6.2 Construction Equipment, Formwork, and Construction Methods
Key Takeaways
A balanced haul fleet equals truck cycle time divided by loading time; extra trucks only queue when the loader already governs.
Crane capacity is read from the load chart at the actual operating radius, and gross load includes hook block and rigging.
Prefabricated vertical drains speed consolidation of soft clay because consolidation time varies with the square of the drainage path.
Balanced cantilever and incremental launching build long-span bridges without full-height falsework.
ACI 347 limits lateral formwork pressure to between 30 C_w kPa and the full liquid head γh.
6.2 Construction Equipment, Formwork, and Construction Methods
Construction equipment and methods form the last area of the AMSTHC table of specifications, Construction Equipment and Methods. Its five competencies cover ground engineering and excavating equipment; concrete production and road-pavement equipment; bridge construction methods; production of excavating, lifting, loading and hauling equipment; and compressed air and water systems. This section covers all five, together with formwork pressure, a frequent construction problem. Safety regulation is treated separately in the construction safety and health section.
Heavy Equipment Productivity & Earthmoving Mechanics
Earthmoving operations involve excavating, loading, hauling, dumping, and compacting soil or blasted rock. Soil volume changes across these phases:
- Bank Measure (): Soil in its natural, undisturbed in-situ state.
- Loose Measure (): Soil after excavation, which expands in volume due to voids (Swell):
- Compacted Measure (): Soil after mechanical compaction, which is less than bank volume (Shrinkage):
1. Hydraulic Excavator & Backhoe Productivity
Hourly production of an excavator loading haul units is computed by:
Where:
- = hourly production in loose cubic meters () or bank cubic meters ()
- = bucket payload per cycle (, where is the bucket fill factor, e.g., for blasted rock to for moist loam)
- = total cycle time in seconds (dig + swing loaded + dump + swing empty, typically )
- = operational efficiency factor (e.g., )
2. Bulldozer Productivity
Bulldozer output is governed by blade capacity and pushing distance:
Where blade capacity ( = blade width, = blade height) and .
Haul Fleet Matching & Loader-Truck Balancing
A critical objective in earthmoving economics is matching the number of haul trucks to the primary loading unit (excavator or wheel loader) to eliminate machine idle time.
Mathematical Formulation
- Number of Loader Passes per Truck (): (Round to the nearest whole integer or load limit).
- Loading Time per Truck (): Where is the excavator cycle time.
- Total Round-Trip Truck Cycle Time (): Where is haul time, is dump and maneuver time, and is empty return time.
- Balanced Fleet Size ():
Operational Implications of Fleet Size ()
- If (Under-trucked): The loader is underutilized and must wait for returning trucks. The truck fleet governs production:
- If (Over-trucked): The loader operates at 100% capacity, but haul trucks form queues at the loading pit. The loader governs production:
Soil Compaction Equipment & Roller Selection
Specifications commonly require a relative compaction of about 95% to 100% of a laboratory maximum dry density. Meeting it requires matching roller mechanics to soil type:
| Compactor Type | Dominant Compactive Action | Most Suitable Soil Types | Field Applications |
|---|---|---|---|
| Smooth-Drum (Static/Vibratory) | Pressure and dynamic vibration | Well-graded gravels, sands, crushed aggregate base courses | Pavement subbase/base courses, asphalt paving breakdown passes |
| Pneumatic-Tired (Rubber-Tired) | Static weight and kneading action | Well-graded granular soils with fines, bituminous asphalt courses | Intermediate asphalt rolling, base course surface sealing |
| Sheepsfoot / Padfoot (Tamping) | High unit contact pressure, kneading | Cohesive clays, high-plasticity silts | Embankment core fills, dam cores; compacts from bottom to top |
| Grid / Segmented Rollers | High crushing impact | Weathered rock, coarse dry gravels | Breaking down oversize rockfill embankments |
| Hand-Operated Rammers / Plates | High-frequency impact / vibration | All soil types in confined zones | Utility trench backfill, retaining wall abutments, column pads |
Lateral Pressure of Fresh Concrete on Formwork (ACI 347)
Freshly poured concrete initially behaves as a dense hydrostatic fluid. As cement hydration initiates, internal shearing resistance develops, causing lateral pressure to peak and then stabilize.
According to ACI 347 (Guide to Formwork for Concrete), the lateral design pressure depends on placement rate , concrete temperature , and admixture chemistry:
1. Maximum Hydrostatic Pressure (Envelope Limit)
At any point, lateral pressure cannot exceed full liquid head:
Where is concrete unit weight (typically ) and is total formwork height in meters.
2. Formwork Design Formulas for Walls
- For placement rate and vertical placement height :
- For placement rate or all walls where :
- Mandatory Limits: Under all conditions, must satisfy:
Where:
- = maximum lateral pressure (kPa)
- = rate of concrete placement (m/hr)
- = concrete mix temperature ()
- = unit weight coefficient ( for normal-weight concrete )
- = chemistry coefficient ( for Type I cement without retarding admixtures; for slag or fly ash blends)
Lifting Equipment and Crane Capacity
Cranes are selected from the manufacturer's load chart, which gives rated capacity as a function of boom length and operating radius. The radius is the horizontal distance from the center of rotation to the load hook.
- Rated capacity falls quickly as radius increases, because the tipping moment is load × radius. The chart may also be governed by the structural strength of the boom at short radii.
- Gross load includes the load itself plus the hook block, slings, spreader beams and other rigging.
- Industry practice limits tipping-governed ratings to a fraction of the actual tipping load. For mobile cranes on outriggers this is commonly 85%; for crawler cranes it is commonly 75%.
- Tower cranes are used for high-rise building work. Lifting cycles are estimated like loader cycles: hook time, swing, landing and return.
Production example. A tower crane places concrete buckets of on a 6-minute cycle at 50 working minutes per hour. Hourly placement is .
Ground Engineering Methods
Excavations below the water table, or in weak soils, need groundwater control, excavation support, or ground improvement before structural work can start.
| Problem | Common method | How it works |
|---|---|---|
| Groundwater in sands and gravels | Wellpoints; deep wells with submersible pumps | Lowers the water table below the excavation base by pumping from closely spaced wellpoints or larger wells |
| Groundwater in silts and clays | Sumps and ditches; vacuum wellpoints; cut-off walls | Low-permeability soils drain slowly, so cut-offs or vacuum assistance are used |
| Vertical excavation sides | Steel sheet piles; soldier piles and timber lagging; contiguous, secant or diaphragm walls | Retains soil and, for sheet piles and diaphragm walls, also cuts off water |
| Deep excavations | Struts, walers, and ground anchors (tiebacks) | Brace the retaining wall; anchors leave the excavation clear for work |
| Loose sands (settlement, liquefaction) | Vibro-compaction; dynamic compaction | Densifies granular soil by vibration or repeated heavy tamping |
| Soft clays | Preloading with prefabricated vertical drains; stone columns | Drains shorten the drainage path (), so consolidation happens before construction |
| Weak or permeable ground | Permeation, jet or compaction grouting | Fills voids or forms soil-cement columns to strengthen and seal the ground |
Concrete Production and Pavement Construction Equipment
| Operation | Equipment | Notes for estimating and control |
|---|---|---|
| Batching | Central or ready-mix batch plant | Rated output in ; batches weighed by mass |
| Transport | Transit mixer trucks (typically to ) | Fleet sized like haul trucks: trucks needed equals round-trip time divided by unloading time |
| Placing | Concrete pumps (boom or line), buckets with cranes, chutes | Pump output depends on pipeline length, bends and vertical lift |
| Consolidation | Internal (poker) vibrators, form vibrators, vibrating screeds | Removes entrapped air; over-vibration causes segregation |
| Concrete pavement | Slipform paver or fixed-form paver, texturing and curing machine, joint saws | Joints are sawn early to control shrinkage cracking |
| Asphalt pavement | Asphalt mixing plant, dump trucks, asphalt paver, steel-wheel and pneumatic rollers | Breakdown, intermediate and finish rolling while the mat is within its compaction temperature range |
Transit mixer example. A plant loads a mixer in 6 minutes. The round trip, including discharge at the pour, takes 54 minutes. Trucks needed for continuous placing: , so the plant can deliver if 9 trucks are assigned.
Bridge Construction Methods
| Method | Description | Typical application |
|---|---|---|
| Cast-in-place on falsework | Formwork supported on shoring from the ground | Short spans over dry land or shallow water |
| Precast girder erection | Prestressed girders placed by mobile cranes or a launching gantry, then a deck is cast | Most short- and medium-span highway bridges and flyovers |
| Balanced cantilever | Segments cast or erected symmetrically from each pier using form travelers | Long spans over rivers and deep valleys without falsework |
| Incremental launching | Deck segments cast behind an abutment and pushed forward with jacks over the piers | Straight or constant-curvature alignments with uniform depth |
| Cable-stayed or suspension erection | Deck built outward from the towers while stays or hangers are installed | Long spans |
Substructure work uses cofferdams for footings in water, together with bored piles (drilled shafts) or driven piles for foundations.
Compressed Air and Water Systems
Compressed air powers rock drills, jackhammers, sandblasters, pneumatic tools and grouting equipment. Plan for these points:
- Capacity. Compressor output is rated as free air delivered, in at atmospheric conditions. Total demand equals the sum of each tool's air consumption times a use factor, the fraction of time tools actually run. Add an allowance for leakage.
- Pressure. Most pneumatic tools operate at about to gauge. Pressure drop in long hoses and pipes must be limited by choosing adequate diameters.
- Altitude. At higher elevations the air is thinner, so a compressor delivers less mass of air per minute, and tool demand expressed as free air rises.
- Receivers smooth out demand peaks and allow moisture to condense and be drained.
Water systems on site serve dewatering and supply for mixing, curing and dust control. Pump power follows the same energy principle used in hydraulics:
Example. A dewatering pump lifts against a total dynamic head of at . The required input is .
Step-by-Step Worked Problem Examples
Worked Example 1: Earthmoving Fleet Production Matching
Problem: A mass excavation operation utilizes a hydraulic backhoe with a struck bucket capacity. The soil has a swell of and the bucket fill factor is . The backhoe has a cycle time . A fleet of dump trucks with an individual loose capacity of transports the soil. The haul cycle parameters are:
- Haul time to spoil site:
- Dump and maneuver time:
- Empty return time:
- Overall job efficiency:
Calculate:
- The loader bucket payload and the number of passes required to load one truck.
- The truck loading time and total truck round-trip cycle time .
- The balanced fleet size .
- The hourly production rate in Bank Cubic Meters () if 6 trucks are deployed versus 8 trucks.
Solution:
- Bucket Payload and Passes:
- Loading Time and Truck Cycle:
- Balanced Fleet Size: Exactly 6 trucks create perfect fleet equilibrium with zero loader or truck waiting time.
- Hourly Production Comparison:
- Load Factor:
- Case A: 6 Trucks Deployed (): Loader is 100% utilized. Loading frequency = .
- Case B: 8 Trucks Deployed (): Because the loader was already at 100% capacity with 6 trucks, adding 2 more trucks merely causes trucks to queue at the shovel. The production rate remains governed by the loader at .
Worked Example 2: Formwork Maximum Lateral Pressure (ACI 347)
Problem: A reinforced concrete retaining wall formwork with height is being cast using normal-weight concrete () with Type I Portland cement and no admixtures (). Concrete is placed at a rate and the mix temperature is .
- Calculate the maximum lateral pressure on the formwork.
- Check the minimum and maximum pressure limits per ACI 347.
Solution:
- Check Governing ACI Formula: Since and , use:
- Check Code Boundary Conditions:
- Minimum Pressure Limit:
- Maximum Hydrostatic Limit: Design Lateral Pressure: .
CELE Board Exam Traps & Strategic Checklists
Warning
Load Chart Radius Trap: Crane capacity is read at the actual operating radius, measured horizontally from the center of rotation to the hook. It is not read at the boom length. Gross load includes rigging and the hook block.
Fleet Rounding Trap: If calculated trucks, deploying 6 trucks underutilizes the loader, while deploying 7 trucks causes haul units to queue. Board questions specify whether loader capacity or truck capacity governs.
ACI 347 Hydrostatic Head Cap: In rapid tall pours (e.g., column forms placed at ), calculated pressure frequently exceeds . The formwork lateral pressure can never exceed the hydrostatic head .
A hydraulic excavator with a cycle time of 20 seconds and a bucket payload of 1.5 m³ loose is loading dump trucks with an effective capacity of 12.0 m³ loose. The round-trip haul, dump, and return time for each truck (excluding loading time) is 14.0 minutes. What is the perfectly balanced fleet size N required to keep the excavator 100% utilized with zero idle time?
6.25 trucks
8.0 trucks
6.0 trucks
5.5 trucks
A concrete wall formwork with a height of 3.6 meters is cast with normal-weight concrete (unit weight = 24.0 kN/m³) at a placement rate of R = 1.8 m/hr. The concrete mix temperature is 26°C with Type I cement and no chemical retarders (C_w = 1.0, C_c = 1.0). According to ACI 347, what is the maximum lateral design pressure exerted by the fresh concrete on the formwork?
30.0 kPa
43.6 kPa
39.5 kPa
86.4 kPa
A long-span river bridge must be built without falsework in the river. The deck is built in segments outward from each pier, symmetrically, using form travelers. Which method is this?
Precast girder erection by launching gantry
Incremental launching
Balanced cantilever construction
Cast-in-place construction on full-height falsework
Sections you finish are checked off in the contents.