7.4 Bonding Requirements & Main Bonding Jumpers
Key Takeaways
- Bonding (NEC 250 Part V) ensures electrical continuity and conductivity between metal parts to safely conduct any fault current likely to be imposed.
- The Main Bonding Jumper (MBJ) per NEC 250.28 connects the grounded neutral conductor to the service equipment enclosure at each service disconnect.
- System Bonding Jumpers (SBJ) per NEC 250.30 serve the same role for separately derived systems (transformers, generators) and are installed at the source or first disconnecting means.
- Sizing of MBJ, SBJ, and supply-side bonding jumpers is governed by NEC Table 250.102(C)(1) based on the size of the ungrounded service/supply conductors; if phase conductors exceed 1100 kcmil Cu / 1750 kcmil Al, the jumper must be at least 12.5% of the total kcmil area.
- Service raceway terminations and enclosures require specialized bonding methods under NEC 250.92 (bonding bushings, jumpers around concentric knockouts); standard locknuts alone are strictly prohibited for service equipment terminations.
7.4 Bonding Requirements & Main Bonding Jumpers
Exam Focus: Grounding vs. bonding definitions, Main Bonding Jumper (MBJ) function (250.28), System Bonding Jumper (SBJ) for separately derived systems (250.30), sizing per Table 250.102(C)(1), the 12.5% rule for conductors > 1100 kcmil Cu, water/gas/steel bonding rules (250.104), and service equipment knockout bonding (250.92).
While grounding connects electrical circuits to the earth, bonding connects non-current-carrying metallic parts of electrical equipment, raceways, and building systems together. Bonding creates an electrically continuous low-impedance path back to the electrical source so that ground-fault currents can flow unimpeded to trip overcurrent devices instantly.
Main Bonding Jumper (MBJ) & System Bonding Jumper (SBJ)
1. Main Bonding Jumper (NEC 250.28)
In a grounded service, the Main Bonding Jumper (MBJ) connects the grounded system conductor (neutral) to the service equipment enclosure and equipment grounding bus at each service disconnecting means.
- Function: Establishes the fault-return bridge between metallic equipment enclosures and the neutral conductor coming from the utility transformer.
- Permitted Materials (250.28(A)): Wire, busbar, screw (with green finish visible), or similar suitable conductor.
- Un-grounded Systems: On ungrounded systems, the MBJ bonds the service enclosure to the grounding electrode conductor.
MAIN BONDING JUMPER (MBJ) LOCATION
+-------------------------------------------------------------------------+
| UTILITY TRANSFORMER |
| Neutral Center Tap ---------------------------------+ |
+-----------------------------------------------------|-------------------+
| Grounded Neutral
v
+-------------------------------------------------------------------------+
| SERVICE DISCONNECT ENCLOSURE |
| Neutral BusBar <=======[ MAIN BONDING JUMPER ]=======> Enclosure / |
| | (NEC 250.28) Ground Bus |
| v | |
| GEC to Earth v |
| EGC to Panel |
+-------------------------------------------------------------------------+
2. System Bonding Jumper (NEC 250.30)
For a separately derived system (SDS)—such as a step-down transformer or generator—a System Bonding Jumper (SBJ) connects the grounded conductor of the derived system to the equipment grounding conductor and source enclosure. It must be installed at the source of the SDS or at the first disconnecting means, but NOT at both locations.
Sizing MBJs, SBJs, and Supply-Side Jumpers (NEC Table 250.102(C)(1))
Main bonding jumpers, system bonding jumpers, and supply-side bonding jumpers are sized using NEC Table 250.102(C)(1) based on the area of the largest ungrounded supply conductor.
| Size of Largest Ungrounded Supply Conductor or Equivalent Area for Parallel Conductors | Minimum Size of Equipment Bonding Jumper or Main Bonding Jumper |
|---|---|
| Copper (Cu) | Aluminum or Cu-Clad Al |
| 2 AWG or smaller | 1/0 AWG or smaller |
| 1 AWG or 1/0 AWG | 2/0 AWG or 3/0 AWG |
| 2/0 AWG or 3/0 AWG | 4/0 AWG or 250 kcmil |
| Over 3/0 AWG thru 350 kcmil | Over 250 kcmil thru 500 kcmil |
| Over 350 kcmil thru 600 kcmil | Over 500 kcmil thru 900 kcmil |
| Over 600 kcmil thru 1100 kcmil | Over 900 kcmil thru 1750 kcmil |
| Over 1100 kcmil | Over 1750 kcmil |
[!IMPORTANT] The 12.5% Rule for Large Services (Table 250.102(C)(1) Note 1): Where the ungrounded supply conductors exceed 1100 kcmil Copper or 1750 kcmil Aluminum, the bonding jumper shall have an area not less than 12.5% of the total area of the ungrounded supply conductors per phase.
Worked Calculation Example: 12.5% Rule Sizing
Scenario: A 2000A 480V service is supplied by four parallel runs of 500 kcmil copper conductors per phase (total $4 \times 500 = 2,000\text{ kcmil}$ copper per phase). What minimum size copper Main Bonding Jumper is required?
- Step 1: Check Total kcmil Area:
- Total ungrounded conductor area per phase = 2,000 kcmil Cu.
- 2,000 kcmil exceeds 1100 kcmil, so Table 250.102(C)(1) cap applies: 12.5% Rule.
- Step 2: Calculate Required Minimum cmil Area:
- Step 3: Select Conductor Size:
- 250 kcmil Copper minimum MBJ wire or equivalent busbar.
Specific Building Bonding Requirements (NEC 250.104)
NEC 250.104 dictates bonding rules for interior metal piping and structural building frames:
BUILDING BONDING REQUIREMENTS SUMMARY
+-------------------------------------------------------------------------+
| INTERIOR METAL WATER PIPING (NEC 250.104(A)) |
| - Bonded to service enclosure, GEC, or grounding electrode system. |
| - Sized per Table 250.102(C)(1) based on service conductor size. |
+-------------------------------------------------------------------------+
| METAL GAS PIPING (NEC 250.104(B)) |
| - Bonded to service equipment, GEC, or circuit EGC. |
| - Sized per Table 250.122 based on OCPD of circuit likely to energize it.|
+-------------------------------------------------------------------------+
| STRUCTURAL METAL FRAMING (NEC 250.104(C)) |
| - Exposed structural steel likely to become energized must be bonded. |
| - Sized per Table 250.102(C)(1) based on service conductor size. |
+-------------------------------------------------------------------------+
1. Bonding Metal Water Piping (NEC 250.104(A))
- Interior metal water piping systems must be bonded to the service equipment enclosure, the grounded conductor at the service, the GEC, or one or more electrodes.
- Sizing: Sized per Table 250.102(C)(1) based on largest service conductor.
2. Bonding Other Metal Piping / Gas Piping (NEC 250.104(B))
- Metal gas piping and other metal piping systems likely to become energized must be bonded to the service enclosure, GEC, or grounded conductor.
- Sizing: Sized per Table 250.122 based on the rating of the circuit likely to energize the piping (e.g., gas furnace branch circuit, gas water heater circuit).
- Practical Note: The equipment grounding conductor (EGC) of the appliance branch circuit supplying the equipment (e.g. 12 AWG Cu for a 20A furnace circuit) is explicitly permitted to satisfy the gas pipe bonding requirement!
Service Equipment & Knockout Bonding (NEC 250.92)
Service equipment raceways and enclosures require a much higher level of bonding integrity than standard branch circuit equipment. Why? Because service conductors have no line-side overcurrent protection ahead of them to trip during a fault!
SERVICE ENCLOSURE BONDING VS BRANCH CIRCUITS
+-------------------------------------------------------------------------+
| SERVICE RACEWAY TERMINATION (NEC 250.92) |
| - Standard locknuts or double locknuts ALONE ARE PROHIBITED! |
| - MUST USE: Bonding bushings with bonding jumpers, threaded hubs, or |
| bonding locknuts with wedge teeth. |
| - Concentric / Eccentric knockouts REQUIRE bonding jumpers around rings!|
+-------------------------------------------------------------------------+
| BRANCH CIRCUIT RACEWAY TERMINATION (< 250V to Ground) |
| - Standard locknuts on painted enclosures permitted. |
+-------------------------------------------------------------------------+
[!CAUTION] Knockout Exam Trap (NEC 250.92(B)): Where service raceways enter service enclosures through concentric or eccentric knockouts, standard locknuts cannot guarantee electrical continuity. A grounding bushing with a bonding jumper sized per Table 250.102(C)(1) must be installed around the knockout ring to ensure a low-impedance ground-fault return path.
What is the primary function of the Main Bonding Jumper (MBJ) in a grounded electrical service per NEC 250.28?
A 3-phase, 4-wire service has ungrounded service-entrance conductors consisting of four parallel 500 kcmil copper conductors per phase (total 2,000 kcmil per phase). According to NEC 250.28(D) and Table 250.102(C)(1), how must the Main Bonding Jumper (MBJ) be sized?
According to NEC 250.92(B), why are standard locknuts and double locknuts NOT permitted as the sole bonding means for metal raceways containing service conductors at service enclosures?
Under NEC 250.104(B), how is the bonding conductor for interior metal gas piping required to be sized?