All Practice Exams

198+ Free PMI-RMP Practice Questions

Pass your PMI Risk Management Professional exam on the first try — instant access, no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
Not published by PMI Pass Rate
198+ Questions
100% Free
1 / 10
Question 1
Score: 0/0

What is the primary purpose of a risk management framework in project management?

A
B
C
D
to track
2026 Statistics

Key Facts: PMI-RMP Exam

115

Total Questions

100 scored + 15 pretest

~65-70%

Passing Score (scaled)

PMI

2.5 hrs

Exam Duration

PMI

$520-670

Exam Fee

PMI member/non-member

23%

Risk Analysis Domain

Largest domain

3 attempts

Per Eligibility Year

PMI policy

The PMI-RMP exam has 115 questions (100 scored + 15 pretest) in 2.5 hours. Five domains: Risk Analysis (23%), Risk Identification (21%), Monitor & Close Risks (21%), Risk Response (20%), and Risk Strategy & Governance (15%). Requires secondary degree + 36 months risk management experience + 40 hours training OR 4-year degree + 24 months + 30 hours. PMI member fee $520, non-member $670.

Sample PMI-RMP Practice Questions

Try these sample questions to test your PMI-RMP exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 198+ question experience with AI tutoring.

1What is the primary purpose of a risk management framework in project management?
A.To eliminate all project risks before the project begins
B.To provide structure and guidance for risk management activities throughout the project life cycle
C.To assign blame when risks materialize into issues
D.To document only the risks that have already occurred
Explanation: A risk management framework provides the structure, processes, and governance for managing risk throughout the project. It establishes how risk management will be conducted, who is responsible, and what tools and techniques will be used. The framework does not eliminate all risks (which is impossible), nor is it for assigning blame. It is proactive, not just documenting past risks.
2A project manager is developing a risk management plan for a new enterprise software implementation. Which of the following should be established FIRST when creating the risk management framework?
A.Detailed risk response strategies for all identified risks
B.Risk thresholds and escalation criteria
C.The methodology, roles and responsibilities, and timing for risk management activities
D.A comprehensive list of all potential risks
Explanation: The risk management plan (which establishes the framework) should first define the methodology (how risk management will be performed), roles and responsibilities (who will do what), and timing (when risk activities will occur). These foundational elements guide all subsequent risk activities. You cannot create detailed response strategies or a complete risk list until the framework is established, and thresholds require understanding the methodology first.
3An organization is implementing a standardized risk management framework across all projects. Which of the following BEST describes how this framework should be tailored for individual projects?
A.The framework should be applied identically to all projects regardless of size or complexity
B.The framework should be tailored based on project size, complexity, risk exposure, and organizational culture
C.Small projects should skip risk management entirely
D.Only high-risk projects need a risk management framework
Explanation: Risk management frameworks should be tailored to fit the specific context of each project. Factors like project size, complexity, strategic importance, risk exposure, and organizational culture influence how the framework is applied. All projects need some level of risk management, but the rigor and formality should be appropriate to the project. Skipping risk management for small projects or only applying frameworks to high-risk projects would leave gaps in risk coverage.
4Which document establishes the governance approach for risk management by defining risk categories, probability and impact scales, and risk reporting formats?
A.Risk register
B.Risk management plan
C.Issue log
D.Change control log
Explanation: The risk management plan is the document that establishes how risk management will be structured and performed on a project. It includes risk categories (often organized in a Risk Breakdown Structure), probability and impact definitions and scales, risk reporting formats, tracking mechanisms, and other governance elements. The risk register contains specific identified risks, the issue log tracks problems that have already occurred, and the change control log tracks change requests.
5What is the difference between risk appetite and risk tolerance?
A.Risk appetite is the specific amount of risk acceptable on a single project, while risk tolerance applies to the entire organization
B.Risk appetite is the degree of uncertainty an organization is willing to accept in pursuit of objectives, while risk tolerance is the specific range of variation around objectives that is acceptable
C.Risk appetite and risk tolerance are synonymous terms with no meaningful difference
D.Risk tolerance is set by the project manager, while risk appetite is determined by the customer
Explanation: Risk appetite describes the general attitude toward risk — how much uncertainty the organization is willing to embrace in pursuit of value. Risk tolerance is more specific, defining the acceptable variation around objectives (e.g., +/- 10% on budget). Risk appetite is broader and strategic, while risk tolerance is measurable and project-specific. Both are typically established by organizational leadership, not just the PM or customer.
6An organization has stated that it has a "low risk appetite" for safety-related risks but a "high risk appetite" for innovation risks. How should a project manager interpret this guidance?
A.All risks should be treated with the same level of caution regardless of category
B.Safety risks require aggressive mitigation strategies while innovation risks can be accepted more readily
C.The project should avoid all innovation to minimize risk
D.Risk appetite statements are irrelevant to project-level risk management
Explanation: Risk appetite can vary by risk category. A low risk appetite for safety means the organization wants rigorous controls and conservative approaches for safety risks. A high risk appetite for innovation means the organization is willing to accept more uncertainty when pursuing innovative solutions. This guides the PM in selecting appropriate response strategies — aggressive mitigation for safety, acceptance or moderate mitigation for innovation. Risk appetite directly informs project risk decisions.
7A project has established that cost overruns up to 5% are within risk tolerance, but overruns exceeding 10% require immediate escalation to the steering committee. This represents an example of:
A.Risk appetite statement
B.Risk threshold definition
C.Risk response strategy
D.Risk transfer mechanism
Explanation: Risk thresholds are specific measures of acceptable variation around objectives with defined escalation points. In this case, the 5% and 10% limits are measurable thresholds that trigger different actions. Risk appetite is broader (the general willingness to accept cost uncertainty). Response strategies are actions taken for specific risks, and transfer is a specific response type (shifting risk to a third party).
8During project execution, a risk is identified that would cause a schedule delay of 3 weeks. The project steering committee has established that any risk with a potential impact greater than 2 weeks must be escalated immediately. What should the project manager do?
A.Handle the risk independently without escalation since it has not occurred yet
B.Escalate the risk to the steering committee as it exceeds the defined risk threshold
C.Wait until the risk actually occurs before escalating
D.Reduce the estimated impact to 2 weeks to avoid escalation
Explanation: Risk thresholds establish clear criteria for when escalation is required. When a risk is identified that exceeds the defined threshold (in this case, >2 weeks schedule impact), the PM must escalate according to the governance structure. Waiting for the risk to occur defeats the purpose of proactive risk management, and manipulating estimates to avoid escalation violates professional ethics and undermines risk governance.
9Who is typically responsible for establishing risk governance structures at the organizational level?
A.Individual project managers
B.Executive management and the board of directors
C.External consultants
D.Project team members
Explanation: Risk governance at the organizational level is the responsibility of executive management and the board of directors. They establish the risk management policies, framework, appetite, and oversight mechanisms. Project managers implement risk management within the governance structure established by the organization. Project teams execute risk responses, and consultants may advise but do not establish governance.
10A project manager is developing a risk management plan and needs to define roles and responsibilities. Which role is typically responsible for providing the resources and funding needed for risk responses?
A.Risk owner
B.Project sponsor
C.Risk manager
D.Project team member
Explanation: The project sponsor is responsible for providing resources and funding for the project, including risk responses. The risk owner is responsible for monitoring specific risks and implementing agreed-upon responses. A risk manager (if designated) coordinates risk activities, and team members may execute specific response actions. However, securing funding and resources is a sponsor responsibility.

About the PMI-RMP Exam

The PMI-RMP (Risk Management Professional) exam validates expertise in project risk management including risk strategy and governance, risk identification, qualitative and quantitative analysis, risk response planning, and risk monitoring and control. The exam has 115 questions (100 scored + 15 pretest).

Questions

115 scored questions

Time Limit

2.5 hours (150 minutes)

Passing Score

Pass/Fail (scaled, ~65-70%)

Exam Fee

$520 (members) / $670 (non-members) (Project Management Institute (PMI) / Pearson VUE)

PMI-RMP Exam Content Outline

15%

Risk Strategy and Governance

Risk management framework, risk appetite/tolerance, governance structures, risk policies, risk culture

21%

Risk Identification

Threat and opportunity identification, risk categorization (RBS), SWOT, Ishikawa, risk register

23%

Risk Analysis

Qualitative analysis, quantitative analysis, Monte Carlo, EMV, decision trees, sensitivity analysis

20%

Risk Response

Threat responses (escalate, avoid, transfer, mitigate, accept), opportunity responses, contingency plans

21%

Monitor and Close Risks

Risk monitoring and control, risk audits, trigger monitoring, risk closure, lessons learned

How to Pass the PMI-RMP Exam

What You Need to Know

  • Passing score: Pass/Fail (scaled, ~65-70%)
  • Exam length: 115 questions
  • Time limit: 2.5 hours (150 minutes)
  • Exam fee: $520 (members) / $670 (non-members)

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

PMI-RMP Study Tips from Top Performers

1Focus on Risk Analysis (23%) — master qualitative analysis, Monte Carlo simulation, EMV, and decision trees
2Know all risk response strategies: 5 for threats (escalate, avoid, transfer, mitigate, accept) and 5 for opportunities (escalate, exploit, share, enhance, accept)
3Understand the Risk Breakdown Structure (RBS) and how it categorizes risks at multiple levels
4Study risk monitoring tools: risk audits, risk reviews, trigger monitoring, reserve analysis, and variance analysis
5Know the difference between risk appetite, risk tolerance, and risk threshold — these are commonly tested
6Practice with scenario-based questions — PMI exams focus on application, not memorization

Frequently Asked Questions

What is the PMI-RMP certification?

PMI-RMP (Risk Management Professional) is a PMI certification that validates expertise in project risk management. It is designed for project professionals who specialize in risk assessment, analysis, response planning, and monitoring across the project lifecycle.

How many questions are on the PMI-RMP exam?

The PMI-RMP exam has 115 questions (100 scored + 15 pretest) in 2.5 hours (150 minutes). The exam uses a pass/fail scoring system with a scaled passing threshold of approximately 65-70%. Administered at Pearson VUE centers.

What are the prerequisites for the PMI-RMP exam?

Path 1: Secondary degree + 36 months risk management experience + 40 contact hours of training. Path 2: Four-year degree + 24 months experience + 30 contact hours. Experience must be within the last 5 years.

How does PMI-RMP compare to PMP?

PMP covers all aspects of project management while PMI-RMP focuses specifically on risk management. PMI-RMP is ideal for risk specialists who want to demonstrate deep expertise in risk identification, analysis, response, and monitoring.

How should I prepare for the PMI-RMP exam?

Plan for 100-150 hours of study over 8-12 weeks. Focus on Risk Analysis (23%) — master Monte Carlo simulation, EMV, and decision trees. Also prioritize Risk Identification (21%) and Monitor & Close (21%). Study the PMBOK Guide risk management chapter thoroughly.