Cheat sheet

PMI-RMP Cheat Sheet

Risk Strategy & Planning

20-24%of exam

Appetite vs ThresholdRisk Mgmt PlanRBSRegister vs ReportReserve Types

Stakeholder Engagement

18-22%of exam

Risk AttitudeRisk CommunicationOwner vs Action OwnerReconcile Thresholds

Risk Process Facilitation

23-27%of exam

Identification ToolsResponse StrategiesContingency vs FallbackWorkaround

Risk Monitoring & Reporting

17-21%of exam

Audit vs ReviewReserve AnalysisKRI vs TriggerRisk Closure

Specialized Risk Analyses

12-16%of exam

Qualitative vs QuantitativeEMVDecision TreeMonte CarloSensitivity

Quick Facts

Exam
PMI-RMP
Credential
Risk Mgmt Professional
Questions
115 (100 scored)
Time
150 min
Pass
Pass/Fail scaled
Eligibility
24-36 mo + 30-40 hrs
Validity
3 yr / 60 PDU
Provider
PMI / Pearson VUE

Reserve Types

Contingency=known | Management=unknown

Contingency: in baselineManagement: outside baselinePM vs sponsor

Contingency vs Management Reserve

Contingency

  • Known risks
  • Inside baseline
  • PM controls

Management

  • Unknown risks
  • Outside baseline
  • Mgmt approval

Known-unknowns vs unknown-unknowns

Core Risk Terms

Risk
Uncertain event/condition
Threat
Negative-effect risk
Opportunity
Positive-effect risk
Individual risk
Single uncertain event
Overall risk
Cumulative project exposure
Residual risk
Leftover after response
Secondary risk
New risk from response
Risk trigger
Warning sign/symptom

Risk Register vs Risk Report

Register

  • Individual risks
  • Owner/response/status
  • Detail

Report

  • Overall risk
  • Big-picture exposure
  • Summary

Detail vs summary

Appetite & Thresholds

Risk appetite
Strategic uncertainty accepted
Risk tolerance
Acceptable variation band
Risk threshold
Specific action trigger point
Risk attitude
Stakeholder uncertainty stance
Risk capacity
Risk org can absorb
Risk culture
Shared risk behaviors

Planning Artifacts

Risk Mgmt Plan
How risk is managed
Risk Register
Individual risk detail
Risk Report
Overall risk summary
RBS
Risk sources hierarchy
Risk owner
Accountable for monitoring
Action owner
Executes response action
P-I definitions
Rating scales agreed

Reserves & Baseline

Contingency reserve
Known risks, in baseline
Management reserve
Unknown risks, outside baseline
Cost baseline
Estimates + contingency
Total budget
Baseline + management reserve
Reserve sizing
From EMV / simulation
PM authority
Spends contingency only

Stakeholder Engagement

Risk attitude
Appetite + tolerance + perception
Engage stakeholders
Surface and own risks
Risk communication
Timely exposure updates
Reconcile thresholds
Align differing attitudes
Risk Report use
Overall-risk communication vehicle
Buy-in
Secure response support

Threat Responses

Every Angry Tiger Must Accept

EscalateAvoidTransferMitigateAccept

Residual vs Secondary Risk

Residual

  • Leftover risk
  • After response
  • What remains

Secondary

  • New risk
  • From the response
  • Side effect

Still left vs newly created

Which Response Strategy?

  1. Threat outside authorityEscalate(Program/portfolio)
  2. Eliminate threat causeAvoid(Remove uncertainty)
  3. Shift threat impactTransfer(Insurance/contract)
  4. Reduce threatMitigate(Lower prob/impact)
  5. Accept minor threatAccept(Active reserve)
  6. Opp outside authorityEscalate(Program/portfolio)
  7. Make opp certainExploit(Guarantee upside)
  8. Allocate opp to partnerShare(Joint venture)
  9. Boost oppEnhance(Raise prob/impact)

Identification Tools

Delphi
Anonymous expert consensus
SWOT
Strengths/weaknesses/opps/threats
Ishikawa
Cause-and-effect fishbone
Assumption analysis
Tests assumption validity
Prompt lists
PESTLE/TECOP/VUCA categories
Brainstorming
Group idea generation
Interviews
Expert elicitation
Checklists
Past-project risk lists

Opportunity Responses

Every Eager Shark Eats Anything

EscalateExploitShareEnhanceAccept

Threat vs Opportunity Response

Threat

  • Avoid
  • Transfer
  • Mitigate

Opportunity

  • Exploit
  • Share
  • Enhance

Both: Escalate + Accept

Threat Responses

Escalate
Hand outside project authority
Avoid
Eliminate the cause
Transfer
Shift impact to third-party
Mitigate
Reduce probability/impact
Accept
No proactive action
Active accept
Set contingency reserve
Passive accept
Document, review only

Risk Process Flow

Plan -> ID -> Analyze -> Respond -> Monitor

Plan: methodologyID: find risksAnalyze: prioritizeRespond: strategiesMonitor: track

Contingency vs Fallback Plan

Contingency

  • Plan A
  • On trigger
  • Pre-planned

Fallback

  • Plan B
  • If A fails
  • Held in reserve

First response vs backup

Opportunity Responses

Escalate
Hand outside project authority
Exploit
Make opportunity certain
Share
Allocate to best partner
Enhance
Increase probability/impact
Accept
Take if it arises

Transfer vs Share

Transfer

  • Threat impact
  • Third party
  • Insurance/contract

Share

  • Opportunity
  • Best partner
  • Joint venture

Threat vs opportunity handoff

Response Plans

Contingency plan
Plan A on trigger
Fallback plan
Plan B if A fails
Workaround
Unplanned response, improvised
Secondary risk
Created by response
Residual risk
Remains after response

Risk Audit vs Risk Review

Audit

  • Process effectiveness
  • Responses working?
  • Evaluates method

Review

  • Reassess risks
  • Close outdated
  • Find new

Process vs the risks

Which Monitoring Activity?

  1. Check process worksRisk audit(Effectiveness)
  2. Reassess open risksRisk review(Close/find)
  3. Reserves still enough?Reserve analysis(Reserve vs risk)
  4. Trend signals exposureKRI(Leading metric)
  5. Risk window passedRisk closure(Archive)

Monitoring Tools

Risk audit
Evaluates process effectiveness
Risk review
Reassess and close risks
Reserve analysis
Reserve vs risk remaining
Reassessment
Find new risks
Risk closure
Risk can't occur
Variance/trend
EVM forecasts exposure
KRI
Leading exposure metric
Lessons learned
Feeds future projects

EMV

EMV = Probability x Impact ($)

Threat: negativeOpportunity: positiveSum across branch

Qualitative vs Quantitative

Qualitative

  • Subjective
  • Prioritize risks
  • Fast/always

Quantitative

  • Numeric
  • Overall outcome
  • Optional/heavy

Rank vs model in dollars

Which Analysis Technique?

  1. Fast prioritizationQualitative(P-I matrix)
  2. Rank by prob x impactP-I matrix(Subjective)
  3. Numeric cost/scheduleQuantitative(After qualitative)
  4. Model overall outcomeMonte Carlo(S-curve)
  5. Compare decisionsDecision tree(EMV branches)
  6. Single-risk valueEMV(P x impact)
  7. Find key driversSensitivity(Tornado)
  8. Estimate duration rangePERT(3-point)

Qualitative Tools

Qualitative analysis
Subjective prioritization
P-I matrix
Probability x impact grid
Risk score
Probability x impact rating
Data quality
Assess data reliability
Urgency
Time before response
Proximity
How soon risk hits
Detectability
Ease of early warning
Categorization
Group by source/cause

Quantitative Tools

Quantitative analysis
Numeric overall outcomes
EMV
Probability x impact value
Decision tree
EMV across choices
Monte Carlo
Iterative random simulation
S-curve
Probability of target
Sensitivity
Most-influential variables
Tornado diagram
Ranks impact bars
PERT/3-point
Optimistic-likely-pessimistic estimate

Key Formulas

EMV
P x Impact ($)
Risk score
Probability x Impact
Triangular mean
(O + M + P) / 3
PERT/Beta mean
(O + 4M + P) / 6
Threat EMV
Negative sign
Opportunity EMV
Positive sign
Cost baseline
Work + contingency

Common Traps

Reserve type

Contingency = known-unknowns Management = unknown-unknowns

Residual vs secondary

Residual is leftover Secondary is new

Tolerance vs threshold

Tolerance is a band Threshold is a line

Transfer vs share

Transfer a threat Share an opportunity

Audit vs review

Audit the process Review the risks

Contingency vs fallback

Contingency on trigger Fallback if it fails

Register vs report

Register lists risks Report summarizes overall

Last Minute

  1. 1.115 questions, 100 scored, 150 minutes
  2. 2.Threats: Escalate Avoid Transfer Mitigate Accept
  3. 3.Opportunities: Escalate Exploit Share Enhance Accept
  4. 4.Escalate + Accept apply to both
  5. 5.Contingency = known risks, inside baseline
  6. 6.Management reserve = unknown risks, outside baseline
  7. 7.Residual = leftover; Secondary = new from response
  8. 8.Tolerance = band; Threshold = trigger line
  9. 9.EMV = Probability x Impact; threats negative
  10. 10.PERT mean = (O + 4M + P) / 6
  11. 11.Qualitative first, then quantitative
  12. 12.Register = detail; Report = overall summary
  13. 13.Contingency plan first; fallback as backup
Same family resources

Explore More PMI Certifications

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.