3.3 Monumentation, Tie Lines & Mapping Requirements (21 NCAC 56 .1602(d)-(h) & .1604)

Key Takeaways

  • 21 NCAC 56 .1602(d) requires metal stakes or materials of comparable permanence at all corners; the rule prescribes no minimum diameter, no minimum length, and no identification cap.
  • Where a corner falls in a right-of-way, tree, stream, or on a fence post, boulder, stone, or similar object, 21 NCAC 56 .1602(e) requires one or more monuments or metal stakes placed in the boundary so the inaccessible point can be located accurately on the ground and on the map.
  • Artificial monuments called for in a survey report must be described as found or set, and where no monument is found or set for a .1602(e) point that fact shall be noted.
  • 21 NCAC 56 .1602(g) requires a tie by azimuths or courses and distances to a horizontal control monument of a United States or State agency survey system where such a monument lies within 2,000 feet of the surveyed entity, with NAD 83 or NAD 27 identified.
  • 21 NCAC 56 .1602(h) requires area to be computed by double meridian distance or an equally accurate method; area by estimation, planimeter, scale, or copying from another source is not acceptable except for inaccessible areas, whose method of computation must be stated.
Last updated: August 2026

3.3 Monumentation, Tie Lines & Mapping Requirements (21 NCAC 56 .1602(d)-(h) & .1604)

This is the section where third-party prep material most often goes wrong, so start with what the rules do not say.

[!CAUTION] North Carolina publishes no monument dimensions. 21 NCAC 56 contains no half-inch minimum diameter, no 24-inch minimum length, no "#4 rebar" specification, and no requirement that a cap be stamped with the surveyor's or firm's license number. Charts asserting those figures are importing another state's standards. If an exam item offers a specific pipe diameter as "the North Carolina requirement," it is a distractor. The correct answer is the language the rule actually uses: metal stakes or materials of comparable permanence.

That does not make caps or #5 rebar bad practice — many North Carolina surveyors use both, and local subdivision ordinances frequently impose their own specifications. It means the state standard is a durability standard, not a dimensional one.


1. The Monument Rule (21 NCAC 56 .1602(d), (e), (f))

(d) All corners. "Except as provided in Paragraph (e) of the Rule, metal stakes or materials of comparable permanence shall be placed at all corners." Two words carry the load: metal stakes sets the presumptive material, and comparable permanence opens the door to concrete monuments, drill holes in rock, and similar durable markers.

(e) Inaccessible corners. "Where a corner falls in a right-of-way, tree, stream, or on a fence post, boulder, stone, or similar object, one or more monuments or metal stakes shall be placed in the boundary so that the inaccessible point may be located accurately on the ground and the map."

         PROPERTY CORNER FALLS IN A LIVE STREAM CHANNEL

         A ------------------- WC ~~~~~~~[X]~~~~~~~ WC ------------ B
                                 |        true        |
           set metal stake       |       corner       |    set metal stake
           IN THE BOUNDARY       |    (inaccessible)  |    IN THE BOUNDARY

         .1602(e): one or more monuments or metal stakes placed IN THE
         BOUNDARY so the inaccessible point can be located accurately on
         the ground AND on the map.
         .1602(f): if no monument is found or set for that point, NOTE IT.

Notice the geometry the rule specifies: the witness monuments go in the boundary, not merely somewhere nearby on convenient ground. The plat must then carry enough data — bearing and distance from each witness monument to the true corner — that a later surveyor can reproduce the corner position.

(f) Reporting. The results of a survey shall be reported to the user as a map or report of survey, in a clear and factual manner, and:

  • All reference sources shall be identified.
  • Artificial monuments called for shall be described as found or set.
  • When no monument is found or set for a point described under (e), that fact shall be noted.

"Found or set" is the phrase to burn in. A plat that shows an iron pipe without saying whether the surveyor recovered it or placed it destroys the evidentiary value of the very thing a retracing surveyor needs most.


2. Tie Lines (21 NCAC 56 .1602(g))

The tie-line rule is a Board Rule, separate from the plat-recording statute:

  • Where a survey is reported as a plat or written description, one or more corners shall be accurately tied, by a system of azimuths or courses and distances, to a horizontal control monument of some United States or State Agency survey system, such as the North Carolina Geodetic Survey, where such monument is within 2,000 feet of the subject property, right-of-way, easement, or other surveyed entity.
  • Where the North Carolina grid coordinates of that monument are on file with the Department of Public Safety, Emergency Management, Geodetic Survey office, the coordinates of both the referenced corner or point and the monument(s) shall be shown as X (easting) and Y (northing).
  • The coordinates shall be identified as based on "NAD 83" or "NAD 27." NGS datums are incorporated by reference, including subsequent amendments and editions.
  • Tie lines to monuments shall be sufficient to establish true north or grid north bearings for the plat or description if the monuments exist in pairs.
  • Control monuments within a previously recorded subdivision may be used in lieu of grid control, and in the interest of bearing consistency with previously recorded plats, existing bearing control may be used where practical.
  • In the absence of grid control, other natural or artificial monuments or landmarks shall be used. In all cases the tie lines must be sufficient to accurately reproduce the subject lands from the control or reference points used.

Section 4.4 covers how this interacts with the coordinate requirement in G.S. 47-30(f)(9), which the General Assembly rewrote in 2019 and which is not the same rule.


3. Area Computation (21 NCAC 56 .1602(h))

Area "is to be computed by double meridian distance or equally accurate method and shown on the face of the plat, written description, or other document." Area computations by estimation, by planimeter, by scale, or by copying from another source are not acceptable — "except in the case of tracts containing inaccessible areas and in these areas the method of computation shall be stated."

Coordinate-geometry area from a closed, adjusted traverse is an "equally accurate method." Lifting the acreage from the deed is copying from another source and is prohibited.


4. The Plat-Content Rule (21 NCAC 56 .1604)

Rule .1604 is titled "Mapping Requirements for Boundary Surveys" — it is not the monument rule. Paragraphs (a) through (c) set three general requirements, and paragraph (d) sets twelve mandatory elements for every plat unless marked "Preliminary Plat - Not for recordation, conveyances, or sales."

(a) Map size such that all details are legible on a copy. (b) Any lines not actually surveyed shall be indicated on the map with a statement revealing the source of the information from which the line is derived. (c) All surveys based on the North Carolina grid system shall contain a statement identifying the coordinate system referenced datum used.

(d) The twelve elements. Every non-preliminary plat shall be sealed, signed, and dated by the PLS and shall contain:

#Required element
1An accurately positioned north arrow coordinated with any bearings shown, indicating whether north is true, magnetic, NC grid (with NAD 83 and realization, or NAD 27), or referenced to old recorded deed or plat bearings — with date and source where magnetic or old-bearing referenced
2Azimuth or courses and distances of every property line surveyed, in feet or meters and decimals, with decimal places appropriate to the class of survey required by .1603
3All plat lines horizontal or grid measurements, correctly plotted to scale; where the NC grid system is used, the combined grid factor shall be shown on the face of the plat, and grid distances shall be identified if used
4For a curved boundary: actual survey data or a series of subchords with bearings and distances; if standard curve data is used, the bearing and distance of the long chord from PC to PT shall be shown
5For a subdivision: all streets and lots accurately plotted with dimension lines and everything needed to retrace the lines in the field, including bearings and distances forming a continuous closure of the entire perimeter
6Control corners and all other corners marked by monument or natural object identified, plus adjacent owners' corners along the boundary that are so marked
7One of: names of adjacent land owners; lot/block/parcel/subdivision designations; or other legal reference — or a note if it could not be determined
8All visible and apparent rights-of-way, easements, watercourses, utilities, roadways and similar improvements accurately located where crossing or forming a boundary
9Tie lines as required by .1602(g), shown on the face of the plat whether or not the plat is to be recorded
10A vicinity (location) map on the face of the plat
11Property designation; owner or prospective owner; location including township, county, and State; date(s) of survey; scale in words or figures; a bargraph; the title source; and a legend for unlabeled nomenclature or symbols
12For any map not certified for recording under G.S. 47-30, and for all reports of survey, the .1604(d)(12) certificate

The .1604(d)(12) certificate (non-recorded maps and all survey reports)

"I certify that this map was drawn under my supervision from an actual survey
made under my supervision (deed description recorded in Book ____, page ____ or
other reference source ____________); that the boundaries not surveyed are
indicated as drawn from information in Book ____, page ____ or other reference
source ____________; that the ratio of precision or positional accuracy is
____________; and that this map meets the requirements of The Standards of
Practice for Land Surveying in North Carolina (21 NCAC 56 .1600)."

This ____ day of ____________, 2____.

Seal                          ____________________________________
                              Professional Land Surveyor

Compare this with the G.S. 47-30(d) certificate used on recordable plats, which recites compliance "in accordance with G.S. 47-30 as amended" and requires the license number. Section 4.2 sets the two side by side. The practical rule: a map headed to the Register of Deeds carries the statutory certificate; an office map, exhibit, or written report of survey carries the .1604(d)(12) certificate.


5. Why Original Monuments Still Control

Nothing in Section .1600 disturbs the common-law hierarchy taught in Chapter 5. When an original, undisturbed monument called for in the deed is recovered, it marks the legal corner even where modern measurement shows the recited distance was off. The rules govern what the surveyor must place, report, and show; the priority of calls governs which evidence controls. A surveyor who sets a new pin "at the deed distance" and ignores a recovered original monument has satisfied .1602(d) and violated the boundary law that gives the corner its meaning.

Loading diagram...
Monumentation and Plat Content: Which Rule Governs What
Test Your Knowledge

What does 21 NCAC 56 .1602(d) require a North Carolina surveyor to place at newly established property corners?

A
B
C
D
Test Your Knowledge

A boundary corner falls inside a paved public right-of-way where a monument cannot be safely set. Under 21 NCAC 56 .1602(e) and (f), what must the surveyor do?

A
B
C
D
Test Your Knowledge

Under 21 NCAC 56 .1602(h), which method of determining the area of a surveyed tract is acceptable?

A
B
C
D
Test Your Knowledge

A surveyor prepares a written report of survey that will not be recorded. Which certificate applies?

A
B
C
D