10.3 Time & Work, Efficiency Ratios & Pipes and Cisterns
Key Takeaways
- The LCM Method establishes Total Work as the Least Common Multiple of individual completion times, converting fractional rates into integer daily efficiency units.
- The Chain Rule equates productive capacity across varying manpower, durations, daily operating hours, and efficiency ratings: (M_1 * D_1 * H_1 * E_1) / W_1 = (M_2 * D_2 * H_2 * E_2) / W_2.
- Individual efficiency is inversely proportional to completion time: if worker A is 50% more efficient than worker B, the efficiency ratio is 3 : 2 and the time ratio is 2 : 3.
- In alternate-day scheduling, compute the work completed per complete multi-day cycle, determine total complete cycles, and allocate residual units sequentially to the scheduled starter.
- In pipes and cisterns systems, inlet conduits represent positive efficiency (+E) while drainage leaks represent negative efficiency (-E); net filling requires sum(E_inlets) > sum(E_leaks).
10.3 Time & Work, Efficiency Ratios & Pipes and Cisterns
Time and Work and its engineering counterpart, Pipes and Cisterns, form one of the highest-weightage arithmetic modules in the SBI Clerk Preliminary and Main examinations. Standard textbook approaches rely on fractions (assigning total work as 1 and tracking fractional daily outputs $\frac{1}{A} + \frac{1}{B}$), which inevitably creates tedious common-denominator arithmetic under exam pressure. The LCM Efficiency Method replaces fractional algebra with integer arithmetic, enabling candidates to solve multi-worker schedules, alternating work shifts, mid-way departures, and drainage leak problems rapidly.
1. The LCM Efficiency Method Foundations
Instead of defining total work as $1$, let:
LCM Efficiency Reference Architecture
Suppose Associate A completes an administrative audit in 12 days, Associate B completes it in 15 days, and Associate C completes it in 20 days.
- Compute $\text{LCM}(12, 15, 20) = 60\text{ units}$ (Total Work).
- Establish individual daily efficiencies:
- $E_A = \frac{60}{12} = +5\text{ units/day}$
- $E_B = \frac{60}{15} = +4\text{ units/day}$
- $E_C = \frac{60}{20} = +3\text{ units/day}$
- Combined daily efficiency ($E_{\text{total}}$) = $5 + 4 + 3 = 12\text{ units/day}$.
- Time taken working concurrently = $\frac{60}{12} = \mathbf{5\text{ days}}$.
| Associate | Individual Time ($T_i$) | Total Work (LCM) | Daily Efficiency ($E_i$) | Output Share in Combined Work |
|---|---|---|---|---|
| Associate A | 12 days | 60 units | $60 / 12 = \mathbf{5\text{ units/day}}$ | $5 / 12 = 41.67%$ |
| Associate B | 15 days | 60 units | $60 / 15 = \mathbf{4\text{ units/day}}$ | $4 / 12 = 33.33%$ |
| Associate C | 20 days | 60 units | $60 / 20 = \mathbf{3\text{ units/day}}$ | $3 / 12 = 25.00%$ |
| Combined (A+B+C) | — | 60 units | $\mathbf{12\text{ units/day}}$ | $12 / 12 = 100.0%$ |
2. The Chain Rule & Workforce Equivalence
When workforce sizes, daily working hours, and physical output requirements vary simultaneously, the Chain Rule provides a single unifying equation:
Where:
- $M = \text{Number of workers}$
- $D = \text{Number of working days}$
- $H = \text{Operating hours per day}$
- $E = \text{Efficiency rating per worker}$
- $W = \text{Quantity of work accomplished (pages verified, meters dug, loans processed)}$
Workforce Equivalence Mechanics (Men, Women, Children)
Examinations frequently feature composite teams (e.g., "6 men or 10 women can complete a task"). Convert heterogeneous worker groups into a single equivalent metric:
Assign integer efficiency ratings: each man possesses an efficiency of $E_M = 5$ units/day, while each woman possesses $E_W = 3$ units/day. Substitute these integer values directly into the Chain Rule.
3. Worker Departures and Arrivals Mid-Way
When team members join or leave mid-way through a project, two systematic techniques replace fractional timelines:
1. Direct Deduction Method (Worker Leaves After $k$ Days)
- Calculate work completed by the initial team during the first $k$ days: $W_{\text{done}} = (\sum E_{\text{initial}}) \times k$.
- Determine remaining work: $W_{\text{rem}} = W_{\text{total}} - W_{\text{done}}$.
- Compute remaining days: $T_{\text{rem}} = \frac{W_{\text{rem}}}{\sum E_{\text{remaining}}}$.
2. Virtual Work Addition Method (Worker Leaves $k$ Days Before Completion)
- When a question states that "Worker A leaves 3 days before the scheduled completion", do not work backwards with variable $T$.
- Shortcut: Force Worker A to stay! Add Worker A's phantom output for those 3 days to the Total Work:
- Divide $W_{\text{virtual}}$ by the combined efficiency of the entire team $(\sum E_{\text{all}})$. The result gives the total completion duration directly in a single step.
4. Alternate-Day Work Schedules
In alternating-day scenarios, workers operate in sequential rotation (e.g., Worker A works on Day 1, Worker B on Day 2, Worker A on Day 3, and so forth).
Step-by-Step Cycle Tracking Algorithm
- Define Cycle Length: For two alternating workers, 1 complete cycle $= 2\text{ days}$. For three workers, 1 complete cycle $= 3\text{ days}$.
- Compute Cycle Work: Sum the individual efficiencies across the full cycle: $W_{\text{cycle}} = E_A + E_B$.
- Compute Complete Cycles:
- Evaluate Cumulative Work & Time:
- Allocate Remaining Units to Sequential Starters:
Allocate $W_{\text{remainder}}$ to the worker whose turn opens the next cycle. If the remainder is less than that worker's daily output, the fractional time added is $\frac{W_{\text{remainder}}}{E_{\text{worker}}}$.
[!WARNING] The Overshoot Trap: Never divide total work directly by cycle work if a fractional remainder exists, because the work concludes the exact moment the cumulative threshold is reached. A worker does not complete a full extra day if only a small fraction of work remains.
5. Pipes & Cisterns: Negative Efficiency Dynamics
Pipes and cisterns problems operate under identical mathematical principles as human labor, with one fundamental physical distinction:
Worked Pipe and Structural Leak Problem
Problem: A main supply tap fills an overhead water tank at an SBI residential quarters in 8 hours. Due to an accidental leak in the base of the tank, it requires 10 hours to fill the tank completely. If the tank is completely full and the inlet tap is turned off, how long will the leak take to empty the entire tank?
- Establish Total Capacity: $\text{LCM}(8, 10) = 40\text{ units}$.
- Determine Inlet Efficiency ($E_{\text{inlet}}$):
- Determine Net Combined Efficiency ($E_{\text{net}}$):
- Isolate Leak Efficiency ($E_{\text{leak}}$):
- Calculate Emptying Time:
Associate A can complete a banking record digitisation assignment in 12 days, while Associate B can complete the exact same assignment in 18 days. If they work on alternate days with Associate A starting on the first day, in how many days will the entire assignment be completed?
Senior Associate A is 50% more efficient than Junior Associate B. If Junior Associate B alone can complete a branch compliance review in 30 days, in how many days can Senior Associate A and Junior Associate B complete the same compliance review working together?
Two inlet pipes P and Q can fill an overhead water cistern at an SBI residential township in 20 minutes and 30 minutes, respectively. An outlet drainage pipe R can empty the entire cistern in 15 minutes. If all three pipes are opened simultaneously when the cistern is completely empty, how long will it take to fill the cistern to capacity?