All Practice Exams

100+ Free C&G 2922-34 Solar PV Practice Questions

Pass your City & Guilds 2922-34 Level 3 Award in the Installation and Maintenance of Small Solar Photovoltaic (PV) Systems exam on the first try — instant access, no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free

Loading practice questions...

2026 Statistics

Key Facts: C&G 2922-34 Solar PV Exam

30 questions

The unit 301 online knowledge test has about 30 multiple-choice questions

City & Guilds 2922-34 qualification handbook

About 60 minutes

Typical time allowed for the 2922-34 online knowledge test

City & Guilds 2922-34 assessment information

Around 75%

Common e-volve pass standard for the 2922-34 knowledge test

City & Guilds e-volve assessment

Level 3 plus 18th Edition

Entry requires a Level 3 electrotechnical qualification and 18th Edition, or an ECS Gold Card

City & Guilds 2922-34 entry requirements

Section 712

BS 7671 Section 712 sets the special requirements for solar PV power supply systems

BS 7671:2018+A2:2022 IET Wiring Regulations

16 A per phase

G98 applies up to 16 A per phase; above this G99 applies and needs DNO approval first

Energy Networks Association EREC G98/G99

LO4 = 53%

Design and installation considerations is the most heavily weighted knowledge-test outcome

City & Guilds 2922-34 test specification

100

Free original practice questions in this bank

OpenExamPrep

City & Guilds 2922-34 is a Level 3 Award that qualifies competent electricians to install and maintain small solar PV systems and progress toward MCS registration. Assessment is an online multiple-choice knowledge test of about 30 questions (unit 301, roughly 60 minutes, commonly around a 75 percent pass standard, open book) plus a separate practical assignment (unit 302). Entry requires an existing Level 3 electrotechnical qualification plus 18th Edition, or an equivalent ECS Gold Card, and learners must be 18 or over. The knowledge test is weighted toward design and installation considerations (LO4, 53 percent) and PV characteristics, components and architectures (LO3, 30 percent), with BS 7671 Section 712, the IET Code of Practice and MCS/G98/G99 requirements running throughout. This 100-question bank gives original practice across PV principles, components, electrical safety, design and siting, and commissioning, testing and maintenance.

Sample C&G 2922-34 Solar PV Practice Questions

Try these sample questions to test your C&G 2922-34 Solar PV exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1In a solar cell, what physical process converts sunlight directly into electrical energy?
A.The photoelectric heating of water
B.The photovoltaic effect
C.Electromagnetic induction
D.Thermionic emission
Explanation: A solar cell generates electricity through the photovoltaic effect: photons of light free charge carriers in a semiconductor p-n junction, producing a direct current. This is distinct from heat-based or induction-based generation.
2Solar irradiance at a site is normally expressed in which units?
A.Watts per square metre (W/m2)
B.Kilowatt-hours (kWh)
C.Amperes (A)
D.Lumens (lm)
Explanation: Irradiance is the instantaneous power of solar radiation falling on a surface, measured in watts per square metre (W/m2). Standard Test Conditions use 1000 W/m2.
3PV modules are rated at Standard Test Conditions (STC). Which set of values defines STC?
A.800 W/m2, 20 C cell temperature, AM1.0
B.1000 W/m2, 25 C cell temperature, AM1.5
C.1000 W/m2, 45 C cell temperature, AM1.0
D.1200 W/m2, 25 C cell temperature, AM2.0
Explanation: Standard Test Conditions are 1000 W/m2 irradiance, a cell temperature of 25 C and an air mass of AM1.5. Module peak power (Wp) is quoted at STC so products can be compared fairly.
4On a module I-V curve, which point represents the condition where the module delivers its greatest power output?
A.The open-circuit voltage (Voc)
B.The short-circuit current (Isc)
C.The maximum power point (MPP)
D.The point where current equals zero
Explanation: The maximum power point (MPP) is the combination of voltage (Vmp) and current (Imp) that yields the highest power on the I-V curve. Inverters use maximum power point tracking (MPPT) to hold the array near this point.
5What happens to a crystalline silicon module's open-circuit voltage (Voc) as the cell temperature falls below 25 C?
A.Voc decreases
B.Voc increases
C.Voc stays exactly the same
D.Voc drops to zero
Explanation: Crystalline silicon modules have a negative temperature coefficient for voltage, so as the cell gets colder than STC the Voc rises. This is why the maximum system DC voltage must be calculated using the lowest expected cell temperature.
6Three identical 12 V, 8 A PV modules are connected in series. What is the approximate output voltage and current of the string?
A.12 V at 24 A
B.36 V at 8 A
C.36 V at 24 A
D.12 V at 8 A
Explanation: Connecting modules in series adds their voltages while the current stays the same. Three 12 V modules give 36 V, and the current remains 8 A. This is the basis of building a string to reach a usable DC voltage.
7Two PV strings, each producing 30 V at 9 A, are connected in parallel. What is the combined output?
A.60 V at 9 A
B.30 V at 18 A
C.60 V at 18 A
D.30 V at 9 A
Explanation: Connecting strings in parallel adds their currents while the voltage stays the same. Two 9 A strings give 18 A, and the voltage remains 30 V. Parallel grouping increases array current.
8A roof has space for 10 PV modules each rated at 410 Wp. What is the nominal peak power (array rating) of the installation?
A.41 kWp
B.4.1 kWp
C.410 kWp
D.0.41 kWp
Explanation: Array peak power is the sum of the module peak powers: 10 x 410 Wp = 4100 Wp = 4.1 kWp. This nominal rating is used for design, DNO notification and yield estimates.
9What does the term 'peak power' or Wp of a PV module describe?
A.Its output at any time of day
B.Its rated DC power output at Standard Test Conditions
C.The maximum AC power its inverter can deliver
D.Its output on the shortest day of the year
Explanation: Peak power (watt-peak, Wp) is the module's rated DC power output measured at Standard Test Conditions of 1000 W/m2 and 25 C. Real output varies with actual irradiance and temperature.
10Why is the current produced by a PV array described as direct current (DC) rather than alternating current (AC)?
A.Because it reverses direction 50 times per second
B.Because it flows in one direction only
C.Because it is always above 230 V
D.Because it cannot be measured with a meter
Explanation: PV cells produce direct current, which flows in one constant direction. An inverter is required to convert this DC into 230 V 50 Hz AC that is compatible with the grid and household loads.

About the C&G 2922-34 Solar PV Exam

The City & Guilds 2922-34 Level 3 Award is a specialist CPD qualification that lets already-qualified electricians install and maintain small solar photovoltaic (PV) systems in domestic and small commercial settings and work toward Microgeneration Certification Scheme (MCS) registration. It is assessed by an online (e-volve) multiple-choice knowledge test (unit 301) plus a practical assignment (unit 302). The syllabus aligns with BS 7671 (the 18th Edition IET Wiring Regulations, including Section 712 for solar PV) and the IET Code of Practice for Grid-Connected Solar Photovoltaic Systems, and covers PV principles, components, system design and siting, electrical safety, MCS requirements, G98/G99 DNO notification and commissioning, testing and maintenance.

Assessment

Two parts: unit 301 online multiple-choice knowledge test (about 30 questions on the City & Guilds e-volve platform) and unit 302 centre-assessed practical assignment. Knowledge-test outcomes are weighted LO1-LO2 PV/EESS introduction 7%, LO3 characteristics/components/architectures 30%, LO4 design and installation considerations 53% and LO6 microgeneration/EESS prosumer 10%.

Time Limit

The online knowledge test is typically about 60 minutes; the practical assignment is timed separately within the course.

Passing Score

Graded pass/fail. The online knowledge test is marked against the City & Guilds e-volve pass standard for unit 301 (commonly around 75 percent), and the practical assignment must also be passed.

Exam Fee

Registration fees are set by approved centres; the typical instructor-led course including assessment is around GBP 500-GBP 1,200 depending on the provider. (City & Guilds)

C&G 2922-34 Solar PV Exam Content Outline

7%

PV principles, EESS introduction and operating theory

Practice on the photovoltaic effect, irradiance and its units, cell-module-array hierarchy, the I-V and power curves, DC versus AC, temperature effects on voltage, and an introduction to electrical energy storage systems (EESS).

30%

PV systems, components and architectures

Practice on PV modules and ratings, string and micro inverters, power optimisers, mounting and racking systems, DC and AC cabling and connectors (such as MC4), DC and AC isolators, generation metering and overall system architectures including AC-coupled and DC-coupled storage.

53%

Design, siting and installation considerations

Practice on orientation, tilt and shading analysis, irradiance and yield estimation, roof structure and wind/snow loading, BS 7671 Section 712 requirements, DC isolation, earthing, bonding and surge protection, working at height and roof safety, and commissioning, inspection, testing and documentation to the IET Code of Practice and IEC 62446-1.

10%

Microgeneration and prosumer EESS integration

Practice on MCS requirements and MIS 3002, DNO notification under EREC G98 and G99 and the 16 A per phase threshold, integration of battery storage and self-consumption, and the documentation a prosumer installation must provide.

How to Pass the C&G 2922-34 Solar PV Exam

What You Need to Know

  • Passing score: Graded pass/fail. The online knowledge test is marked against the City & Guilds e-volve pass standard for unit 301 (commonly around 75 percent), and the practical assignment must also be passed.
  • Assessment: Two parts: unit 301 online multiple-choice knowledge test (about 30 questions on the City & Guilds e-volve platform) and unit 302 centre-assessed practical assignment. Knowledge-test outcomes are weighted LO1-LO2 PV/EESS introduction 7%, LO3 characteristics/components/architectures 30%, LO4 design and installation considerations 53% and LO6 microgeneration/EESS prosumer 10%.
  • Time limit: The online knowledge test is typically about 60 minutes; the practical assignment is timed separately within the course.
  • Exam fee: Registration fees are set by approved centres; the typical instructor-led course including assessment is around GBP 500-GBP 1,200 depending on the provider.

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

C&G 2922-34 Solar PV Study Tips from Top Performers

1Make sure your 18th Edition knowledge is current, especially BS 7671 Section 712 for solar PV, because the test assumes you already understand general electrical installation requirements.
2Practise the core PV calculations: modules in series add voltage while current stays the same, modules in parallel add current while voltage stays the same, and array power is roughly module power times the number of modules.
3Learn the G98 and G99 split cold: G98 applies up to and including 16 A per phase (about 3.68 kW single phase) with notification within 28 days, while G99 applies above that and needs DNO approval before connection.
4Because the knowledge test is open book, tab your BS 7671 and IET Code of Practice so you can find isolation, earthing, labelling and SPD requirements quickly.
5Understand why module voltage rises in cold conditions, since maximum Voc at the lowest expected temperature drives DC cable, isolator and inverter voltage ratings.
6Revise the commissioning and test sequence from the IET Code of Practice and IEC 62446-1, including insulation resistance, polarity, string open-circuit voltage and short-circuit current checks, and what goes in the handover documentation.

Frequently Asked Questions

How is the City & Guilds 2922-34 qualification assessed?

There are two parts: an online (e-volve) multiple-choice knowledge test (unit 301) of about 30 questions, and a centre-assessed practical assignment (unit 302). Both must be passed and the qualification is graded pass/fail.

How many questions are on the 2922-34 knowledge test and how long is it?

The online knowledge test has approximately 30 multiple-choice questions and typically lasts about 60 minutes. It is open book, so candidates can refer to BS 7671 and the IET Code of Practice.

What pass mark do I need?

The knowledge test is graded pass/fail against the City & Guilds e-volve pass standard for unit 301, which is commonly around 75 percent. The practical assignment must also be passed separately.

What are the entry requirements for 2922-34?

You must already hold a Level 3 electrotechnical qualification (such as C&G 2357 or 5357) plus an 18th Edition (BS 7671) qualification, or an equivalent ECS Gold Card, and be aged 18 or over. It is a specialist CPD award, not an entry-level course.

Which standards does the 2922-34 syllabus cover?

It covers BS 7671 (the 18th Edition IET Wiring Regulations, especially Section 712 for solar PV), the IET Code of Practice for Grid-Connected Solar Photovoltaic Systems, MCS requirements (including MIS 3002), and G98/G99 DNO notification.

Does passing 2922-34 make me MCS certified?

No. The qualification demonstrates the competence required for MCS, but MCS certification is a separate process applied for through an MCS certification body, usually alongside membership of a Competent Person Scheme.