1.2 Codes, Referenced Standards & the Medical Gas Team

Key Takeaways

  • NFPA 99 Chapter 5 covers gas and vacuum systems: 5.1 for Category 1, 5.2 for Category 2, and 5.3 for Category 3. Chapter 15 covers dental gas and vacuum systems.

  • For cryogenic fluid central supply systems, the source valve marks the boundary between NFPA 55 and NFPA 99.

  • Brazing procedures and brazers are qualified to ASME Boiler and Pressure Vessel Code Section IX or AWS B2.2, as modified by NFPA 99.

  • Inspections and verification tests must be performed by a party other than the installing contractor. Inspectors are certified to ASSE 6020 and verifiers to ASSE 6030.

  • New construction must meet the current code. In an existing system, only the altered portion must comply unless the authority having jurisdiction finds a distinct hazard to life.

Last updated: October 2026

How the Rulebook Is Organized

NFPA 99, Health Care Facilities Code is the core document for this exam. Installers mostly work in Chapter 5, Gas and Vacuum Systems, but several other chapters feed into it:

NFPA 99 locationWhat it gives the installer
Chapter 1 (Administration)Applies requirements to new construction and new equipment; the altered portion of an existing system must comply
Chapter 3 (Definitions)Exact meanings of terms such as station outlet, zone valve, and medical support gas
Chapter 4 (Fundamentals)Risk categories that decide whether a space needs Category 1, 2, or 3 systems
5.1Category 1 piped gas and vacuum systems (the full rule set)
5.2 and 5.3Category 2 and Category 3 systems, mostly by reference back to 5.1 with listed exceptions
Chapter 15Dental gas and vacuum systems

The existing-systems rule in Chapter 1 is easy to test. Only the altered, renovated, or modernized portion of an existing system has to meet the installation and equipment requirements. Further upgrading is required only if the work would hurt the existing system's performance. An existing system that does not strictly comply may stay in service unless the authority having jurisdiction (AHJ) decides it is a distinct hazard to life.

Editions matter. NITC's exam uses NFPA 99-2024 together with ASSE Series 6000. A job site, however, follows whatever edition the AHJ has adopted. Some plumbing codes, such as the Uniform Plumbing Code's health care chapter, extract NFPA 99 text with paragraph references. Learn the 2024 rules for the exam and confirm the adopted edition before you install.

Referenced Standards You Must Recognize

StandardWhy it appears in medical gas work
ASTM B819Seamless copper medical gas tube for positive-pressure systems
ASTM B88, ASTM B280Copper tube options permitted for vacuum piping
ASME B16.22 / ASME B16.50Wrought copper solder-joint fittings and wrought braze-joint fittings
AWS A5.8Specification for brazing filler metals (BCuP and BAg series)
ASME BPVC Section IX or AWS B2.2Qualification of brazing procedures and brazer performance
CGA G-4.1Cleaning equipment for oxygen service
CGA V-1Cylinder valve outlet and inlet connections (manifold leads)
CGA V-5Diameter Index Safety System (DISS) noninterchangeable threaded connections
CGA M-1Bulk/cryogenic supply systems (verification by ASSE 6035 personnel)
ASME B1.20.1Tapered pipe threads for the few threaded joints that are permitted
MSS SP-58Pipe hangers and supports
ASME BPVC Section VIIIUnfired pressure vessels, such as air and vacuum receivers
CDA Copper Tube HandbookBrazing technique that NFPA 99 references for heating and filling joints
NFPA 55Compressed gases and cryogenic fluids

The NFPA 55 boundary: for cryogenic fluid central supply systems, NFPA 99 adopts NFPA 55 language that makes the source valve the line between the two codes. Everything from the bulk vessel up to the source valve falls under NFPA 55. The pipeline on the facility side of it falls under NFPA 99.

Who Does What

RoleQualificationTypical responsibility
DesignerASSE 6060, or another qualification the governing body acceptsLays out sources, sizes piping, locates valves and alarms
Installer / brazerASSE 6010Installs piping and components; performs installer tests
Cryogenic installerASSE 6015Installs permanently installed bulk cryogenic supply systems
InspectorASSE 6020 (or 6030)Inspects before piping is concealed; can witness installer tests
VerifierASSE 6030Performs system verification after the installer tests are complete
Cryogenic verifierASSE 6035Tests cryogenic fluid central supply systems under CGA M-1
Maintenance personnelASSE 6040Maintains systems that are already in service
InstructorsASSE 6050 / 6055 / 6070Teach the qualification courses
AHJGovernment or designated officialApproves plans and permits; can witness tests
Responsible facility authorityQualified person named by the facilityOperates and manages the systems after turnover

Independence is written into the code. System inspections must be performed by a party other than the installing contractor, and so must verification testing. When the facility's own staff did not install the system, the facility's qualified personnel may perform the inspection or the testing. When the facility's own staff did install it, an outside party is required.

Finding Topics in NFPA 99-2024 Chapter 5

Course materials and exam questions often cite paragraph numbers. The major Chapter 5 divisions for Category 1 systems are:

ParagraphTopic
5.1.3Central supply systems (sources)
5.1.4Valves
5.1.5Station outlets and inlets
5.1.6Manufactured assemblies
5.1.7Surface-mounted medical gas rails
5.1.8Pressure and vacuum indicators
5.1.9Warning systems (alarms)
5.1.10Distribution: piping materials, joints, brazing, installation, installer and brazer qualification
5.1.11Labeling, identification, and operating pressures
5.1.12Performance criteria and testing (5.1.12.2 installer tests, 5.1.12.3 inspection, 5.1.12.4 verification)
5.1.13Medical support gases
5.1.14Operation and management

Paragraph numbers can shift between editions, so learn the topics, not just the numbers.

The Workflow in One Picture

The diagram after this text shows the normal order: design and approval, installation by ASSE 6010 personnel, inspection before concealment, the installer's tests, and finally independent verification before the system is used for patient care.

Loading diagram...
Medical Gas Project Roles and Sequence
Test Your Knowledge

For an outdoor bulk cryogenic oxygen system serving a hospital, where does NFPA 55's jurisdiction end and NFPA 99's pipeline requirements begin?

A

At the first zone valve inside the building

B

At the vaporizer outlet

C

At the source valve

D

At the main line valve where the pipe enters the building

Test Your Knowledge

The installing contractor's own project foreman is a certified ASSE 6020 inspector. Can that foreman perform the system inspection required before the new piping is concealed?

A

Yes, because the foreman's ASSE 6020 certification is personal

B

No; inspections must be by a party other than the installing contractor

C

Yes, provided the AHJ witnesses the inspection

D

No, because only an ASSE 6030 verifier may inspect concealed piping

Test Your Knowledge

A clinic is renovating one wing of an older medical gas system that met an earlier edition of NFPA 99. Which statement reflects NFPA 99's rule for existing systems?

A

The entire facility system must be upgraded to the current edition before the work is accepted

B

Only the altered portion must comply, unless the AHJ finds a distinct hazard to life

C

Existing systems are always exempt from the current edition, even if the AHJ finds a distinct hazard

D

Only the source equipment must be upgraded to the current edition