7.2 Installer Tests II: 24-Hour Standing Pressure & Vacuum Tests, Inspection & Witnessing
Key Takeaways
Positive-pressure systems get a 24-hour standing pressure test with nitrogen NF at 20% above normal operating line pressure, after outlet valve bodies, faceplates, and all other distribution components are installed.
Leakage during the 24-hour positive-pressure test may not exceed 0.5% of the starting pressure (for example, 0.3 psi starting at 60 psig), excluding effects of ambient temperature changes.
Vacuum systems get a 24-hour standing vacuum test between 12 in. HgV and full vacuum, with the test vacuum source disconnected, and leakage limited to 0.5% of the starting vacuum.
The 24-hour positive-pressure test must be witnessed by an ASSE 6020 inspector, an ASSE 6030 verifier, or the AHJ or its designee, and a form documenting it goes to the verifier.
System inspections, including labeling and valve tagging of concealed components, happen before piping is concealed and must be done by a party other than the installing contractor.
The 24-Hour Standing Pressure Test (Positive-Pressure Gases)
| Item | Requirement |
|---|---|
| Prerequisite | The initial pressure tests passed |
| Timing | After final installation of station outlet valve bodies, faceplates, and all other distribution system components |
| Source valve | Closed |
| Test gas | Oil-free, dry nitrogen NF |
| Duration | 24 hours |
| Test pressure | 20% above the normal system operating line pressure |
| Acceptance | Leakage over 24 hours may not exceed 0.5% of the starting pressure (for example, 0.3 psi starting at 60 psig), except changes caused by ambient temperature |
| Leaks | Locate them, repair (where permitted) or replace, and retest |
| Witness | An ASSE 6020 inspector, an ASSE 6030 verifier, or the AHJ or its designee; a form documenting the witnessed test goes to the verifier at the start of verification |
Worked examples
| System | Normal line pressure | Test pressure (normal x 1.2) | Maximum leakage (0.5% of start) |
|---|---|---|---|
| Oxygen | 50 psig | 60 psig | 0.30 psi |
| Medical air | 55 psig | 66 psig | 0.33 psi |
| Nitrogen | 160 psig | 192 psig | 0.96 psi |
| Instrument air | 175 psig | 210 psig | 1.05 psi |
Accounting for temperature
Gas pressure follows absolute temperature. Suppose an oxygen line starts at 60 psig (about 74.7 psia) at 70°F (529.67°R), and the space cools to 65°F (524.67°R) overnight. With no leakage at all, the absolute pressure falls in proportion:
That is a drop of about 0.7 psi, more than twice the 0.3 psi limit, with no leak. This is why NFPA 99 excludes changes attributed to specific changes in ambient temperature. Record the temperature at the start and the end of the test. Then you can show whether a drop is temperature or a real leak, and a real leak must be found and fixed.
The 24-Hour Standing Vacuum Test
| Item | Requirement |
|---|---|
| Prerequisite | The initial pressure tests passed (vacuum piping is also pressure tested at 150 psi minimum) |
| Timing | After installation of all components of the vacuum system |
| Duration | 24 hours |
| Test level | Between 12 in. HgV and full vacuum |
| Test source | Disconnected from the piping during the test |
| Acceptance | Leakage may not exceed 0.5% of the starting vacuum (for example, 0.125 in. HgV starting at 25 in. HgV), except changes caused by ambient temperature |
| Leaks | Locate them, repair (where permitted) or replace, and retest |
| Witness and form | The test is witnessed, and a form documenting it goes to the verifier at the start of verification |
Example: a WAGD and vacuum branch is pulled to 24 in. HgV and isolated from the pump. The maximum allowable loss is 0.5% of 24, or 0.12 in. HgV. A reading of 23.7 in. HgV the next morning (a 0.3 in. loss) fails unless the change can be attributed to temperature.
System Inspection Before Concealment
NFPA 99 also requires inspections separate from the installer's own tests:
- When: before piping is concealed in walls, ceilings, chases, trenches, underground, or otherwise hidden from view
- Test gas: nitrogen NF, where gas is needed for the inspection
- Who: a qualified party experienced in medical gas and vacuum pipeline inspection and testing, certified to ASSE 6020 (inspector) or ASSE 6030 (verifier)
- Independence: performed by a party other than the installing contractor. Where the system was not installed by the facility's own personnel, the facility's qualified personnel may inspect it.
- What: the presence and correctness of labeling and valve tagging for all concealed components and piping
- Witnessing: the initial pressure tests performed by the installer are witnessed by an ASSE 6020 inspector, an ASSE 6030 verifier, or the AHJ or its designee, and documented on a form for the verifier
Practical Test-Day Checklist
- Confirm the system is complete for the test stage: rough-ins for the initial test; valve bodies, faceplates, and components for the 24-hour test.
- Close the source valve. Disconnect or isolate anything that test pressure could damage during initial tests.
- Use calibrated gauges with a range and resolution suited to the acceptance criterion. A 0.3 psi limit cannot be read on a gauge with 5 psi divisions.
- Record the start time, pressure, and temperature, and the end time, pressure, and temperature.
- Have the witness sign the form, and file it for the verifier.
- If a leak is found, repair it as the code permits. A joint may be reheated only once. Then retest from the start.
Tip
Do not mix up the two "20%" rules. 20% above normal pressure is the installer's 24-hour standing test pressure. Plus or minus 20% is the alarm trigger for line pressure. Also keep the durations straight: the installer's standing test lasts 24 hours, and the verifier's standing test lasts 10 minutes (Section 7.3).
An oxygen system normally operates at 50 psig. What are the test pressure and the maximum allowable leakage for the installer's 24-hour standing pressure test?
75 psig, with 0.5 psi allowable
150 psig, with no allowable drop
55 psig, with 1 psi allowable
60 psig, with 0.3 psi allowable
What vacuum level does NFPA 99 require for the installer's 24-hour standing vacuum test?
Between 12 in. HgV and full vacuum, with the vacuum source disconnected
Exactly 19 in. HgV with the pumps running
At least 5 in. HgV, with the WAGD producer running to hold the vacuum steady
Any vacuum level, held for 10 minutes
Who may witness the installer's 24-hour standing pressure test of a positive-pressure medical gas system under NFPA 99?
The installing contractor's own superintendent
The facility's purchasing agent
An ASSE 6020 inspector, ASSE 6030 verifier, or the AHJ or designee
Any ASSE 6010-certified installer on the project who did not braze the joints