7.5 Documentation, Records & System Turnover

Key Takeaways

  • Brazing procedure and brazer qualification documentation must be provided and kept on the job site before any installation work begins.

  • The installer must furnish documentation certifying that installed piping materials were cleaned for oxygen service per CGA G-4.1.

  • Forms documenting the witnessed initial pressure tests and the 24-hour standing tests must be given to the verifier at the start of verification.

  • Inspection and testing reports go to the party that contracted for the testing, then through channels to the responsible facility authority, with detailed listings of all findings and results.

  • Copies of the manufacturer's instructions for installed components must be left with the system owner.

Last updated: October 2026

Why Documentation Is Tested

NITC weights conducting, documenting, and recording inspections and tests at 6% of the written exam. Documentation questions are also some of the easiest points to win, because the rules are specific about what is documented, when, and who receives it.

Before Work Starts

DocumentNFPA 99 requirement
Brazing procedure qualifications (BPS and PQR)Provided and maintained on the job site before any installation work
Individual brazer qualificationsOn the job site before work; include records accepted from previous employers, signed and dated
Procedures from a technically competent group or agencyCopies of the BPS and PQR signed and dated by the employer, plus at least one brazer qualified on each BPS
Installer certificationsEvery installer must be qualified. A certified installer may not oversee noncertified installers, so each worker's ASSE 6010 card should be available.

Some jurisdictions also require construction documents before work starts. The California Plumbing Code, for example, requires duplicate construction documents filed with the AHJ and approved before a permit is issued. Those documents show the plot plan with cylinder storage, the piping layout with alarms, valves, sources, outlets, and inlets, the demand and loading, and a complete materials specification.

During Construction

  • Material certification: the installer furnishes documentation certifying that all installed piping materials were cleaned for oxygen service per CGA G-4.1. Metallic flexible joints arrive with a factory certification of cleanliness.
  • Brazing continuity: under NITC's program, an authorized employer representative documents each brazer's continuity every six months. The employer keeps the Record of Brazer Qualification.
  • Inspection before concealment: the ASSE 6020 or 6030 inspector records that labeling and valve tagging of concealed piping and components were present and correct.
  • Test records: log the system, date, test pressure or vacuum, duration, start and end readings, temperatures, the person performing the test, the witness, and the result for:
    • initial blowdown
    • initial pressure test (witnessed)
    • initial cross-connection test
    • initial piping purge test
    • 24-hour standing pressure test, positive pressure (witnessed)
    • 24-hour standing vacuum test (witnessed)

Handing Off to the Verifier

NFPA 99 requires forms indicating that the initial pressure tests and the 24-hour standing tests were performed and witnessed to be provided to the verifier at the start of the verification tests. Verification may begin only after all installer-performed tests are complete, and these forms are how the verifier confirms that.

Reports and Permanent Records

  • Inspection and testing reports go directly to the party that contracted for the testing, which passes them through channels to the responsible facility authority and anyone else who requires them. Reports contain detailed listings of all findings and results.
  • Final tie-in tests: permanent records must be kept.
  • Some plumbing codes require a report delivered to the AHJ before acceptance, covering leakage, zoning, labeling, cross-connection, flow, alarms, purge, purity, and gas identity. They may also require that as-built plans and valve identification records remain on the site. California's plumbing code is one example.

Turnover to the Owner

ItemRequirement or best practice
Manufacturer's instructionsCopies left with the system owner (NFPA 99). They must include what the manufacturer considers adequate for operation, testing, and maintenance.
Verification reportDelivered through channels to the responsible facility authority
As-built drawings and valve identification recordsRequired on site by some plumbing codes; essential for future shutdowns, breaches, and maintenance
Test records and witness formsPart of the permanent project record

What the Facility Does Next

After turnover, the responsible facility authority runs the systems. That person must be qualified, for example through an ASSE 6010, 6020, 6030, or 6040 credential plus competence on the facility's specific equipment and design, or through an equivalent education program the governing body accepts. NFPA 99's operation and management rules include:

  • Calibrating carbon monoxide monitors at least annually, or more often if the manufacturer recommends
  • Maintenance programs for the medical air compressor system, the vacuum piping and the equipment attached to vacuum inlets, and the WAGD system
  • Periodic testing of audible and visual alarm indicators, with records kept at least until the next test
  • Never using medical-surgical vacuum or WAGD for nonmedical applications

The installer's records feed directly into these programs. A facility cannot plan a safe shutdown without accurate valve identification records, or judge an alarm without knowing where its sensor was installed.

Documentation Checklist

  1. BPS and PQR (signed and dated by the employer) on site before work
  2. Brazer qualification and continuity records on site
  3. ASSE 6010 cards for every installer
  4. Material cleanliness certifications per CGA G-4.1
  5. Inspection record for labeling and valve tagging before concealment
  6. Installer test logs: blowdown, initial pressure, cross-connection, purge
  7. Witnessed forms for the initial pressure tests and the 24-hour standing tests, handed to the verifier
  8. Final tie-in test records, kept permanently
  9. As-built drawings and valve identification records, where required
  10. Manufacturer's instructions left with the owner
Test Your Knowledge

When must documentation of brazing procedure and brazer qualifications be available on the job site?

A

Within 30 days after the system is placed in service

B

Before the 24-hour standing pressure test

C

When the verifier arrives

D

Before any installation work begins

Test Your Knowledge

Who must receive the forms documenting the witnessed initial pressure tests and 24-hour standing tests, and when?

A

The AHJ, within 10 days after the tests

B

The verifier, at the start of verification

C

The equipment manufacturer, before warranty starts

D

The installer's insurance carrier, at project closeout

Test Your Knowledge

What does NFPA 99 require the installer to do with the manufacturer's instructions for installed components such as valves, outlets, and alarms?

A

Keep them in the installer's office files only

B

Send them to ASSE International

C

Leave copies with the system owner

D

Discard them after verification passes