline:
- standing scaffolds must have guardrails and working platforms in place on all areas in use, safe access to every platform, sufficient ties and braces, load-bearing members in place with the correct fittings, and platforms fully decked with planks secured against movement (section 5.2)
- the guardrail on scaffolds must be within 200 mm horizontally of the platform edge (section 4.2)
- if instability or damage is found, the scaffold should not be used until repaired by a certificated scaffolder (section 5.2)
Common good-practice rules, used widely and taken from British and European scaffold codes:
- Each board end rests on at least the specified number of supports and overhangs its last support by at least 50 mm, but not so far that it tips if stepped on. A common limit is four times the board thickness, about 150 mm for a 38 mm board.
- No gaps in the deck large enough to drop tools through, and no trip steps between boards.
- Width suited to the work and the load.
Tower scaffolds: DOSH falls guideline section 5.5
Tower scaffolds cause many falls and topple-overs because they are moved often and used by non-scaffolders.
| Topic | Requirement |
|---|---|
| Ground | Firm ground; static towers on metal base plates, with timber sole plates unless the base is concrete or similar |
| Mobile towers | Hard, level surfaces only; castors at least 125 mm in diameter, locked into the standards, with brakes that cannot be released accidentally; maximum load stamped on the castors |
| Stability (height to least base, measured to platform level) | Static internal 4:1; static external 3.5:1; mobile internal 3.5:1; mobile external 3:1 |
| Maximum free-standing height | Mobile 9.6 m; static 12 m |
| Exceeding ratios or exposed to wind | Tie to the structure, or design for stability with ground anchors, guys or kentledge |
| Platform | Fully boarded; at least 635 mm wide, or 860 mm where materials are deposited; boards secured; 38 mm boards supported at least every 1.5 m; trapdoors closed when in use |
| Edge protection | Guardrails and toe-boards on all four sides; toe-boards at least 200 mm; guardrail 1.0 m above the platform; gap between toe-board and lowest guardrail no more than 690 mm |
| Access | Inside the tower, on the narrowest side. Never a ladder leaning on the outside. A vertical ladder lashed to a narrow side extends at least 1.05 m above the platform |
| Prohibited | Ladders or trestles on the platform to gain height |
| Moving | Castors turned outwards and brakes on while in use; move only by pushing or pulling at the base, with the platform clear of people and materials |
| Tube-and-fitting towers | Ledgers and transoms start about 150 mm from the bottom; lifts no more than 2.7 m; plan bracing at the base, working platform and alternate lifts; zig-zag diagonal bracing to full height on all four sides |
Worked example: a mobile aluminium tower used outdoors has a 1.45 m x 1.45 m base. The maximum platform height at 3:1 is 3 x 1.45 = 4.35 m, unless the manufacturer's instructions are more restrictive (aluminium towers, being lighter, may have lower permitted ratios) or outriggers increase the effective base as the manufacturer specifies.
Scenario: the façade scaffold on new backfill
An independent tied scaffold has been erected on freshly backfilled ground beside a drain. The SSS finds:
- standards on broken bricks
- swivel couplers used to fix load-bearing transoms
- boards overhanging by about 300 mm
- two ties removed by the window installers
Actions:
- Withdraw the scaffold from use (red tag at every access point) and keep people off.
- Have the scaffolding contractor's competent scaffolders prop the affected bays, re-base them on compacted ground with sole boards and base plates, replace the couplers with right-angle couplers, re-lay the boards, and reinstate the ties to the design.
- Before handing the scaffold back, have a competent person inspect it and record the inspection (Section 5.3).
- Under the construction phase plan's site rules, only the scaffolding contractor may alter the scaffold. Brief the window installers at a toolbox meeting.
Under DOSH's falls guideline, what is the maximum height-to-least-base ratio for a mobile tower scaffold used outdoors?
4 to 1
3 to 1
5 to 1
2 to 1
Which coupler should connect a load-bearing transom to a ledger at a right angle on a tube-and-fitting scaffold?
A right-angle coupler
A putlog (single) coupler
A sleeve coupler
A swivel coupler
A worker wants to move a mobile tower scaffold to the next bay while standing on its platform. What does DOSH's falls guideline require?
Allowed if the worker holds the guardrail and moves under 3 m
Allowed if another worker on the platform steers it
Moved by pulling the top of the frame with a rope
Clear the platform, then push or pull the tower at its base