1 / 100
Question 1
Score: 0/0

The Agilometer shows that the project scores LOW on 'flexibility on what is delivered' and LOW on 'acceptance of agile'. What does this combination MOST likely indicate?

A
B
C
D
to track
2026 Statistics

Key Facts: PRINCE2 Agile Practitioner Exam

100

Free Practice Questions

OpenExamPrep PRINCE2 Agile Practitioner bank

60%

Passing Score

PeopleCert/AXELOS

150 min

Time Limit

PeopleCert

Open Book

Exam Format

Official PRINCE2 Agile guide only

3 years

Certification Validity

Renewal required every 3 years

2026

Content Refresh

Current syllabus prep

PRINCE2 Agile Practitioner is a 150-minute, 50-question open-book exam (official PRINCE2 Agile guide only) requiring 60% to pass (30/50). It is scenario-based: questions relate to a case study. Key topics are fixing and flexing the six project aspects (time, cost, quality fixed; scope flexed), the five targets (be on time, protect quality, embrace change, keep teams stable, customer doesn't need everything), the five behaviours (transparency, collaboration, rich communication, self-organisation, exploration), the Agilometer (six sliders), and tailoring all seven PRINCE2 themes and processes for agile. Prerequisites: PRINCE2 Agile Foundation or approved equivalent.

Sample PRINCE2 Agile Practitioner Practice Questions

Try these sample questions to test your PRINCE2 Agile Practitioner exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1A project manager is initiating a software delivery project. The project board wants governance while the delivery teams prefer Scrum. Which statement BEST describes how PRINCE2 Agile achieves this balance?
A.PRINCE2 Agile replaces PRINCE2 processes with Scrum ceremonies at all levels of the project
B.PRINCE2 Agile uses PRINCE2 for project direction and management while agile techniques operate within the delivery stages
C.PRINCE2 Agile eliminates the need for stages by converting them into sprints across the whole project
D.PRINCE2 Agile requires the project board to attend all sprint reviews as the only governance mechanism
Explanation: PRINCE2 Agile keeps PRINCE2's governance structure (project board, stages, directing, controlling) intact at the management layers while allowing agile delivery techniques (Scrum, Kanban) to operate within each stage. The project board governs via exception and stage boundaries; delivery teams self-organise within those boundaries. This is the fundamental 'blend' that distinguishes PRINCE2 Agile from pure Scrum.
2During a project's Controlling a Stage process, the team is using Kanban. The project manager notices that the team's WIP limit is being consistently breached. According to PRINCE2 Agile, what is the MOST appropriate immediate action?
A.Raise an exception report to the project board immediately
B.Remove the WIP limit so the team can work freely
C.Investigate with the team to understand the cause and whether flow needs rebalancing
D.Add more team members to increase throughput across all columns
Explanation: A persistently breached WIP limit is a signal that flow is impeded — not an automatic exception. PRINCE2 Agile calls for the project manager to work collaboratively with the team (Behaviour: Collaboration) to understand whether the constraint is skill-based, dependency-based, or a systemic blocker. Only if it threatens stage tolerances would an exception report be needed. Removing WIP limits defeats the purpose of Kanban.
3The Agilometer shows that the project scores LOW on 'flexibility on what is delivered' and LOW on 'acceptance of agile'. What does this combination MOST likely indicate?
A.Agile is an ideal fit and the project should proceed with full Scrum
B.The project faces significant risk in using agile and the project manager should consider risk responses
C.The project should immediately switch to a waterfall approach
D.The project board should be dissolved to allow the team to self-organise
Explanation: Low Agilometer scores on 'flexibility on what is delivered' and 'acceptance of agile' indicate that the environment is resistant to agile working. The Agilometer is a risk assessment tool — low scores flag where risk responses are needed (e.g., additional governance, stakeholder engagement, or phased agile adoption) rather than directing an outright rejection of agile or a full switch to waterfall.
4A project is using the hexagon to set tolerances. The customer has a fixed go-live date and fixed budget. According to PRINCE2 Agile's fix and flex approach, which tolerance should be FLEXED to protect the deadline?
A.Time
B.Cost
C.Scope
D.Quality
Explanation: In PRINCE2 Agile's hexagon, time and cost are typically fixed (the deadline and budget cannot move). When these are fixed, scope is the primary tolerance to flex — the team delivers the most valuable features first, and lower-priority scope is deferred or dropped if necessary to hit the deadline. Quality is also protected (it should not be sacrificed) and is therefore generally fixed.
5During Managing Product Delivery, a Scrum team completes a sprint but the product owner has not accepted two user stories due to failing acceptance criteria. According to PRINCE2 Agile, what should happen NEXT?
A.The project manager raises a change request and escalates to the project board
B.The team marks the stories done and moves them to the next sprint without changes
C.The incomplete stories are renegotiated with the product owner, re-prioritised in the backlog, and worked on in the next iteration
D.The Definition of Done is relaxed so the stories can be accepted as partially complete
Explanation: PRINCE2 Agile's Managing Product Delivery process expects that unaccepted work is re-prioritised in the backlog rather than carried as false 'done' items. The product owner renegotiates acceptance criteria if needed, reprioritises the stories, and the team addresses them in the next timebox. This maintains integrity of the Definition of Done while keeping the backlog honest and transparent.
6A project scenario shows the team is dispersed across three continents and cannot meet face-to-face. Which PRINCE2 Agile behaviour is MOST important to consciously embed in this context?
A.Exploration
B.Rich communication
C.Self-organisation
D.Transparency
Explanation: Rich communication is the PRINCE2 Agile behaviour that encompasses face-to-face interaction, use of visual models, workshops, and collaboration tools. When a team cannot meet in person, deliberate effort must be made to replicate richness through video calls, digital whiteboards, and regular structured communication. This behaviour is most directly threatened by geographical dispersion.
7The project scenario involves delivering an entirely novel digital product where requirements are highly uncertain and cause-and-effect relationships are only understood in hindsight. Which Cynefin domain does this represent and what delivery approach does PRINCE2 Agile recommend?
A.Simple domain — use best practice and plan all requirements upfront
B.Complicated domain — analyse the problem fully before starting delivery
C.Complex domain — probe-sense-respond using iterative and incremental delivery
D.Chaotic domain — act immediately then assess outcomes
Explanation: When cause and effect are only understood in retrospect and requirements are unknown, the work sits in the Complex Cynefin domain. PRINCE2 Agile recommends probe-sense-respond: small experiments (spikes, prototypes, MVPs) to generate learning, with iterative delivery to continuously sense results and adapt. This is where agile is most naturally suited.
8A project manager is tailoring the Business Case theme for an agile project. Which approach BEST reflects PRINCE2 Agile guidance?
A.The business case is fixed at project initiation and reviewed only at project closure
B.The business case is replaced entirely by a product vision and customer value statement
C.The business case is kept live throughout the project, with benefits reviewed at each stage boundary as scope and value evolve
D.The business case is owned exclusively by the product owner and updated in each sprint
Explanation: In PRINCE2 Agile, the Business Case remains a live document owned by the Executive and reviewed at each stage boundary. Because scope is flexed in agile delivery, the expected benefits may shift as the product evolves. Keeping the Business Case live ensures the project continues to justify itself and that the most valuable scope is delivered first. It is not replaced by a product vision.
9A project is in its second stage and the team is using Scrum. The stage plan shows 4 sprints. After sprint 2, the burn-up chart indicates the team will complete only 70% of planned stories by stage end. What is the MOST appropriate PRINCE2 Agile action?
A.Extend the stage by two additional sprints to complete all stories
B.Reprioritise the backlog so the highest-value stories are completed first; drop or defer lower-priority stories
C.Add three more developers immediately to accelerate delivery
D.Issue a concession to the project board accepting 70% as the final delivery
Explanation: PRINCE2 Agile's fix-and-flex approach means scope is the primary tolerance to flex when time is fixed. The project manager and product owner reprioritise the backlog — ensuring the most valuable stories are delivered in the remaining sprints and lower-priority work is deferred. This preserves the stage end date (time is fixed) while maximising value. A concession would only be raised if the outcome threatened the business case.
10The PRINCE2 Agile Practitioner exam is open book. Which material is the ONLY permitted reference during the exam?
A.Any printed notes the candidate has prepared
B.The official PRINCE2 Agile guide
C.The PRINCE2 Foundation manual
D.Any agile framework reference card
Explanation: The PRINCE2 Agile Practitioner examination is open book, but only the official PRINCE2 Agile guide is permitted. No other materials — personal notes, the PRINCE2 Foundation manual, or third-party references — are allowed. Candidates should be familiar enough with the guide's structure to locate answers quickly during the exam.

About the PRINCE2 Agile Practitioner Exam

PRINCE2 Agile Practitioner from PeopleCert (AXELOS) tests the ability to apply and tailor PRINCE2 governance with agile delivery techniques in project scenarios. The exam is open-book (official PRINCE2 Agile guide only), scenario-based, 150 minutes, and 50 multiple-choice questions requiring 60% (30/50) to pass. It covers fix and flex (the hexagon, six aspects, five targets), the five focus areas (Agilometer, requirements, rich communication, frequent releases, contracts), the five behaviours, and tailoring all PRINCE2 themes and processes for agile.

Questions

50 scored questions

Time Limit

150 minutes

Passing Score

60% (30/50)

Exam Fee

~£701 / ~$875 (PeopleCert (AXELOS))

PRINCE2 Agile Practitioner Exam Content Outline

6%

Agile Concepts and Context

Agile ways of working; PRINCE2 and agile complementarity; Cynefin domains; Scrum, Kanban, Lean Startup

24%

Five Focus Areas

Agilometer (6 sliders), requirements and user stories, rich communication, frequent releases, contracts and agile-friendly contracting

16%

Fix and Flex (Hexagon)

The hexagon's six aspects of project performance; the five targets; when and how to fix or flex tolerances in an agile context

48%

Tailoring PRINCE2 for Agile

Applying and tailoring all seven PRINCE2 principles, themes (business case, organisation, plans, quality, risk, change, progress), and processes (SU, IP, DP, CS, MP, SB, CP) to agile project scenarios; management products

How to Pass the PRINCE2 Agile Practitioner Exam

What You Need to Know

  • Passing score: 60% (30/50)
  • Exam length: 50 questions
  • Time limit: 150 minutes
  • Exam fee: ~£701 / ~$875

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

PRINCE2 Agile Practitioner Study Tips from Top Performers

1Read the scenario and additional information carefully before answering — all questions are set in context, and the 'right' answer depends on the scenario details
2Memorise the hexagon defaults: TIME fixed, COST fixed, QUALITY fixed, SCOPE flexed — and know when and why this changes
3Know all five PRINCE2 Agile focus areas by name: Agilometer, Requirements (user stories), Rich Communication, Frequent Releases, Contracts
4Understand how PRINCE2 roles (project board, PM, team manager) map to agile roles (Product Owner, Scrum Master) — they coexist, not replace
5For process tailoring questions: know what the project manager does vs the project board vs the delivery team at each process
6Practice reading the official PRINCE2 Agile guide efficiently — know the chapter structure so you can locate answers in the 150-minute window

Frequently Asked Questions

What is the PRINCE2 Agile Practitioner passing score?

The PRINCE2 Agile Practitioner exam requires 60% to pass — at least 30 correct answers out of 50 scenario-based questions. The exam is 150 minutes (2.5 hours), open-book (official PRINCE2 Agile guide only), delivered by PeopleCert at test centres or via online proctoring.

What is the difference between PRINCE2 Agile Foundation and Practitioner?

Foundation tests recall and understanding of PRINCE2 Agile concepts (closed-book, 60 min, 50 questions, 55%). Practitioner tests the ability to apply and tailor PRINCE2 Agile to project scenarios (open-book, 150 min, 50 scenario-based questions, 60%). Practitioner requires Foundation or an approved equivalent as a prerequisite.

Is the PRINCE2 Agile Practitioner exam open book?

Yes. The PRINCE2 Agile Practitioner exam is open book, but ONLY the official PRINCE2 Agile guide is permitted. Personal notes, the PRINCE2 Foundation manual, and other materials are not allowed. Candidates should know the guide's structure well enough to locate answers quickly under time pressure.

How long is PRINCE2 Agile Practitioner certification valid?

PRINCE2 Agile Practitioner certification is valid for 3 years. Renewal is required via the PeopleCert re-registration exam (30 questions, 1 hour, 55%) or Continuing Professional Development (CPD) activities through PeopleCert membership. Foundation certification does not expire.

What are the prerequisites for PRINCE2 Agile Practitioner?

You must hold PRINCE2 Agile Foundation, PRINCE2 Foundation, PRINCE2 Practitioner, PMP, CAPM, or an approved equivalent qualification. No mandatory work experience is required, but accredited training is strongly recommended.

How is the PRINCE2 Agile Practitioner exam structured?

The exam contains 50 multiple-choice questions in 5 sets, each related to a case study scenario. Each set tests a different learning outcome (agile concepts, focus areas, fix/flex, PRINCE2 tailoring). Questions use the scenario booklet and, for most sections, a set of additional project documents.