On an electrical job, how does a hazard differ from a risk?
A hazard is a possible source of harm, such as exposed live parts. Risk combines the likelihood that someone will be harmed with how serious the harm could be.
Filter by Topic
Jump to Card
About These AM2 / AM2S Flashcards
These 50 flashcards are designed to help you memorize key terms and definitions for the AM2 / AM2S Electrical Installation Assessment (Applied Knowledge). Each card shows a term on the front and its definition on the back—the classic flashcard format for vocabulary memorization. Use these alongside our practice questions to build both recall and comprehension.
Topics Covered
Complete Flashcard Reference
Review every term in this set. Open any term to reveal its definition.
On an electrical job, how does a hazard differ from a risk?
A hazard is a possible source of harm, such as exposed live parts. Risk combines the likelihood that someone will be harmed with how serious the harm could be.
What control should you consider first when assessing a hazard?
Consider whether you can remove the hazard altogether. If it remains, reduce exposure with measures such as separation or a safer work method before relying on personal protective equipment.
Why must an isolation point be secured against reconnection?
An open switch can be operated by someone else. A suitable lock-off and warning notice help keep the circuit isolated while work is in progress, with the key kept secure.
What does re-proving a voltage indicator after a dead check establish?
It confirms that the indicator still works after the check. If it fails to prove, the absence of an indication is unreliable and the circuit must be treated as live until safely verified.
Why identify every source of supply before isolating a circuit?
A battery, generator or other alternative source can keep conductors energised after the normal supply is isolated. Identify each relevant supply so the safe system of work accounts for every possible feed.
What three conditions must all be met under regulation 14 for work on or near a live conductor where danger may arise?
Making it dead must be unreasonable in the circumstances, doing the work while it is live must be reasonable in those circumstances, and suitable precautions must be taken to prevent injury.
When electrical work requires technical knowledge to prevent danger, how can a trainee take part?
Regulation 16 of the Electricity at Work Regulations permits work under supervision appropriate to the nature of the task when the worker lacks the necessary technical knowledge or experience.
What does automatic disconnection of supply (ADS) achieve after an earth fault?
The protective device disconnects the supply within the time required for that circuit. This limits how long a dangerous touch voltage can persist.
What makes the metal casing of Class I equipment an exposed-conductive-part?
It can be touched and is normally free of voltage, but it can become live if basic insulation fails. The protective conductor provides a path for fault current.
What makes an incoming metal service an extraneous-conductive-part?
It can introduce a potential, usually Earth potential, from outside the electrical installation. Where required, protective bonding connects it to the main earthing terminal to limit dangerous touch voltages.
What protection does an RCBO add to the residual-current function of an RCCB?
An RCBO also protects against overload and short-circuit current. An RCCB needs suitable separate overcurrent protection.
What is the purpose of a surge protective device (SPD)?
An SPD limits brief overvoltages and diverts surge current. This helps protect insulation and equipment from transients such as those caused by lightning or switching.
How are an installation’s exposed-conductive-parts earthed in a TT system?
They connect to an installation earth electrode independent of the supply’s earthing electrode. The earth path can have too much impedance for an overcurrent device to disconnect in time, so fault protection commonly uses an RCD.
What does a 30 mA RCD provide when specified as additional protection against electric shock?
It adds a layer of protection if basic or fault protection fails, or if a user is careless. The circuit still needs the basic and fault protection required by BS 7671.
What is the purpose of Part P for electrical installations in dwellings in England?
It requires reasonable provision in design and installation to protect people from fire or injury when they use, maintain or alter the installation.
Which kinds of domestic electrical work normally trigger Part P notification in England?
A new circuit, a replacement consumer unit, or an addition or alteration to an existing circuit in a defined special location. Wales has its own notification guidance.
What electrical-safety duty remains when domestic work in England is non-notifiable?
The work still has to comply with Part P. The installer should carry out appropriate inspection and testing and provide the electrical documentation relevant to the work.
Who can self-certify notifiable domestic electrical work under a competent person scheme in England?
An installer registered for that type of work can self-certify their own work. The installer or registration body provides the compliance certificate to the occupier and informs building control.
What must be preserved when a cable passes through a fire-resisting wall?
The wall’s required fire resistance. Use an appropriate fire-stopping system for the penetration so the opening does not undermine the compartment.
Which part of the Building Regulations in England covers accessible locations for switches and sockets?
Part M covers access to and use of buildings. Its guidance addresses mounting positions for controls and outlets so people can reach and use them.
What is the purpose of visual inspection during initial verification?
It checks selection, installation and visible condition, such as suitability of equipment, identification and protection against contact. A satisfactory instrument reading cannot reveal every defect in workmanship.
What do r₁, rₙ and r₂ record on a ring final circuit test schedule?
They are the end-to-end resistances of the ring’s line, neutral and circuit protective conductors respectively, in ohms. They help check whether each conductor forms a complete loop.
What is an insulation resistance test designed to reveal?
It checks that conductors intended to be insulated from each other or from earth are adequately separated electrically. A low reading can point to damaged insulation, moisture or connected equipment affecting the test.
What does a circuit polarity check confirm about a single-pole switch?
The switch interrupts the line conductor. A switch placed in the neutral alone can turn the load off while leaving live parts connected to line.
How does earth fault loop impedance Zₛ differ from Zₑ?
Zₑ is the external part of the earth fault loop at the origin. Zₛ is the total loop impedance at the point assessed, including the relevant installation path.
What records accompany an Electrical Installation Certificate for a new installation?
The applicable schedule of inspections and schedule of test results, with circuit details. They show what was inspected and verified and give a record for future work.
Why use the specified conductor size and cable type in the NET installation task?
The job drawings and specification set the required installation. A substitution can change mechanical or electrical performance and make the work fail the brief.
Why follow the manufacturer’s torque setting for a terminal?
A loose joint can overheat or arc, while excessive torque can damage the conductor or terminal. The specified setting helps achieve a secure, durable connection.
Why protect a cable where it enters a metal enclosure through an opening?
The edge can abrade or cut insulation as the cable moves. A suitable gland, bush or other edge protection helps prevent damage at the entry.
Why are wiring supports selected to resist premature collapse during a fire?
Fallen wiring can obstruct escape and endanger firefighters. The support arrangement must keep the wiring from collapsing prematurely under fire conditions.
What should an installer check about unused openings in a distribution board?
Check that suitable blanks or closures maintain the enclosure’s protection against access to live parts. Verify the enclosure with its covers and accessories fitted.
What should a circuit schedule at a distribution board make clear?
It should let someone identify which protective device serves each circuit. Accurate identification helps with safe operation, isolation and later maintenance.
What distinguishes an open circuit from a short circuit?
An open circuit breaks an intended current path. A short circuit creates an unintended low-impedance path between points that should be at different potentials.
Why can a high-resistance joint overheat without an overload trip?
Normal load current can produce concentrated heating at the resistive joint. The total current can stay below the level that would cause the overcurrent device to operate.
How might a misconnection differ from a break when diagnosing a circuit?
A misconnected conductor may still have electrical continuity, but it reaches the wrong terminal or device. Compare the actual connections with the circuit diagram.
What makes a fault location specific enough for a NET fault record?
Name the affected conductor and the two points between which the fault lies, or identify the equipment and connection where it occurs. This tells the reader which part needs attention.
Why start fault diagnosis with the reported symptom and the circuit diagram?
Together they show which parts of the circuit could explain the symptom. They help you select checks that distinguish likely causes before choosing a repair.
What shows that an electrical fault repair has been effective?
Repeat the checks relevant to the defect and any protective measures affected by the repair. Record the results and verify the circuit functions as intended when safe to do so.
How do Ib, In and Iz relate in ordinary overload protection design?
Ib ≤ In ≤ Iz. The device rating or setting (In) must cover the design current (Ib). The cable’s current-carrying capacity under its actual installation conditions (Iz) must cover In.
Why can grouping cables or enclosing them in thermal insulation reduce their current rating?
Cables lose heat less easily in those conditions. Select the rating for the actual installation method and apply the relevant correction factors before choosing the cable size.
How do you convert a tabulated mV/A/m value into a circuit voltage drop in volts?
Multiply the appropriate mV/A/m value by the design current in amps and the one-way route length in metres, then divide by 1,000. For example, 10 mV/A/m × 12 A × 20 m ÷ 1,000 = 2.4 V.
Why check prospective fault current when selecting a circuit-breaker?
The device must be able to interrupt the fault current at its point of installation. Check its breaking capacity or a verified backup-protection combination for that current.
What does the adiabatic check establish for a protective conductor?
It checks whether the conductor can withstand the heating caused by fault current until the protective device disconnects. Conductor material and insulation affect the allowable thermal stress.
What does diversity account for when estimating maximum demand?
It accounts for loads that are unlikely to draw their full current at the same time. Base the allowance on expected use and applicable guidance for the installation.
How should you respond when someone asks you to continue with an unsafe working method?
Pause the affected work, explain the hazard and raise it with the responsible person. Continue once a safe method is agreed and in place.
What should you tell affected people before a planned power interruption?
Explain the expected time, duration and services affected. Check for critical equipment or other dependencies so the interruption can be coordinated safely.
How should you explain new equipment to a customer at handover?
Use plain language to explain normal operation and what to do if a warning or trip occurs. Give the relevant instructions and check that the customer understands.
What should you do if a requested change affects the agreed installation specification?
Confirm the change with the responsible person before carrying it out and record the agreed revision. This gives everyone a common basis for installation and verification.
What does responsible waste handling look like at the end of an electrical job?
Separate reusable, recyclable and hazardous materials as appropriate and use the designated disposal routes. Leave the work area safe for the people who use it next.
How does continuing professional development support electrical competence?
It keeps knowledge and practical skills current as standards, equipment and work methods change. Examples include reviewing amendments and training on unfamiliar systems before taking on that work.
Frequently Asked Questions
How many questions are on AM2 Section E?
AM2 and original AM2S each have 30 online multiple-choice questions in 60 minutes. AM2S v1 has 45 in 90 minutes. Section E is one part of a competence assessment that also includes practical work.
Which version of the assessment should I prepare for?
AM2 is used for qualifying Level 3 NVQ routes. NET directs Installation and Maintenance Electrician apprentices who started before September 2023 to original AM2S and apprentices registered from September 2023 to AM2S v1. Your training provider can confirm your registration and the assessment plan that applies to you.
What score passes the applied knowledge test?
NET gives 21 correct answers out of 30 (70%) for original AM2S. The Skills England ST0152 v1.2 plan gives 32 out of 45 for the AM2S v1 test under that plan. Confirm the applicable threshold with your provider if you are on another plan. NET’s standalone AM2 materials give the question count and timing but omit a numerical pass mark.
Which reference books can I use during Section E?
NET supplies the permitted references at the centre. Its AM2S v1 manual lists BS 7671, IET Guidance Note 3, the IET On-Site Guide and the IET Electrician’s Guide to the Building Regulations. Use the centre’s copies during the assessment.
Which edition of BS 7671 should I revise?
The IET identifies BS 7671:2018+A4:2026 as the current Wiring Regulations. NET’s AM2S v1 materials say centres supply the versions current at the time of assessment.
How do Section E re-sits work?
Arrange a re-sit of the failed section with a NET centre. NET bars re-sits within 10 days of the original sitting and recommends three weeks with further preparation. Under ST0152 plan v1.2, the employer and assessment organisation agree the timing, with a re-sit typically taken within three months of the EPA outcome. Ask your provider about the plan and any action plan requirements that apply to you.