6.2 Maximum Demand Calculation and Diversity Factors for ≤45 kVA
Key Takeaways
- Connected Load is the total sum of continuous power ratings of all installed electrical appliances, whereas Maximum Demand is the actual peak load expected during normal operation.
- Applying diversity factors per SS 638 Appendix 4 accounts for the non-simultaneous usage of connected appliances, preventing unnecessary over-sizing of supply cables and main switchgear.
- In Singapore, single-phase supplies are generally restricted to 30A or 60A (up to ~14 kVA); loads exceeding 14 kVA require upgrade to a 3-phase 400V supply rated up to 45 kVA (~63A per phase).
- The three-phase apparent power formula S = √3 × VL × IL (where VL = 400V) converts line current to kVA: S(kVA) = 0.6928 × IL.
- Phase balancing across L1, L2, and L3 is critical in 3-phase installations to minimize neutral current and optimize transformer efficiency.
6.2 Maximum Demand Calculation and Diversity Factors for ≤45 kVA
Quick Summary: Maximum Demand (MD) is the maximum load current or power drawn by an electrical installation from the supply grid during any specified operational interval. Because not all electrical appliances, lights, or socket outlets operate simultaneously at full rated capacity, calculating maximum demand using Diversity Factors under SS 638 Appendix 4 allows engineers to determine the realistic peak load. Proper maximum demand calculation prevents costly over-design while ensuring incoming supply cables, main cut-out fuses, and circuit breakers do not trip under normal peak operating conditions.
1. Connected Load vs. Maximum Demand
Before sizing intake cables and protective switchgear, a clear distinction must be made between Connected Load and Maximum Demand:
- Total Connected Load ($P_{conn}$ or $S_{conn}$): The mathematical sum of the full-load power ratings of all installed electrical equipment, luminaires, socket outlets, motors, and appliances connected to the installation.
- Maximum Demand ($I_{md}$ or $S_{md}$): The maximum current or apparent power actually drawn by the installation at any one time under normal operating conditions. It is calculated by applying standardized diversity factors to individual sub-circuits.
- Diversity Factor: The ratio of the sum of individual maximum demands of sub-circuits to the maximum demand of the complete installation. In practical design, diversity factors are expressed as derating percentages or fixed allowances applied to connected loads.
2. Supply Capacity Boundaries in Singapore (≤45 kVA Regime)
In Singapore, SP PowerGrid classifies low-voltage electricity supplies based on load capacity boundaries:
Single-Phase 230V Supply Limits
- 30A Single-Phase: Equivalent to $30\text{ A} \times 230\text{ V} = 6.9\text{ kVA}$. Standard intake for small domestic apartments.
- 60A Single-Phase: Equivalent to $60\text{ A} \times 230\text{ V} = 13.8\text{ kVA} \approx 14\text{ kVA}$. Maximum permissible single-phase supply allocation for residential or commercial units.
- Threshold Rule: If the calculated maximum demand exceeds $60\text{ A}$ (or $14\text{ kVA}$), SP PowerGrid mandates an upgrade to a Three-Phase 400V supply to prevent severe phase imbalance on the distribution network.
Three-Phase 400V Supply up to 45 kVA
- 45 kVA 3-Phase Rating: The maximum capacity boundary for standard small-commercial, food shop, office, or residential house installations operating on direct CT-less or standard 63A meter cut-outs.
- Current per Phase Calculation: For a balanced $45\text{ kVA}$ 3-phase supply at $400\text{ V}$ line voltage:
Thus, a $45\text{ kVA}$ 3-phase supply corresponds to a standard $63\text{ A}$ 3-pole main isolator / MCCB per phase.
3. SS 638 Appendix 4 Diversity Factor Rules
Singapore Standard SS 638 Appendix 4 provides prescriptive rules for estimating maximum demand across domestic, commercial, and small industrial premises. The table below summarizes the mandatory diversity allowances:
| Type of Load Circuit | Domestic Premises Diversity Allowance | Commercial / Office Premises Diversity Allowance | Small Industrial Premises Diversity Allowance |
|---|---|---|---|
| Lighting Circuits | 66% of total connected lighting load | 90% of total connected lighting load | 90% of total connected lighting load |
| 13A Socket-Outlet Circuits | 100% of largest circuit + 40% of remaining socket circuits | 100% of largest circuit + 50% of remaining socket circuits | 100% of largest circuit + 50% of remaining socket circuits |
| Cooking Appliances | 10A + 30% of remaining full load + 5A for socket on switch unit | 100% of largest appliance + 80% of 2nd + 60% of remaining | 100% of largest appliance + 80% of 2nd + 60% of remaining |
| Instantaneous Water Heaters | 100% of largest heater + 100% of 2nd heater + 25% of remaining | 100% of largest heater + 100% of 2nd heater + 50% of remaining | 100% of largest heater + 100% of 2nd heater + 50% of remaining |
| Thermal Storage Water Heaters | 100% full load (No diversity allowed) | 100% full load (No diversity allowed) | 100% full load (No diversity allowed) |
| Air-Conditioning & Motors | 100% of largest AC unit + 80% of 2nd unit + 60% of remaining | 100% of largest motor/AC + 80% of 2nd motor + 60% of remaining | 100% of largest motor + 80% of 2nd motor + 60% of remaining |
4. Single-Phase and Three-Phase Power Formulas
To compute phase currents accurately from connected active power ($P$ in kW) or apparent power ($S$ in kVA), use the standard electrical power equations:
Single-Phase Calculations (230V AC)
Three-Phase Calculations (400V Line-to-Line / 230V Line-to-Neutral)
Phase Balancing and Neutral Current
In a 3-phase 4-wire installation, single-phase loads must be distributed evenly across Phase L1, Phase L2, and Phase L3. If the phase currents $I_1, I_2, I_3$ are balanced ($I_1 = I_2 = I_3$), the neutral current $I_N = 0\text{ A}$. For unbalanced loads, the resultant vector neutral current is calculated using:
5. Comprehensive Step-by-Step Worked Maximum Demand Calculation
Example Scenario:
A small commercial office unit with a 3-phase 400V supply has the following connected loads:
- Lighting: $40 \times 2 \times 18\text{W}$ LED panel fittings ($0.95$ power factor, total $1.52\text{ kW}$). Distributed equally: $0.507\text{ kW}$ per phase.
- Socket Outlets: 6 separate $13\text{A}$ twin ring final circuits ($32\text{A}$ protection each). 2 ring circuits connected to L1, 2 to L2, 2 to L3.
- Water Heating: $2 \times 3.5\text{ kW}$ single-phase instantaneous water heaters ($15.2\text{ A}$ each at $230\text{V}$). Heater 1 on L1, Heater 2 on L2.
- Air-Conditioning: $3 \times 3\text{HP}$ 3-phase cassette air-conditioners ($3\text{ kW}$ each, $\cos\phi = 0.85$, total $9\text{ kW}$). Line current per AC unit $= \frac{3000}{\sqrt{3} \times 400 \times 0.85} = 5.1\text{ A}$.
Step-by-Step Calculation Solution:
Step 1: Calculate Diversity for Lighting (Commercial: 90% allowance)
- Total Connected Lighting Power $= 1,520\text{ W}$
- Maximum Demand Power $= 1,520\text{ W} \times 0.90 = 1,368\text{ W}$
- Total 3-Phase Current $= \frac{1368}{\sqrt{3} \times 400 \times 0.95} = 2.08\text{ A per phase}$
Step 2: Calculate Diversity for 13A Socket Outlets (Commercial: 100% largest + 50% remaining)
- Each phase has 2 ring circuits rated at $32\text{A}$ capacity.
- Per Phase Socket Maximum Demand $= 100% \text{ of Circuit 1 } (32\text{A}) + 50% \text{ of Circuit 2 } (32\text{A} \times 0.50 = 16\text{A})$
- Per Phase Socket Maximum Demand $= 32\text{A} + 16\text{A} = 48\text{A per phase}$
Step 3: Calculate Diversity for Instantaneous Water Heaters (Commercial: 100% 1st + 100% 2nd)
- Heater 1 on L1 $= 15.2\text{ A}$
- Heater 2 on L2 $= 15.2\text{ A}$
- L3 Water Heater Load $= 0\text{ A}$
Step 4: Calculate Diversity for Air-Conditioning Units (3-Phase Motors: 100% 1st + 80% 2nd + 60% 3rd)
- Unit 1 (Largest) $= 100% \times 5.1\text{ A} = 5.1\text{ A}$
- Unit 2 $= 80% \times 5.1\text{ A} = 4.08\text{ A}$
- Unit 3 $= 60% \times 5.1\text{ A} = 3.06\text{ A}$
- Total AC Maximum Demand per Phase $= 5.1 + 4.08 + 3.06 = 12.24\text{ A per phase}$
Step 5: Tabulate Maximum Demand per Phase (L1, L2, L3)
| Load Category | Phase L1 Current (A) | Phase L2 Current (A) | Phase L3 Current (A) |
|---|---|---|---|
| Lighting | $2.08\text{ A}$ | $2.08\text{ A}$ | $2.08\text{ A}$ |
| 13A Sockets | $48.00\text{ A}$ | $48.00\text{ A}$ | $48.00\text{ A}$ |
| Water Heaters | $15.20\text{ A}$ | $15.20\text{ A}$ | $0.00\text{ A}$ |
| Air-Conditioning | $12.24\text{ A}$ | $12.24\text{ A}$ | $12.24\text{ A}$ |
| Total Phase Demand | $77.52\text{ A}$ | $77.52\text{ A}$ | $62.32\text{ A}$ |
Step 6: Determine Overall Maximum Demand in kVA and Verify Supply Class
- Peak Phase Line Current occurs on L1 / L2 at $77.52\text{ A}$.
- Overall 3-Phase Apparent Power Demand:
Technical Conclusion & Design Verification:
Since the calculated Maximum Demand is $53.71\text{ kVA}$ ($77.52\text{ A per phase}$), this exceeds the standard $45\text{ kVA}$ / $63\text{ A}$ supply limit. To bring this installation within the $45\text{ kVA}$ limit, the LEW must either:
- Apply load management or re-group socket circuits (reducing socket demand to $32\text{A}$ per phase base), or
- Upgrade the intake submission to SP PowerGrid for a $100\text{ A}$ 3-phase supply ($69.3\text{ kVA}$).
What is the calculated balanced line current per phase for a 3-phase installation drawing its maximum rated capacity of 45 kVA at 400V line voltage?
Under SS 638 Appendix 4, what is the diversity factor allowance for a commercial office installation with 10 installed 13A socket-outlet sub-circuits?
According to SP PowerGrid supply guidelines, what is the maximum single-phase 230V supply allocation permitted before a mandatory 3-phase 400V upgrade is required?