8.2 Three-Phase Per-Unit Network Modeling & Equipment Impedance Conversion

Key Takeaways

  • Power transformers partition a transmission and distribution network into distinct voltage zones, where base voltages in adjacent zones must strictly scale by the transformer nominal line-to-line turns ratio (Vbase,2=Vbase,1×N2/N1V_{base,2} = V_{base,1} \times N_2 / N_1).

  • Manufacturer percent impedance is converted to per-unit by dividing by 100 (%Z→Zpu=%Z/100\%Z \to Z_{pu} = \%Z / 100), and transformer per-unit leakage reactance remains invariant whether referenced to primary or secondary windings on transformer base.

  • Loads are modeled in per-unit based on bus characteristics: constant power (Spu=Ppu+jQpuS_{pu} = P_{pu} + jQ_{pu}), constant impedance (Zpu=∣Vpu∣2/Spu∗Z_{pu} = |V_{pu}|^2 / S_{pu}^*), or constant current (Ipu=I0∠(θV−θ)I_{pu} = I_0 \angle (\theta_V - \theta)).

  • Three-phase symmetrical fault current in physical amperes is evaluated directly from per-unit Thevenin impedance via Isc=Ibase/∣Zth,pu∣=Sbase/(3Vbase,LL∣Zth,pu∣)I_{sc} = I_{base} / |Z_{th,pu}| = S_{base} / (\sqrt{3} V_{base,LL} |Z_{th,pu}|).

Last updated: August 2026

8.2 Three-Phase Per-Unit Network Modeling & Equipment Impedance Conversion

Key Exam Takeaway: Power transformers partition networks into distinct voltage zones where the base voltage of each zone is dictated by the transformer turns ratio (Vbase,2=Vbase,1×N2N1V_{base,2} = V_{base,1} \times \frac{N_2}{N_1}). When modeling loads for fault studies, constant impedance representations are calculated as Zload,pu=∣Vpu∣2Sload,pu∗Z_{load,pu} = \frac{|V_{pu}|^2}{S_{load,pu}^*}. Symmetrical three-phase fault currents are solved directly in per-unit using Isc,pu=VfZth,puI_{sc,pu} = \frac{V_f}{Z_{th,pu}} and converted to physical amperes via Isc=Isc,pu×IbaseI_{sc} = I_{sc,pu} \times I_{base}.


1. Multi-Voltage Level Network Partitioning & Voltage Zones

A complete power system is an interconnected network of synchronous machines, transformers, overhead transmission lines, underground cables, industrial motors, and static loads. When modeling the positive-sequence network in per-unit, the fundamental rule is that power transformers serve as the structural boundaries between voltage zones.

Rules for Establishing Network Zones

  1. Single System Power Base: A single value of Sbase,3ϕS_{base,3\phi} (such as 100 MVA100\text{ MVA}) applies uniformly to all zones across the entire network.
  2. Voltage Base Transformation: The base voltage in Zone k+1k+1 is derived from Zone kk through the rated voltage ratio of the interconnecting transformer: Vbase,k+1=Vbase,k×(VT,winding 2VT,winding 1)V_{base,k+1} = V_{base,k} \times \left(\frac{V_{T,winding\ 2}}{V_{T,winding\ 1}}\right)
  3. Transformer Elimination: Once all equipment impedances are converted to their respective zone bases, all ideal transformers disappear from the positive-sequence circuit diagram. The multi-voltage network reduces to a single contiguous impedance network operating at a nominal 1.0 pu1.0\text{ pu} voltage.

2. Per-Unit Modeling of Power System Components

Synchronous Generators

Synchronous generators are modeled as an ideal internal electromotive force (EMF) EgE_g in series with an internal reactance:

  • Subtransient Reactance (Xd′′X_d''): Governs current during the first 11 to 55 cycles after fault initiation (00 to 80 ms80\text{ ms}). Used for circuit breaker momentary ratings and fast-acting protective device sizing.
  • Transient Reactance (Xd′X_d'): Governs current from 55 to 3030 cycles (0.10.1 to 0.5 s0.5\text{ s}). Used for transient stability studies and medium-speed relay operations.
  • Synchronous Reactance (XdX_d): Governs steady-state fault and power flow conditions (t>1.0 st > 1.0\text{ s}).
Per-Unit Model: Eg′′=Vterm,pu+Igen,pu(Ra+jXd′′)\text{Per-Unit Model: } E_g'' = V_{term,pu} + I_{gen,pu}(R_a + jX_d'')

For fault studies, generator armature resistance RaR_a is negligible (Ra≪Xd′′R_a \ll X_d''), and the prefault internal voltage is typically taken as Eg′′≈1.0∠0∘ puE_g'' \approx 1.0 \angle 0^\circ\text{ pu}.

Power Transformers

Two-winding power transformers are represented by their equivalent series leakage impedance ZT=RT+jXTZ_T = R_T + jX_T on the system base:

  • Winding resistance RTR_T is typically 0.5%0.5\% to 2%2\% of XTX_T and is often neglected in short-circuit studies (ZT≈jXTZ_T \approx jX_T).
  • Shunt magnetizing branch (Rc∥jXmR_c \parallel jX_m) has high impedance (>100 pu> 100\text{ pu}) and is omitted during fault analysis.
  • Standard ANSI/IEEE Δ−Y\Delta - \text{Y} Phase Shift: Positive-sequence voltages and currents on the high-voltage (HV) side lead corresponding quantities on the low-voltage (LV) side by 30∘30^\circ: VHV=VLV∠+30∘\mathbf{V}_{HV} = \mathbf{V}_{LV} \angle +30^\circ

Transmission Lines and Cables

Transmission lines are represented by their series impedance (Zseries=R+jXZ_{series} = R + jX) and total shunt susceptance (jBjB):

  • Short Lines (<50 miles< 50\text{ miles}): Shunt capacitance is negligible; modeled as pure series impedance Zline,pu=(R+jX)/Zbase,zoneZ_{line,pu} = (R + jX) / Z_{base,zone}.
  • Medium Lines (50−150 miles50 - 150\text{ miles}): Modeled using the nominal π\pi-equivalent circuit with half of the line charging susceptance (jB/2jB/2) lumped at each bus terminal.

Load Modeling in Per-Unit

In power system analysis, electrical loads are represented under three primary modeling conventions:

┌───────────────────────────────────────────────────────────────────────────────┐
│                            PER-UNIT LOAD MODELS                               │
├───────────────────────┬───────────────────────────────┬───────────────────────┤
│ Constant Power (PQ)   │ Constant Current (I)          │ Constant Impedance (Z)│
│ S_pu = P_pu + jQ_pu   │ |I_pu| = Constant             │ Z_pu = |V_pu|² / S_pu*│
│ I_pu = (S_pu/V_pu)*   │ P_pu ∝ |V_pu|, Q_pu ∝ |V_pu|  │ P, Q ∝ |V_pu|²        │
│ (Power Flow Analysis) │ (Arc Furnaces, Discharge)     │ (Fault Studies)       │
└───────────────────────┴───────────────────────────────┴───────────────────────┘

For short-circuit analysis and linear network reduction, loads are converted to constant per-unit impedance at nominal voltage (Vpu=1.0V_{pu} = 1.0):

Zload,pu=∣Vbus,pu∣2Sload,pu∗=∣Vbus,pu∣2Pload,pu−jQload,pu=Rload,pu+jXload,puZ_{load,pu} = \frac{|V_{bus,pu}|^2}{S_{load,pu}^*} = \frac{|V_{bus,pu}|^2}{P_{load,pu} - jQ_{load,pu}} = R_{load,pu} + jX_{load,pu}

3. End-to-End Three-Phase Symmetrical Fault Analysis

The per-unit system reduces complex three-phase short-circuit calculations to basic single-phase Thevenin equivalent circuits:

  1. Positive-Sequence Impedance Diagram: Replace all generators and utility grid interconnections with ideal voltage sources (1.0∠0∘ pu1.0 \angle 0^\circ\text{ pu}) behind their subtransient reactances, tied to the reference neutral.
  2. Thevenin Impedance (Zth,puZ_{th,pu}): De-energize all ideal voltage sources (short to ground) and compute the driving-point impedance viewed from the faulted bus: Zth,pu=Rth,pu+jXth,pu≈jXth,puZ_{th,pu} = R_{th,pu} + jX_{th,pu} \approx jX_{th,pu}
  3. Per-Unit Symmetrical Fault Current (If,puI_{f,pu}): If,pu=VfZth,pu=1.0∠0∘jXth,pu=−j1.0Xth,pu[pu]I_{f,pu} = \frac{V_f}{Z_{th,pu}} = \frac{1.0 \angle 0^\circ}{jX_{th,pu}} = -j \frac{1.0}{X_{th,pu}} \quad [\text{pu}]
  4. Three-Phase Short-Circuit Apparent Power (Ssc,3ϕS_{sc,3\phi}): Ssc,3ϕ=Sbase,3ϕ∣Zth,pu∣=Sbase,3ϕXth,pu[MVA]S_{sc,3\phi} = \frac{S_{base,3\phi}}{|Z_{th,pu}|} = \frac{S_{base,3\phi}}{X_{th,pu}} \quad [\text{MVA}]
  5. Actual RMS Symmetrical Fault Current (If,actualI_{f,actual}): If,actual=If,pu×Ibase,fault_zone=1.0Xth,pu×(Sbase,3ϕ3⋅Vbase,fault_zone)[Amperes]I_{f,actual} = I_{f,pu} \times I_{base,fault\_zone} = \frac{1.0}{X_{th,pu}} \times \left(\frac{S_{base,3\phi}}{\sqrt{3} \cdot V_{base,fault\_zone}}\right) \quad [\text{Amperes}]

4. Comprehensive Multi-Bus Industrial System Worked Example

System Configuration & Parameters

An industrial manufacturing complex is supplied by a utility generation source through a transmission line and plant substation:

  • Utility Generator G1 (Bus 1): Rated 50 MVA50\text{ MVA}, 13.8 kV13.8\text{ kV}, Xd′′=0.15 puX_d'' = 0.15\text{ pu}.
  • GSU Transformer T1 (Buses 1–2): Rated 60 MVA60\text{ MVA}, 13.8 kV/138 kV13.8\text{ kV} / 138\text{ kV}, XT1=0.09 puX_{T1} = 0.09\text{ pu}.
  • Transmission Line TL1 (Buses 2–3): 138 kV138\text{ kV}, 15 miles15\text{ miles}, total series reactance Xline=19.044 ΩX_{line} = 19.044\ \Omega (resistance neglected).
  • Substation Transformer T2 (Buses 3–4): Rated 25 MVA25\text{ MVA}, 138 kV/4.16 kV138\text{ kV} / 4.16\text{ kV}, XT2=0.0625 puX_{T2} = 0.0625\text{ pu} (6.25%6.25\%).
  • Plant Induction Motor Load M1 (Bus 4): Totaling 20 MVA20\text{ MVA}, rated 4.16 kV4.16\text{ kV}, with subtransient reactance Xm′′=0.20 puX_m'' = 0.20\text{ pu} on motor base.

Objective: Using a system base of Sbase=100 MVAS_{base} = 100\text{ MVA} and Vbase,1=13.8 kVV_{base,1} = 13.8\text{ kV}, calculate:

  1. Base voltages and base currents in all zones.
  2. All component per-unit reactances on the common 100 MVA100\text{ MVA} system base.
  3. The total symmetrical subtransient fault current (IscI_{sc}) in physical Amperes for a solid 3-phase fault at the 4.16 kV4.16\text{ kV} industrial bus (Bus 4).
  Bus 1 (13.8 kV)     Bus 2 (138 kV)               Bus 3 (138 kV)    Bus 4 (4.16 kV)
 ┌──────────────┐     ┌───────────┐                ┌───────────┐     ┌─────────────┐
 │ Generator G1 ├──┬──┤ T1 (GSU)  ├───[TL1: 15 mi]─┤ T2 (Plant)├──┬──┤   FAULT F1  │
 │   50 MVA     │  │  │ 60 MVA    │   X=19.044 Ω   │ 25 MVA    │  │  │      X      │
 │   13.8 kV    │  │  │ 13.8/138  │                │ 138/4.16  │  │  ├─────────────┤
 │  X'' = 0.15  │  │  │ X = 0.09  │                │ X = 0.0625│  │  │  Motor M1   │
 └──────────────┘  │  └───────────┘                └───────────┘  │  │  20 MVA     │
                   │                                              │  │  X'' = 0.20 │
                 Zone 1                                         Zone 2 └─────────────┘
                (13.8 kV)                                      (138 kV)     Zone 3
                                                                           (4.16 kV)

Step-by-Step Solution

Step 1: Establish Zone Voltage and Current Bases

  • Zone 1 (13.8 kV13.8\text{ kV}): Vbase,1=13.8 kV,Ibase,1=100 MVA3×13.8 kV=4,183.7 AV_{base,1} = 13.8\text{ kV}, \quad I_{base,1} = \frac{100\text{ MVA}}{\sqrt{3} \times 13.8\text{ kV}} = 4,183.7\text{ A}
  • Zone 2 (138 kV138\text{ kV}): Vbase,2=13.8 kV×(138 kV13.8 kV)=138 kV,Ibase,2=100 MVA3×138 kV=418.37 AV_{base,2} = 13.8\text{ kV} \times \left(\frac{138\text{ kV}}{13.8\text{ kV}}\right) = 138\text{ kV}, \quad I_{base,2} = \frac{100\text{ MVA}}{\sqrt{3} \times 138\text{ kV}} = 418.37\text{ A} Zbase,2=(138 kV)2100 MVA=190.44 ΩZ_{base,2} = \frac{(138\text{ kV})^2}{100\text{ MVA}} = 190.44\ \Omega
  • Zone 3 (4.16 kV4.16\text{ kV}): Vbase,3=138 kV×(4.16 kV138 kV)=4.16 kV,Ibase,3=100 MVA3×4.16 kV=13,878.6 AV_{base,3} = 138\text{ kV} \times \left(\frac{4.16\text{ kV}}{138\text{ kV}}\right) = 4.16\text{ kV}, \quad I_{base,3} = \frac{100\text{ MVA}}{\sqrt{3} \times 4.16\text{ kV}} = 13,878.6\text{ A}

Step 2: Convert Component Reactances to 100 MVA Base

  • Generator G1: XG1,pu=0.15×(13.813.8)2×(10050)=0.3000 puX_{G1,pu} = 0.15 \times \left(\frac{13.8}{13.8}\right)^2 \times \left(\frac{100}{50}\right) = 0.3000\text{ pu}
  • Transformer T1: XT1,pu=0.09×(13.813.8)2×(10060)=0.1500 puX_{T1,pu} = 0.09 \times \left(\frac{13.8}{13.8}\right)^2 \times \left(\frac{100}{60}\right) = 0.1500\text{ pu}
  • Transmission Line TL1: XTL1,pu=XactualZbase,2=19.044 Ω190.44 Ω=0.1000 puX_{TL1,pu} = \frac{X_{actual}}{Z_{base,2}} = \frac{19.044\ \Omega}{190.44\ \Omega} = 0.1000\text{ pu}
  • Transformer T2: XT2,pu=0.0625×(138138)2×(10025)=0.2500 puX_{T2,pu} = 0.0625 \times \left(\frac{138}{138}\right)^2 \times \left(\frac{100}{25}\right) = 0.2500\text{ pu}
  • Induction Motor Load M1: XM1,pu=0.20×(4.164.16)2×(10020)=1.0000 puX_{M1,pu} = 0.20 \times \left(\frac{4.16}{4.16}\right)^2 \times \left(\frac{100}{20}\right) = 1.0000\text{ pu}

Step 3: Calculate Thevenin Equivalent Impedance at Faulted Bus 4

The total impedance is formed by the utility supply branch in parallel with the motor back-feed branch:

  • Utility Supply Branch Impedance (XsysX_{sys}): Xsys=XG1+XT1+XTL1+XT2=0.30+0.15+0.10+0.25=0.8000 puX_{sys} = X_{G1} + X_{T1} + X_{TL1} + X_{T2} = 0.30 + 0.15 + 0.10 + 0.25 = 0.8000\text{ pu}
  • Motor Branch Impedance (XmotorX_{motor}): Xmotor=XM1=1.0000 puX_{motor} = X_{M1} = 1.0000\text{ pu}
  • Parallel Equivalent Thevenin Reactance (XthX_{th}): Xth,pu=Xsys×XmotorXsys+Xmotor=0.80×1.000.80+1.00=0.801.80=0.4444 puX_{th,pu} = \frac{X_{sys} \times X_{motor}}{X_{sys} + X_{motor}} = \frac{0.80 \times 1.00}{0.80 + 1.00} = \frac{0.80}{1.80} = 0.4444\text{ pu}

Step 4: Compute Fault Quantities

  • Per-Unit Symmetrical Fault Current: If,pu=VfXth,pu=1.0 pu0.4444 pu=2.2500 puI_{f,pu} = \frac{V_f}{X_{th,pu}} = \frac{1.0\text{ pu}}{0.4444\text{ pu}} = 2.2500\text{ pu}
  • Short-Circuit MVA: Ssc,3ϕ=SbaseXth,pu=100 MVA0.4444=225.0 MVAS_{sc,3\phi} = \frac{S_{base}}{X_{th,pu}} = \frac{100\text{ MVA}}{0.4444} = 225.0\text{ MVA}
  • Actual Physical RMS Symmetrical Short-Circuit Current: If,actual=If,pu×Ibase,3=2.2500×13,878.6 A=31,227 A=31.23 kAI_{f,actual} = I_{f,pu} \times I_{base,3} = 2.2500 \times 13,878.6\text{ A} = 31,227\text{ A} = 31.23\text{ kA}

5. Critical Exam Tips & Common Traps

Warning

Exam Trap 1: Neglecting Motor Contribution to Faults. Induction and synchronous motors act as generators during the first few cycles of a fault due to trapped rotor magnetic flux. In short-circuit duty calculations, always place motor subtransient reactances in parallel with the utility grid supply.

Caution

Exam Trap 2: Using the Wrong Base Current for Physical Conversion. When converting per-unit fault current to physical Amperes, you must multiply by the base current of the specific zone where the fault occurs (Ibase,3I_{base,3} at the 4.16 kV4.16\text{ kV} bus), not the generator bus or transmission line base current.

Loading diagram...
Positive-Sequence Per-Unit Reactance Diagram of Multi-Bus Industrial System
Test Your Knowledge

A power system consists of a generator in Zone 1 (13.8 kV base), connected to a step-up transformer T1 rated 13.8 kV : 230 kV, a transmission line in Zone 2, and a step-down transformer T2 rated 220 kV : 4.16 kV feeding Zone 3. If the base voltage in Zone 1 is selected as 13.8 kV, what is the base voltage in Zone 3?

A

4.16 kV

B

4.35 kV

C

3.98 kV

D

4.80 kV

Test Your Knowledge

A 3-phase industrial load connected to a 4.16 kV bus consumes 10 MVA at 0.80 power factor lagging. The system base is 100 MVA and 4.16 kV. If the bus voltage is 1.0 pu, what is the equivalent constant impedance of this load in per-unit?

A

0.100 + j0.075 pu

B

8.000 + j6.000 pu

C

0.080 + j0.060 pu

D

0.800 + j0.600 pu

Test Your Knowledge

A 3-phase 13.8 kV substation bus has a total equivalent Thevenin per-unit reactance of X_th = 0.050 pu on a 100 MVA base. What is the physical symmetrical RMS three-phase short-circuit current at this bus assuming a prefault voltage of 1.0 pu?

A

83.67 kA

B

4.18 kA

C

48.31 kA

D

144.92 kA

Sections you finish are checked off in the contents.