6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates

Key Takeaways

  • A detailed estimate takes off quantities item by item in standard units and prices each with a unit cost built up from materials, labor and equipment.

  • Concrete is measured in cubic meters, formwork in square meters of contact area, reinforcement in kilograms, and masonry in square meters or pieces.

  • A detailed unit price analysis adds indirect costs (overhead, contingencies, miscellaneous and profit) and VAT to the direct cost of each pay item.

  • Quantity takeoff should follow a consistent sequence and measure net dimensions, with waste allowances added separately.

  • A preliminary estimate uses cost per square meter of floor area or per unit of capacity, while a detailed estimate requires complete plans and specifications.

Last updated: October 2026

6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates

The AMSTHC TOS area "Quantity Surveying" has five competencies:

  1. Understand methods used to prepare building, bridge and construction cost estimates.
  2. Review specifications, plans and details.
  3. Analyze and derive unit costs for labor, material and equipment.
  4. Apply methods of estimating for detailed quantity surveys.
  5. Create a summary of total project costs.

Types of Estimates

EstimateWhen usedBasisTypical accuracy
Conceptual or order-of-magnitudeFeasibilityCost per m² of floor area, per lane-km, per bed or per classroomRough
PreliminarySchematic designMajor elements and assembliesModerate
Detailed (definitive)Bidding and contract awardComplete takeoff of every pay item from final plans and specificationsBest

Bridge estimates are often built per element: foundations by piles, substructure by concrete and reinforcement, superstructure by girders and deck, plus approaches and slope protection.


Reading Plans and Specifications

  • Plans give dimensions and quantities. Specifications give quality, materials, workmanship and the method of measurement and basis of payment for each pay item.
  • Check scale, units and revision status. Reconcile plan and detail conflicts using the contract's order of precedence (Section 1.3).
  • Note items that are easy to miss: excavation and backfill, formwork, lap splices and hooks, embedded items, waterproofing, curing, scaffolding and temporary works.

Quantity Takeoff Methods

Work itemUnitTakeoff rule
Excavationm³Net trench or pit volume, plus working space and slope where required
Concretem³Net volume of each member; do not double-count beam-slab intersections
Formworkm²Contact area of concrete with the forms
Reinforcing steelkgBar length × number × mass per meter, plus laps and hooks
CHB masonrym² or piecesNet wall area × 12.5 blocks/m²
Plastering, paintingm²Net area of each face finished

Worked takeoff: isolated footing and pedestal. The footing is 2.0×2.0×0.40 m2.0 \times 2.0 \times 0.40\text{ m}, and the pedestal is 0.40×0.40×1.20 m0.40 \times 0.40 \times 1.20\text{ m}. Reinforcement is 10-16 mm bars each way in the footing, each 1.85 m1.85\text{ m} long.

  • Concrete: footing 2.0(2.0)(0.40)=1.600 m32.0(2.0)(0.40) = 1.600\text{ m}^3; pedestal 0.40(0.40)(1.20)=0.192 m30.40(0.40)(1.20) = 0.192\text{ m}^3; total 1.792 m31.792\text{ m}^3.
  • Formwork: footing sides 4(2.0)(0.40)=3.20 m24(2.0)(0.40) = 3.20\text{ m}^2; pedestal sides 4(0.40)(1.20)=1.92 m24(0.40)(1.20) = 1.92\text{ m}^2; total 5.12 m25.12\text{ m}^2.
  • Footing bars: 2×10=202 \times 10 = 20 bars × 1.85 m1.85\text{ m} = 37.0 m37.0\text{ m}, which at 1.58 kg/m1.58\text{ kg/m} is 58.5 kg58.5\text{ kg}.

Unit Cost Analysis

The detailed unit price analysis (DUPA) builds the cost of one unit of a pay item:

ComponentHow computed
MaterialsQuantity of each material per unit × unit price, including waste allowance
LaborCrew composition × daily rates ÷ crew output per day
EquipmentEquipment hours per unit × hourly rental or operating rate
Direct costSum of the three
Indirect costsOverhead, contingencies, miscellaneous expenses and contractor's profit, as percentages of direct cost
Value-added taxApplied to direct plus indirect cost
Unit price(Direct + indirect + VAT) per unit

Government agencies prescribe indirect-cost percentages and DUPA formats for their projects. Use the percentages given in the problem or in the current agency guideline.

Example: one cubic meter of concrete. Assume 9 bags of cement at ₱280, 0.50 m30.50\text{ m}^3 sand at ₱1,400 and 1.00 m31.00\text{ m}^3 gravel at ₱1,600.

  • Materials: ₱4,820, from 9(280)+0.5(1,400)+1.0(1,600)=2,520+700+1,6009(280) + 0.5(1{,}400) + 1.0(1{,}600) = 2{,}520 + 700 + 1{,}600.
  • Labor: a crew costing ₱8,000 per day places 8 m38\text{ m}^3 per day, so ₱1,000 per m³.
  • Mixer: ₱300 per m³.
  • Direct cost: ₱6,120.
  • With 15% indirect costs: ₱7,038, from 6,120×1.156{,}120 \times 1.15.
  • With 12% VAT: ₱7,883 per m³, from 7,038×1.127{,}038 \times 1.12.

Summary of Total Project Costs

A bill of quantities lists every pay item with quantity, unit, unit price and amount. The summary groups items by division and adds the following:

LineExample (₱)
Earthworks1,250,000
Concrete and reinforcement6,800,000
Masonry and finishes3,100,000
Steel and roofing2,400,000
Plumbing, electrical and mechanical2,950,000
Total direct cost16,500,000
Indirect costs (overhead, contingency, miscellaneous, profit), say 15%2,475,000
Subtotal18,975,000
VAT 12%2,277,000
Total project cost21,252,000

Cross-check with a cost per square meter. For a 1,200 m21{,}200\text{ m}^2 building, ₱21.25 million is about ₱17,700/m². Compare that with similar recent projects to catch takeoff errors.

Tip

In board problems, read carefully whether VAT and indirect costs are already included in a given unit price, and whether waste allowances are to be added.

Loading diagram...
Building Up a Unit Price
Test Your Knowledge

A wall footing is 0.60 m wide, 0.30 m thick and 25 m long. What volume of concrete is required?

A

0.45 m³

B

15.0 m³

C

7.50 m³

D

4.50 m³

Test Your Knowledge

The direct cost of a pay item is ₱50,000. Indirect costs are 15% of direct cost and VAT is 12% of the subtotal. What is the total price?

A

₱57,500

B

₱63,500

C

₱56,000

D

₱64,400

Test Your Knowledge

How is formwork normally measured for payment?

A

By the cubic meter of concrete placed

B

By the square meter of form surface in contact with the concrete

C

As a lump sum fixed at 10% of concrete cost

D

By the kilogram of form materials delivered

Sections you finish are checked off in the contents.