15.1 Sewer Rehabilitation, Trenchless Renewal and New-Pipe Acceptance Testing

Key Takeaways

  • Rehabilitation choices follow condition grades from CCTV inspection and the cost of the consequences of failure, not just pipe age.

  • Cured-in-place pipe (CIPP) inverts a resin-saturated liner into the host pipe and cures it with hot water, steam or UV light; laterals are then reopened with a robotic cutter.

  • Pipe bursting pulls a new HDPE pipe through the old one, breaking it outward, and can upsize capacity; sliplining inserts a smaller pipe and grouts the annulus.

  • Low-pressure air testing of new gravity sewers times a 1.0 psi drop (from 3.5 to 2.5 psig, adjusted for groundwater), and vacuum testing of manholes times the drop from 10 to 9 inches of mercury.

  • Before cutting roots or obstructions in a sewer, check for cross bores: gas lines accidentally bored through the sewer can be ruptured by cutters.

Last updated: October 2026

From Inspection to Decision

CCTV inspection coded to NASSCO PACP gives each pipe segment structural and operation-and-maintenance grades from 1 (minor) to 5 (failure imminent or occurring). Utilities combine those grades with the consequence of failure to rank work. Consequence factors include pipe depth and size, traffic, nearby waterways and critical customers. Typical outcomes:

ConditionTypical response
Roots, grease, debris onlyCleaning, root control, FOG enforcement
Isolated joint leaks or a single defectSpot repair or chemical grouting
Widespread cracks or leaking joints with the pipe still roundFull-length lining (CIPP)
Undersized pipe or severe deformationPipe bursting (upsizing) or open-cut replacement
Collapse or loss of grade (sags)Open-cut replacement

Trenchless Rehabilitation Methods

Cured-in-place pipe (CIPP). A felt or fiberglass tube saturated with resin (polyester, vinyl ester or epoxy) is inverted into the host pipe with water or air pressure, or pulled in. It is then cured with hot water, steam or UV light, creating a tight-fitting new pipe inside the old one.

  • Cleaning and CCTV beforehand are critical; roots and protruding taps must be removed.
  • After curing, a robotic cutter reinstates service laterals from inside the main.
  • Some resins release styrene during curing. Manage odors and vapors in buildings, and watch confined-space atmospheres.

Pipe bursting. A bursting head is pulled or pushed through the old pipe, fracturing it outward, while a new pipe (usually fusion-welded HDPE) follows behind. It can increase diameter and is good for brittle clay or cast iron. Watch for nearby utilities and for heave or settlement near shallow lines.

Sliplining. A smaller new pipe is inserted into the host and the annular space is grouted. It is simple, but it loses some diameter.

Fold-and-form and close-fit liners. These are thermoplastic pipes folded for insertion, then expanded with heat and pressure.

Spot repairs and grouting. Short sectional liners fix single defects. Chemical grout (acrylamide, acrylate or urethane) is injected at leaking joints using a packer and sealed after an air test of the joint. Grouting controls infiltration but does not add structural strength.

Lateral rehabilitation. Lateral-main connection liners (top hats) and lateral lining seal one of the largest infiltration sources. Private laterals often need a cost-sharing or ordinance-based program.

Manhole Rehabilitation

  • Chimney seals (internal or external rubber sleeves) stop infiltration between the frame and cone.
  • Inflow dishes under lids and raised frames keep street runoff out.
  • Cementitious or epoxy liners restore walls attacked by hydrogen sulfide corrosion.
  • Grout leaking pipe penetrations and rebuild benches and inverts.

Cross-Bore Safety

A cross bore happens when a gas line or other utility installed by horizontal directional drilling passes through a sewer main or lateral. A root cutter or rodder can rupture the gas line, causing explosions inside buildings. Before cutting a blockage, especially in a lateral, check CCTV records and known cross-bore locations. If a sewer backup is near a newer gas service installed by boring, stop and call the gas utility first.

Acceptance Testing of New Sewers and Manholes

TestProcedure (summary)Purpose
Low-pressure air test (ASTM F1417 for plastic, C828 for clay)Plug the section, pressurize to about 4 psig and let it stabilize, then time the drop from 3.5 to 2.5 psig; compare with minimum times for the diameter and length. Raise test pressures by the groundwater backpressure above the pipe (0.433 psi per ft).Finds leaking joints and damaged pipe
Deflection (mandrel) testPull a go/no-go mandrel through flexible pipe, commonly sized for 5 percent deflection, after backfill has settled (often 30 days)Confirms bedding and haunching held the pipe round
Manhole vacuum test (ASTM C1244)Seal the manhole, draw 10 inches of mercury, and time the drop to 9 inches against the specified minimumFinds leaks in joints, pipe connections and walls
CCTV final inspectionVideo the new line before acceptanceConfirms grade (no sags), joints and service connections
Hydrostatic test (force mains)Hold test pressure for a set time and measure makeup waterPressure pipe leakage

Safety during air testing: never stand in front of plugs while pressurized, and use pressure relief devices. A plug blown out at a few psi on a large pipe carries enormous force.

Measuring Results

I/I programs should measure flow before and after rehabilitation, using temporary flow meters and rainfall data, to show results. Rehabilitating public mains alone often removes less infiltration than expected, because water migrates to unrehabilitated laterals. That is why whole-basin approaches including laterals often perform best.

Worked Example: Adjusting an Air Test for Groundwater

Groundwater stands 4.6 feet above the top of a new sewer.

  • Backpressure = 4.6 ft × 0.433 psi/ft ≈ 2.0 psi
  • Instead of timing the drop from 3.5 to 2.5 psig, time the drop from 5.5 to 4.5 psig.

Without the adjustment, groundwater pushing in through a leaking joint would offset the air leaking out and hide the defect. Check the project specification for any maximum test pressure, and plug and brace laterals before the test. Plugs under pressure can blow out with enough force to injure workers, so nobody enters a manhole while a line is pressurized.

Test Your Knowledge

A new 8-inch PVC gravity sewer is being accepted with a low-pressure air test. Which procedure is correct?

A

Pressurize to about 4 psig, then time the drop from 3.5 to 2.5 psig against the minimum

B

Pressurize to 15 psi and hold it for 2 hours with no drop in pressure allowed

C

Fill the pipe with water and measure the overflow at the downstream manhole

D

Pull a deflection mandrel through the pipe while it is held under air pressure

Test Your Knowledge

Which trenchless method can increase the diameter of an undersized clay sewer?

A

Pipe bursting

B

Manhole chimney sealing

C

Cured-in-place pipe

D

Chemical grouting

Test Your Knowledge

A crew is about to run a root cutter through a backed-up lateral where a natural gas service was recently installed by directional boring. What should they do first?

A

Check for a cross bore and contact the gas utility before cutting

B

Proceed quickly with the root cutter to relieve the backup

C

Pour a chemical root killer into the lateral and wait a day

D

Pressurize the lateral with air to locate the exact blockage

Sections you finish are checked off in the contents.