Under the Construction (Design and Management) Regulations 2015 (CDM 2015), who holds the overall duty to make suitable arrangements for managing a project and to ensure welfare facilities are provided?
Cdm 2015 Regulations Duty Holders
Question · Easy
On a project involving more than one contractor, which CDM 2015 duty holder is responsible for planning, managing and coordinating health and safety during the construction phase?
Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work
Study guide
Under CDM 2015, when must a principal designer be appointed by the client?
Question · Medium
Trades Exam Prep Podcast
Listen on Spotify
Podcast
A construction project is expected to last 45 working days with 25 workers on site at the same time. What is the correct action under CDM 2015?
Statutory Inspections Notifications
Which document must the principal contractor draw up before the construction phase begins on a CDM 2015 project?
What is the primary purpose of the health and safety file required under CDM 2015?
1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties
Under CDM 2015, what is a designer's main duty in relation to health and safety?
Which Act is the primary piece of UK legislation placing general duties on employers to ensure, so far as is reasonably practicable, the health, safety and welfare of employees at work?
Hasawa Management Duties
Under section 7 of the Health and Safety at Work etc. Act 1974, what duty is placed on every employee?
What does the phrase 'so far as is reasonably practicable' require a duty holder to do when deciding on control measures?
1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act)
Which regulations specifically require employers to carry out a 'suitable and sufficient' assessment of the risks to the health and safety of their employees?
Risk Assessment Method Statements
What are the five steps of risk assessment as set out in traditional HSE guidance?
In the hierarchy of control, which measure should always be considered FIRST when controlling a hazard?
What is the main purpose of a method statement (or safe system of work) on a construction site?
1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor)
Under the Work at Height Regulations 2005, what is the correct order of the hierarchy a manager must apply?
Working At Height
A scaffold has been in continuous use on a project. How often, as a minimum, must it be inspected by a competent person while it remains in use?
When MUST a scaffold be re-inspected in addition to the routine 7-day interval?
Which of the following is a 'collective' fall-protection measure, protecting everyone in the area rather than only the individual?
1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File
Before a mobile elevating work platform (MEWP) is used to lift people, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require it to undergo a thorough examination at what maximum interval?
Question · Hard
What is the most reliable way to protect workers from collapse when working in a deep, vertical-sided trench?
Excavations Confined Spaces
A site manager hears that 'excavations under 1.2 metres deep do not need any support'. How should this be treated?
Before digging an excavation, which control is essential to prevent contact with buried services such as electricity cables and gas mains?
1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI)
Under the Confined Spaces Regulations 1997, what is the correct general approach to confined-space work?
Which of the following is a recognised specified risk that can make a space a 'confined space' under the Confined Spaces Regulations 1997?
What is the recommended standard voltage for portable electric hand tools on a UK construction site to reduce the risk of fatal electric shock?
Electrical Safety
Which regulations place the main legal duties on duty holders to prevent danger from electricity in the workplace, including on construction sites?
1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
What is the safest first action when an overhead power line crosses a site where tall plant such as cranes or tipper lorries will operate?
According to HSE guidance, at roughly what interval should 110 V portable tools used on a construction site receive a combined inspection and electrical test?
Before any maintenance is carried out on an electrical circuit, what is the essential procedure to follow?
Which three elements must be present together for a fire to start, as described by the 'fire triangle'?
Fire Prevention
Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment
What control should be put in place before 'hot works' such as welding, grinding or using a blowtorch are carried out on site?
On a construction site, which fire-prevention measure is most effective at reducing the amount of available fuel for a fire?
Which type of fire extinguisher is generally suitable for a fire involving live electrical equipment?
What is the primary purpose of a site fire and emergency plan?
2.2 Hierarchy of Control Measures & Risk Matrices
Under the Control of Noise at Work Regulations 2005, at which daily or weekly average noise exposure must employers provide hearing protection and designate hearing-protection zones?
Occupational Health
Which occupational health condition is caused by prolonged exposure to vibration from hand-held power tools such as breakers and grinders?
Which Regulations require employers to assess and control the risks to health from hazardous substances such as silica dust, solvents and cement?
What is the most effective way to control respirable crystalline silica (RCS) dust when cutting paving slabs or concrete?