2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit

Key Takeaways

  • Under regulation 5 of NADOPOD 2004 a death, a serious bodily injury or a dangerous occurrence must be notified to the nearest DOSH office immediately by the quickest means and reported in the approved form within seven days.

  • DOSH's NADOPOD forms are JKKP 6 for accidents and dangerous occurrences, JKKP 7 for occupational poisoning and disease, and JKKP 8 for the register and annual summary.

  • Under regulation 9 of NADOPOD 2004 nobody may disturb the scene of a fatal or serious incident except to save life or relieve suffering, maintain public access to an essential service, or prevent further serious damage.

  • The NADOPOD register must be kept for at least five years, and an annual extract must reach the Director General before 31 January each year (regulation 10).

  • An audit tests whether the whole OSH management system is working against defined criteria, while an inspection checks the physical condition of a work area at a point in time.

Last updated: October 2026

Monitoring: knowing whether controls work

Planning and controls are only half of a management system. ISO 45001 clause 9 calls the other half performance evaluation: monitoring, measurement, analysis and evaluation, internal audit and management review.

TypeWhat it looks atConstruction examples
Active (proactive) monitoringChecks that controls are in place before harm happensDaily SSS inspections; scaffold and excavation inspections; permit audits; noise and dust monitoring; health surveillance; behavioural observations; committee inspections at least every three months
Reactive monitoringLearns from failures after they happenAccidents, near misses, dangerous occurrences, ill-health cases, DOSH notices, complaints

Good sites track leading indicators, such as the percentage of inspections completed, the number of near misses reported and closed, and toolbox attendance. They also track lagging indicators, such as lost-time injuries. Where hours worked are known, an injury frequency rate is often calculated as (number of lost-time injuries x 1,000,000) / total hours worked.

NADOPOD 2004: what, when and how

Section 32 of OSHA 1994 requires notification. The NADOPOD Regulations 2004 (P.U.(A) 128/2004) give the details.

EventRegulationEmployer's duty
Death, or serious bodily injury in the First Schedule, from a work accident5(1)Immediately notify the nearest DOSH office by the quickest means available, and send a report in the approved form within 7 days
Dangerous occurrence in the Second Schedule (even with no injury)5(1)Same as above
Injury that prevents normal work for more than four calendar days5(2)Report in the approved form within 7 days
Death within one year of a reportable accident5(3)Notify the Director General in writing as soon as practicable
Occupational poisoning or disease in the Third Schedule7(1)Report within 7 days; the registered medical practitioner also reports within 7 days

DOSH's NADOPOD guideline names the forms: JKKP 6 for notifying accidents and dangerous occurrences, JKKP 7 for occupational poisoning and disease, and JKKP 8 for the register. JKKP 8 records every case during the year, from minor cuts to fatalities, and is summarised for the annual return.

Serious bodily injury (First Schedule)

The First Schedule lists 11 categories, including:

  • loss of a limb or joint
  • fracture or dislocation of a bone
  • permanent loss of sight or hearing in one eye or ear
  • loss of consciousness from lack of oxygen or from absorbing, inhaling or ingesting a substance
  • any work-related injury or burn requiring immediate admission to hospital for more than 24 hours

Construction-relevant dangerous occurrences (Second Schedule, Part I)

  • Collapse or partial collapse of a scaffold more than 5 metres high that causes a substantial part to fall or overturn (item 1)
  • Collapse or partial collapse of any part of a building or structure under construction, reconstruction, alteration or demolition, or of any temporary support, unless intended (item 2)
  • An electrical short circuit or overload with fire or explosion that stops the plant for more than 24 hours (item 3)
  • An uncontrolled release of a substance that could cause serious injury or damage to health (item 4)
  • Explosion, fire or structural failure affecting the safety of a workplace or plant (items 5 and 6)
  • Collapse, overturning or failure of a load-bearing part of a crane, derrick, winch, hoist, piling frame, lift, excavator or other lifting appliance (item 11)

Records and penalties

  • Register: every employer and self-employed person keeps a register of all accidents, dangerous occurrences, poisonings and diseases, whether or not they were reportable (regulation 10(1)). Entries are kept for at least 5 years (regulation 10(2)), and an extract covering the year to 31 December is sent to the Director General before 31 January (regulation 10(3)).
  • Penalty: contravening NADOPOD carries up to RM10,000 or one year or both (regulation 13).

Preserving the scene

Regulation 9 says that after an accident or dangerous occurrence causing death, serious bodily injury, or serious damage to plant or property, no person may disturb or interfere with any plant, substance or article involved unless authorised to do so, except as far as necessary to:

  1. save life, prevent injury or relieve suffering
  2. maintain public access to an essential service or facility
  3. prevent further damage to property or the environment, or serious loss

In practice the SSS:

  • makes the area safe without destroying evidence
  • barricades the area and posts a guard
  • photographs and sketches the scene
  • lists witnesses
  • impounds failed items such as slings, harnesses and couplers

Investigating to root cause

Four phases

  1. Respond: give first aid, call emergency services, make the area safe, preserve the scene, and notify management and DOSH.
  2. Gather evidence: use the "4P" checklist:
    • People: separate, early, open-question interviews with the injured person and witnesses
    • Position: measurements, photographs, weather and lighting
    • Parts: equipment, PPE and failed components, tagged and secured
    • Paper: HIRARC, method statement, permit, inspection records, certificates of fitness, training and competency records
  3. Analyse causes with structured tools.
  4. Act: define corrective and preventive actions, assign owners and dates, update HIRARC and procedures, share lessons, and verify effectiveness.

Levels of cause

LevelQuestionExample (fall through a floor opening)
ImmediateWhat directly caused the harm?Worker stepped on an unsecured plywood cover
UnderlyingWhy was that condition or act present?Cover removed for a delivery and replaced loosely; no inspection after delivery
RootWhat system failure allowed it?No procedure for removing opening covers; delivery not covered by a permit; supervision stretched

5 Whys: keep asking "why?" until you reach a management system cause that, if fixed, prevents recurrence.

Fishbone (Ishikawa) diagram: group causes under people, plant and equipment, methods, materials, environment and management.

Avoid ending an investigation at "worker careless". As Section 2.2 explains, that describes the act, not the cause.

Records an SSS should know

RecordRuleMinimum retention
NADOPOD register (JKKP 8)NADOPOD reg. 105 years
Safety and health committee minutesSHC Regs reg. 277 years
Committee inspection and investigation reportsSHC Regs reg. 147 years
SHO monthly reportsSHO Regs reg. 2010 years
Excavation and cofferdam inspection reportsCDM 2024 reg. 26On site until completion, plus 3 months
Personal exposure monitoring (chemicals)USECHH reg. 2630 years (other monitoring 5 years)
Health surveillance recordsUSECHH reg. 2730 years
Noise risk assessment reportsNoise Regs 2019 reg. 1130 years
Audiometric test reportsNoise Regs 2019 reg. 11Employment plus 5 years

Audit

An OSH audit is a systematic, independent and documented examination of whether the OSH management system meets its planned arrangements and criteria, such as ISO 45001, the client's requirements, the construction phase plan or the law, and whether it is effective.

FeatureInspectionAudit
FocusPhysical conditions and behaviour nowThe management system over time
FrequencyDaily or weeklyPlanned periodically, for example quarterly or six-monthly
Done bySSS, supervisors, committeeTrained auditors independent of the area audited
EvidenceWhat is seen on the walkDocuments, records, interviews and observation, sampled against criteria
OutputDefect list, immediate correctionsFindings (nonconformities, observations), corrective action plan, management review input

A typical internal audit cycle:

  1. plan the scope and criteria
  2. hold an opening meeting
  3. review documents
  4. sample site evidence and interview staff
  5. grade the findings
  6. hold a closing meeting
  7. issue the report
  8. follow up corrective actions until they are closed

SHC Regulations regulation 15(b) requires the committee to consider safety audits submitted to it. Audit results also feed the PDCA Act stage.

Test Your Knowledge

A 6-metre birdcage scaffold collapses overnight on a construction site and nobody is injured. Under NADOPOD 2004, what must the employer do?

A

Record it in the site diary only, because there were no injuries to anyone

B

Wait for the annual summary and include it in the return before 31 January

C

Report it only if repair costs exceed RM10,000

D

Notify DOSH immediately and send a written report within seven days

Test Your Knowledge

After a fatal fall, the project manager wants the damaged edge protection removed at once so concreting can continue. Under regulation 9 of NADOPOD 2004, when may the scene be disturbed without authorisation?

A

When the project faces liquidated damages for delay

B

When photographs, measurements and witness statements of the scene have been taken by the safety team

C

Only to save life or relieve suffering, keep access to an essential service, or prevent serious damage

D

Whenever the SSS signs a written release after inspecting the area

Test Your Knowledge

Which activity is an audit rather than an inspection?

A

The SSS's morning walk to check guardrails, floor-opening covers and housekeeping on every level

B

A planned, independent review of whether the site's OSH management system meets ISO 45001 criteria

C

A rigger's pre-use check of slings, shackles and hooks before the first lift of the day

D

The supervisor's scaffold tag check before the painting crew climbs up