8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment
Key Takeaways
Design demand is population × per capita consumption, scaled by peak factors for the maximum day and peak hour.
Distribution storage combines equalizing storage, fire reserve and emergency reserve.
Pump water power is γQH, and brake power is γQH divided by pump efficiency.
A settling basin removes particles whose settling velocity exceeds the overflow rate Q/A, independent of tank depth.
Geometric population growth projects P = P₀(1 + r)ⁿ, while arithmetic growth adds a constant number per year.
8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment
The 2022 HGE table of specifications gives Water Supply 8% of the subject, or 4 of its 50 items. That is as much as buoyancy and flotation, and more than hydrodynamics. The items are computational and draw directly on pipe flow (Section 8.3) and on pumps and the energy equation (Section 8.1).
Population Forecasting
| Method | Formula | Use |
|---|---|---|
| Arithmetic | Mature towns with steady growth | |
| Geometric (uniform percentage) | Young, growing towns | |
| Exponential (continuous) | Equivalent to geometric growth with continuous compounding | |
| Declining growth rate | Growth slows as the population approaches a saturation value | Large cities |
Example. A town of 40,000 grew 3% per year. Projected to a 20-year design period: . An arithmetic increase of 1,200 per year would give .
Water Demand and Peaking Factors
Average day demand (ADD):
Here includes domestic use, commercial and institutional use, and an allowance for non-revenue water (leakage).
| Demand condition | Typical peaking factor | Used for |
|---|---|---|
| Maximum day demand (MDD) | about 1.2 to 1.5 × ADD | Source, treatment plant and transmission main capacity |
| Peak hour demand (PHD) | about 1.5 to 3.0 × ADD | Distribution network sizing |
| Fire demand | Fire flow for a set duration, added to MDD | Distribution mains, hydrants, fire reserve |
Smaller communities have higher peak factors, because their demand is less spread out over time.
Example. A population of 72,000 uses 150 L/capita/day.
- ADD .
- With MDD = 1.3 × ADD, MDD .
- With PHD = 2.0 × ADD, PHD .
Storage
Elevated tanks and ground reservoirs hold three volumes:
- Equalizing (operational) storage covers hourly demand above the steady supply rate. It is found from a mass diagram: plot cumulative supply and cumulative demand over a day. The required storage is the largest surplus plus the largest deficit, measured from the supply line. Rule-of-thumb values are often around 15% to 25% of MDD.
- Fire reserve equals fire flow times fire duration.
- Emergency reserve covers power or source outages.
Example. A pumping plant delivers a steady for 24 hours. Cumulative demand exceeds cumulative supply by at most at 8 PM, and falls below it by at most at 5 AM. Equalizing storage is .
Pressure. An elevated tank's water surface sets the hydraulic grade line. Residual pressure at a service point is the HGL elevation minus ground elevation, less head losses. Distribution systems typically aim to keep enough residual pressure for upper-floor fixtures without excessive pressure that drives leakage.
Pumping
Total dynamic head is .
Example. A pump delivers from a well with its water level at elevation 12 m to a tank surface at elevation 52 m. Pipe losses total 6 m, and the pump efficiency is 0.75.
- .
- Brake power .
Cavitation. The available net positive suction head must exceed the pump's required NPSH, so suction lifts are kept short.
Distribution Systems
Layouts:
- Branching (tree) systems are simple, but they have dead ends with stagnant water and a single supply path.
- Grid or loop systems give two-way flow, better pressure and reliability, and are analyzed by the Hardy Cross method (Section 8.3).
Pipe sizing. Choose a diameter so the friction slope keeps pressures acceptable and velocities moderate, roughly 0.6 to 2 m/s. With Hazen-Williams:
Example. A main carries the peak-hour flow of , and the allowable head loss is 12 m with . Solving for D:
So . Select the next standard size, 450 mm.
Treatment Hydraulics
| Process | Design relation |
|---|---|
| Plain sedimentation | Overflow (surface loading) rate . Particles with settling velocity are fully removed, and smaller ones are removed in the ratio . Detention time . |
| Stokes' law for discrete particles | |
| Coagulation and flocculation | Chemicals such as alum destabilize fine particles, and slow mixing builds flocs that settle |
| Filtration | Rapid sand filters run at roughly to and are cleaned by backwashing; slow sand filters run far slower and rely on a biological layer |
| Disinfection | Chlorination; effectiveness depends on concentration × contact time (CT) |
Drinking-water quality limits in the Philippines are set by the Department of Health's Philippine National Standards for Drinking Water.
Example. A rectangular settling tank treats at an overflow rate of .
- Surface area: .
- With a depth of 3.5 m, detention time is .
A town of 25,000 is projected to grow geometrically at 2.5% per year. What is its population after 20 years?
40,965
43,859
37,500
38,750
A settling tank must treat 0.10 m³/s at an overflow rate of 24 m³/m²/day. What surface area is required?
240 m²
600 m²
360 m²
420 m²
A pump lifts 0.05 m³/s through a total dynamic head of 40 m. If the pump efficiency is 0.80, what brake power is required?
24.5 kW
19.6 kW
31.4 kW
15.7 kW
Sections you finish are checked off in the contents.