Cheat sheet

PRINCE2 Foundation Cheat Sheet

Key Concepts

3%of exam

Principles

8%of exam

Seven PrinciplesPrinciple PickerTailoringJustification

People

14%of exam

Practices

60%of exam

Processes

15%of exam

Quick Facts

Exam
PRINCE2 7 Foundation
Body
PeopleCert AXELOS
Questions
60
Time
60 min
Pass
60% 36/60
Book
Closed book
Prereqs
None
Style
Standard list missing negative

Domain Weights

Concepts 3 | Principles 8 | People 14

Practices 60Processes 15Practices dominate

Principles vs Practices

Principles

  • Always required
  • Universal rules
  • Seven obligations

Practices

  • Management controls
  • Tailored use
  • Seven areas

Musts vs controls

Project Basics

Project
Temporary change organization
BAU
Ongoing operations
Product
Project output
Outcome
Change from outputs
Benefit
Measurable improvement
Dis-benefit
Expected negative outcome

Output vs Outcome

Output

  • Specialist product
  • Project delivers
  • Tangible result

Outcome

  • Operational change
  • Users realize
  • Enables benefit

Thing vs change

Performance Aspects

Time
Delivery schedule
Cost
Approved budget
Quality
Fitness criteria
Scope
Products included
Benefits
Expected value
Risk
Uncertain effect
Sustainability
Environmental impact

Integrated Elements

Principles
Universal obligations
People
Project relationships
Practices
Management controls
Processes
Project lifecycle
Context
Tailoring driver
Tailoring
Fit method

Principles Line

Justify Learn Roles Stages Exception Products Tailor

Business reasonLessons usedTolerances matterOutputs first

Principle Picker

  1. Reason questionedJustification
  2. Past insightLearn
  3. Who decidesRoles
  4. Boundary reviewStages
  5. Forecast breachException
  6. Unclear deliverableProducts
  7. Small projectTailor

Seven Principles

Justification
Business reason continues
Learn
Use lessons
Roles
Clear accountability
Stages
Control by chunks
Exception
Escalate tolerance breach
Products
Define outputs first
Tailor
Adapt to context

Board Interests

Executive business | User benefits | Supplier delivery

ValueNeedsCapabilityDirection

Executive vs Project Manager

Executive

  • Business case
  • Board decisions
  • Owns value

Project Manager

  • Daily control
  • Stage delivery
  • Escalates exceptions

Direction vs management

Role Picker

  1. Business valueExecutive
  2. User acceptanceSenior User
  3. Specialist capabilitySenior Supplier
  4. Daily controlProject Manager
  5. Work package deliveryTeam Manager
  6. Delegated changeChange Authority

Roles

Executive
Owns business case
Senior User
Owns user needs
Senior Supplier
Owns supplier capability
Project Manager
Runs daily project
Team Manager
Delivers work packages
Project Assurance
Checks board interests
Project Support
Administers controls
Change Authority
Approves delegated changes

Stakeholder Interests

Business
Value for money
User
Needs and benefits
Supplier
Feasible delivery
Project Board
Direction decisions
Stakeholder
Affected party
Communication
Engagement control

Practices Line

Case Org Plans Quality Risk Issues Progress

WhyWhoHowControl

Risk vs Issue

Risk

  • May happen
  • Uncertain
  • Plan response

Issue

  • Happened now
  • Current concern
  • Control change

Future vs current

Practice Picker

  1. Why continueBusiness Case
  2. Who accountableOrganizing
  3. Acceptance criteriaQuality
  4. How deliverPlans
  5. UncertaintyRisk
  6. Change requestIssues
  7. Tolerance forecastProgress

Business Case

Purpose
Why project
Desirable
Worth doing
Viable
Investment sound
Achievable
Can deliver
Benefits plan
Realization approach
Executive
Accountable owner

Exception vs Issue

Exception

  • Tolerance breach
  • Escalate upward
  • Plan recovery

Issue

  • Event concern
  • Assess impact
  • May stay local

Limit vs concern

Organizing

Organization
Who does what
Accountability
Single answerability
Delegation
Authority passed down
Assurance
Independent checking
Support
Administrative help
Communication
Information flow

Checkpoint vs Highlight

Checkpoint

  • Team to PM
  • Work package
  • Frequent status

Highlight

  • PM to Board
  • Stage status
  • Exception warning

Team vs board

Quality Plans

Quality
Product fitness
Criteria
Acceptance measures
Tolerance
Allowed variation
Plan
How and when
Product Description
Product definition
Quality Register
Quality activity record

Risk Issues

Risk
Uncertain event
Threat
Negative risk
Opportunity
Positive risk
Issue
Current concern
Request
Proposed change
Off-spec
Requirement gap
Problem
Other concern
Issue Register
Issue record

Progress Controls

Progress
Actual versus plan
Tolerance
Delegated limits
Exception
Forecast breach
Checkpoint
Team progress report
Highlight
Board progress report
End Stage
Boundary review
Exception Plan
Recovery plan

Process Flow

SU DP IP CS MP SB CP

StartDirectInitiateClose

SU vs IP

SU

  • Is it worthwhile
  • Project Brief
  • Before initiation

IP

  • How govern
  • PID baseline
  • Initiation stage

Check vs define

Process Picker

  1. Viable ideaSU
  2. Board decisionDP
  3. Baseline projectIP
  4. Manage stageCS
  5. Accept packageMP
  6. Next stageSB
  7. Finish projectCP

Seven Processes

SU
Starting up
DP
Directing project
IP
Initiating project
CS
Controlling stage
MP
Managing delivery
SB
Managing boundaries
CP
Closing project

Management Products

Project Brief
Pre-initiation outline
PID
Project definition baseline
Business Case
Justification record
Stage Plan
Next-stage plan
Work Package
Team agreement
Project Log
Captured records
Lessons Report
Reusable learning

Common Traps

Principle trap

Tailored application Principles still mandatory

Tolerance trap

Within tolerance: continue Forecast breach: escalate

Business case trap

Executive owns PM maintains

Risk timing

Risk may happen Issue happened now

Product focus

Define products first Then plan activities

SU versus IP

SU checks viability IP creates PID

Board reports

Highlight to board Checkpoint to PM

Dis-benefit trap

Expected negative Not uncertain risk

Last Minute

  1. 1.Weights: 3/8/14/60/15
  2. 2.Practices are 60%
  3. 3.Pass = 36/60
  4. 4.Closed book, 60 minutes
  5. 5.Principles always apply
  6. 6.Tailor to context
  7. 7.Executive owns business case
  8. 8.Board directs; PM manages
  9. 9.Risk future; issue current
  10. 10.Tolerance breach escalates
  11. 11.Products before activities
  12. 12.SU checks; IP defines
Same family resources

Explore More PRINCE2 Certifications

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.