9.1 Scope of Incidental Street & Storm Sewer Design (G.S. 89C-3(7) & the Board Guidelines)
Key Takeaways
- G.S. 89C-3(7)a.3. includes within the practice of land surveying "making any survey for the subdivision of any tract of land, including the topography, alignment and grades of streets and incidental drainage within the subdivision."
- G.S. 89C-3(7)b.(vi) bars a land surveyor from designing or preparing specifications for streets or storm sewer systems "except as incidental to a subdivision," and separately bars major highways, wastewater systems, wastewater or industrial waste treatment works, pumping or lift stations, and water supply, treatment, or distribution systems.
- The Board Guidelines state that what is incidental is initially determined by the designer in order to stay within that designer's expertise, and is then subject to the Board's determination of what is incidental or appertains solely to the public works needs of the proposed subdivision.
- North Carolina publishes no acreage cap on incidental drainage design; the eleven-item exclusion list, not a numeric threshold, is the governing test.
- The Guidelines expressly permit use of NCDOT standard sub-base, base, and paving surface designs from the Subdivision Roads Minimum Construction Standards where special structural design is not required, and permit design of geometric features common to subdivision streets and the use of stop or yield signs at intersections.
9.1 Scope of Incidental Street & Storm Sewer Design (G.S. 89C-3(7) & the Board Guidelines)
Drainage is 16 percent of the state-specific exam, and the Board's own description of the exam says it tests "what a PLS can do per G. S. 89C and the incidental drainage guidelines with respect to erosion control and surface drainage." The first thing to master is not hydrology — it is the boundary of your license.
1. The Statutory Exception
North Carolina builds the authority out of two halves of the same definition. The inclusion is G.S. 89C-3(7)a.3.:
The practice of land surveying includes "Making any survey for the subdivision of any tract of land, including the topography, alignment and grades of streets and incidental drainage within the subdivision, and the preparation and perpetuation of maps, record plats, field note records, and property descriptions that represent these surveys."
The exclusion is G.S. 89C-3(7)b., which provides that the term shall not be construed to permit the design or preparation of specifications for:
| Excluded work | |
|---|---|
| (i) | major highways |
| (ii) | wastewater systems |
| (iii) | wastewater or industrial waste treatment works |
| (iv) | pumping or lift stations |
| (v) | water supply, treatment, or distribution systems |
| (vi) | streets or storm sewer systems except as incidental to a subdivision |
Item (vi) is the hinge. Streets and storm sewers are engineering by default; they become surveying only in the narrow channel the statute cuts — incidental to a subdivision the surveyor is surveying. The Board's guideline opens by saying exactly that: "The law restricts design and preparation of the plans for the above to subdivisions only."
2. Who Decides What Is "Incidental"
The Guidelines answer this in one sentence worth quoting in full:
"Items which are 'incidental' to a subdivision are initially determined by the designer in order to stay within that designer's expertise, and the designer's decision is then subject to this Board's determination of what is 'incidental' or what 'appertains solely to the public works needs of the proposed subdivision.'"
That is a two-stage, competence-anchored test, and it lines up with 21 NCAC 56 .0701(c), which permits a licensee to undertake assignments only when qualified by education or experience in the specific technical field. The surveyor makes the first call against their own competence; the Board reviews it after the fact.
[!CAUTION] There is no acreage limit. North Carolina publishes no "200-acre," "100-acre," or any other numeric ceiling on incidental drainage design, and no such figure appears in G.S. 89C, in 21 NCAC 56, or in the Guidelines. Prep material that supplies one is inventing a bright line the Board deliberately declined to draw. The real test is the exclusion list below plus your own competence.
3. The Eleven Exclusions — Memorize These
The Guidelines state that items not permitted to be designed under the term "incidental streets and drainage" include but are not limited to the following:
1. Structural sub-base, base, paving surface of the streets, super elevation,
traffic control, etc., necessary for street design; hydraulics for drainage
systems, and hydrology for storm conditions; trench safety conditions; pipe
bedding, structure backfill, and all structural load conditions from traffic
on trenches, catch basins, manholes, grates and frames -- EXCEPT that level
of hydrology and hydraulics necessary in the performance of "incidental
drainage" may be performed within a subdivision.
a) Nothing prohibits use of the STANDARD sub-base, base and/or paving
surface designs provided by NCDOT in "Subdivision Roads Minimum
Construction Standards," where special structural design is not
required.
b) "Traffic control" does not prohibit the design of geometric features
common to subdivision streets, nor the use of stop or yield signs at
intersections.
2. Any street or drainage system which the surveyor is not TOTALLY COMPETENT
in all aspects of the design of the facilities.
3. Any streets or storm sewers SEPARATE from a subdivision design.
4. Any DAMS or RETAINING WALLS.
5. Any major drainage ditch, storm culvert, branch, deep structure, catch
basin, manhole, etc., requiring SPECIAL or STRUCTURAL design.
6. Any design of major drainageways or storm sewers carrying storm sewer
THROUGH the subdivision to drain a LARGE DRAINAGE BASIN (major drainage
canal, creek, river, large conduit system, etc.).
7. Any special design or selection of conduits for HIGHWAY LOADS, other than
residential streets, or deep sewers requiring special conduit selection due
to drainage loading.
8. Any drainage system for the purpose or facilitation of SEWAGE DISPOSAL.
9. Any storm sewer carrying more than a SMALL REASONABLE AMOUNT of storm water
from lands ADJACENT to the subdivision being designed.
10. Streets designated as THOROUGHFARES or COLLECTOR STREETS in an adopted
thoroughfare plan.
11. Any SURCHARGED storm sewers or PUMPING STATIONS.
(As Revised and Adopted June 8, 1989; Issued June
19, 1989; Names Edited November 1, 2004; Reviewed
September 20, 2012)
Reading item 1 correctly
Item 1 looks, on a fast read, as though it forbids hydrology and hydraulics outright — and then the same sentence gives it back: "except, that level of hydrology and hydraulics necessary in the performance of 'incidental drainage' may be performed within a subdivision." What item 1 actually excludes is the structural side of street and drainage construction: pavement structural design, superelevation, trench safety, pipe bedding, backfill, and traffic loading on structures. The hydrologic and hydraulic computations taught in Sections 9.2 and 9.3 sit inside the exception.
Sub-item (a) is a practical gift: a surveyor may use NCDOT's standard sub-base, base, and paving designs from the Subdivision Roads Minimum Construction Standards where no special structural design is required. Sub-item (b) confirms that "traffic control" does not sweep in the ordinary geometry of a subdivision street or the placement of stop and yield signs.
The four recurring themes
| Theme | Exclusions that express it |
|---|---|
| Structural design belongs to a PE | 1, 4, 5, 7 |
| It must be inside a subdivision | 3, 6, 9, 10 |
| Scale and complexity have limits | 5, 6, 9, 11 |
| Competence is a hard gate | 2 |
Exclusion 2 deserves separate attention because it is unbounded: "Any street or drainage system which the surveyor is not totally competent in all aspects of the design of the facilities." A surveyor cannot satisfy the other ten and still proceed if they cannot competently design every aspect. On an exam item that describes a technically permissible design the surveyor has never attempted, exclusion 2 is the answer.
4. Worked Scope Judgments
| Scenario | Permitted? | Why |
|---|---|---|
| Roadside swales and driveway cross-pipes for a 30-lot residential subdivision the surveyor platted | Yes | Incidental drainage within a subdivision; ordinary geometry; no special structural design |
| Gravity storm sewer collecting only the subdivision's own runoff, using standard RCP and standard NCDOT details | Yes | Within the exception; standard designs expressly permitted by sub-item (a) |
| Stop signs and street geometry at internal intersections | Yes | Sub-item (b) |
| A trunk storm sewer routed through the subdivision to drain a 400-acre upstream basin | No | Exclusion 6 — major drainageway draining a large basin |
| A 12-foot retaining wall supporting the subdivision entrance road | No | Exclusion 4 — retaining walls |
| Widening a state-designated collector street abutting the subdivision | No | Exclusion 10 — thoroughfares and collectors |
| A detention outlet requiring a pump | No | Exclusion 11 — pumping stations |
| Storm drainage for a standalone commercial site with no subdivision | No | Exclusion 3, and G.S. 89C-3(7)b.(vi) — not incidental to a subdivision |
| A culvert requiring a special structural design for highway loading on a state route | No | Exclusions 5 and 7 |
| A drainage system installed to make a septic field work | No | Exclusion 8 — drainage facilitating sewage disposal |
5. Consequences of Overstepping
Designing outside the incidental exception is the unlicensed practice of engineering. The exposure is layered:
- G.S. 89C-23 makes practicing or offering to practice engineering without licensure a Class 2 misdemeanor.
- G.S. 89C-10(c) lets the Board obtain an injunction in the name of the State, without bond, without alleging irreparable damage or the absence of an adequate remedy at law.
- G.S. 89C-21(a)(2) and (a)(4) expose the surveyor's own license to reprimand, suspension, refusal to renew or reinstate, revocation, additional education, or required re-examination, with a civil penalty of up to $2,000 for a land surveyor under G.S. 89C-21(c).
- 21 NCAC 56 .0701(c) independently prohibits accepting an assignment outside one's competence.
The Board's structure reinforces the point: NCBELS licenses both professions, so a surveyor's overreach into engineering is adjudicated by the same body, in front of engineer members, using the same rules.
Which statutory provision supplies a North Carolina land surveyor's authority to design drainage within a subdivision?
A surveyor platting a 60-lot subdivision is asked to design a storm sewer trunk line that will be routed through the subdivision to convey runoff from a 400-acre upstream watershed to a creek. Is this within the incidental exception?
Under sub-item (a) of the first exclusion in the Board Guidelines, what may a surveyor do with respect to street pavement design?
A surveyor determines that a proposed subdivision storm drainage system is not on any of the eleven exclusions, but has never designed a system with this configuration and is unsure how to size several of its components. What does the guidance require?