Cheat sheet

PRINCE2 7 Foundation Cheat Sheet

Quick Facts

Exam
PRINCE2 7 Foundation
Body
PeopleCert (AXELOS)
Questions
60 multiple choice
Time
60 minutes
Pass
36/60 = 60%
Marking
1 mark; no negatives
Book
Closed book
Question styles
Standard, missing word, list
Bloom levels
1 and 2
Extra time
75 min if non-native
Prerequisite
None
Renewal
3 years; CPD or retake
Version
PRINCE2 7 (2023)

Performance Aspects

Benefits Cost Time Quality Scope Sustainability Risk

Sustainability is newVersion 6 had sixEach aspect carries toleranceTolerances enable exception management

Practice vs Process

Practice

  • Ongoing throughout project
  • Seven, renamed from themes
  • Business case, risk, progress

Process

  • Step-by-step activities
  • Seven, in time order
  • Starting up, initiating, closing

Continuous versus sequential

Exam Mechanics

Standard question
Four options, one correct
Missing word
Choose word completing sentence
List question
Pick two correct statements
Negative question
Used only exceptionally
Bloom level 1
Recall facts
Bloom level 2
Show understanding
Marks needed
36 of 6060%

Five Integrated Elements

Principles
Seven guiding obligations
People
New fifth elementv7
Practices
Renamed from themesv7
Processes
Seven step-by-step stages
Project context
Where PRINCE2 is applied
Version 6 count
Four elements, no people

Seven Performance Aspects

Benefits
Measurable improvement from outcome
Cost
Permitted overspend or underspend
Time
Permitted early or late
Quality
Variation from acceptance criteria
Scope
Products in or out
Sustainability
Environmental, social, economic impactNEW
Risk
Threat and opportunity exposure

Delivery Approaches + Definitions

Linear-sequential
Plan fully, then build
Iterative-incremental
Repeated cycles add features
Hybrid
Mixes both approaches
Project
Temporary, creates business change
Project management
Plan, delegate, monitor, control
Management product
Used to run project
Specialist product
What the project delivers

Seven Principles

Business Lessons Roles Stages Exception Products Tailor

Business: continued justificationLessons: learn from experienceRoles: and relationshipsStages: manage by stagesException: tolerance breaches onlyProducts: focus on productsTailor: to the project

Seven Principles

Ensure continued business justification
Desirable, viable, achievable throughout
Learn from experience
Lessons sought, recorded, applied
Define roles, responsibilities and relationships
Relationships added in v7v7
Manage by stages
Authorize one stage ahead
Manage by exception
Escalate only tolerance breaches
Focus on products
Agree product descriptions first
Tailor to suit the project
Adapt to project context

Tailoring Rules

Can tailor
Processes, terminology, products, roles
Cannot tailor
The seven principles
Recorded in
PID tailoring section
Recommends tailoring
Project manager
Approves tailoring
Project board
Drivers
Size, complexity, importance, environment

Change Management vs Change Control

Change management

  • People element
  • Adoption of outputs
  • Change management approach

Change control

  • Issues practice
  • Protects the baseline
  • Issue management approach

People adopt versus baselines protected

People Element Concepts

Organizational ecosystem
Wider organization around project
Project ecosystem
People delivering the project
Change management
Moving people to target
Stakeholder
Affects or is affected
Culture
Shared values and behaviours
Collaboration
Working together toward objectives
Co-creation
Stakeholders build solution together
Leadership
Influence, motivate, set direction
Management
Plan, delegate, monitor, control

People Management Products

Change management approach
How adoption is achieved
Communication management approach
Means and frequency defined
Both stored in
The PID
Effective team
Capability, diversity, cultural intelligence
Stakeholder engagement
Planned two-way communication

Seven Practices

Big Old Projects Quickly Reveal Interesting Progress

B: business caseO: organizingP: plansQ: qualityR: riskI: issuesP: progress

Project Brief vs PID

Project brief

  • Created in starting up
  • Outline business case
  • Not a baseline

PID

  • Assembled in initiating
  • Full business case
  • Baseline for the project

Proposal versus baseline

Which Practice Applies?

  1. Is it still worthwhileBusiness case(Desirable, viable, achievable)
  2. Who is accountableOrganizing(Roles and interests)
  3. What, when, how muchPlans(Product-based planning)
  4. Will product be acceptableQuality(Acceptance criteria)
  5. Uncertain future eventRisk(Threat or opportunity)
  6. Something has already happenedIssues(Change control included)
  7. Are we on trackProgress(Tolerance and exception)
  8. People must adopt changePeople element(Not a practice)

Seven Practices

Business case
Judge desirable, viable, achievable
Organizing
Accountability, roles, relationships
Plans
What, who, how, when
Quality
Meet the user requirements
Risk
Manage threats and opportunities
Issues
Assess issues, control changes
Progress
Monitor, forecast, control deviation

Project Log Records

Daily Lessons, Issue Risk Quality Product

Two logs: daily, lessonsFour registers: issue, riskPlus quality and productSix records in total

Issue vs Exception

Issue

  • Something has happened
  • Logged in issue register
  • May need no change

Exception

  • Tolerance forecast to breach
  • Triggers exception report
  • Escalated one level up

Event versus tolerance breach

Which Management Product?

  1. Pre-initiation summaryProject brief(Outline business case)
  2. Baseline after initiationPID(Approved by board)
  3. Regular team updateCheckpoint report(Time-driven)
  4. Board progress updateHighlight report(Time-driven)
  5. Tolerance forecast breachException report(Event-driven)
  6. Informal noteDaily log(Project manager)
  7. Formal change requestIssue register(Plus issue report)
  8. Quality event scheduledQuality register(Inside project log)

PID Management Approaches

Benefits management
How benefits are measured
Sustainability management
How sustainability targets met
Commercial management
Supplier and contract handling
Quality management
Standards, tools, responsibilities
Risk management
How risk is handled
Issue management
How issues, changes handled
Change management
How people adopt outputs
Communication management
Means and frequency
Digital and data management
Data, tools, security rulesv7

Risk Technique

Identify Assess Plan Implement Communicate

Identify: threats, opportunitiesAssess: probability, impactPlan: response typesImplement: owners, actionsCommunicate: runs throughout

Risk Appetite vs Tolerance

Risk appetite

  • Willingness to take risk
  • Set by the business
  • Qualitative attitude

Risk tolerance

  • Measurable threshold
  • Triggers escalation
  • Set per performance aspect

Attitude versus measurable limit

Who Decides?

  1. Within work package toleranceTeam manager(No escalation)
  2. Within stage toleranceProject manager(Corrective action)
  3. Stage tolerance forecast breachedProject board(Exception report)
  4. Project tolerance breachedBusiness layer(Beyond board authority)
  5. Request for changeChange authority(Board may delegate)
  6. Business case no longer viableProject board(May close early)

Project Log Records

Project log
Single repository for recordsv7
Daily log
Informal notes and actions
Lessons log
Lessons captured and applied
Issue register
Formally managed issues
Risk register
Identified threats and opportunities
Quality register
Planned and actual quality
Product register
Product status and versionsv7

Issue Technique

Capture Assess Recommend Decide Implement

Capture: type and severityAssess: impact on objectivesRecommend: options and actionsDecide: authority approvesImplement: and update register

Work Package vs Stage Plan

Work package

  • Agreed with team manager
  • Covers specific products
  • Carries its own tolerances

Stage plan

  • Approved by project board
  • Covers the whole stage
  • Baseline for project manager

Delegated work versus stage baseline

Reports: Who Writes Them

Checkpoint report
Team manager to project manager
Highlight report
Project manager to board
End stage report
Project manager at boundary
End project report
Project manager at closure
Exception report
Project manager forecasts breach
Lessons report
Shares lessons with organization
Issue report
Describes a formal issue

Output vs Outcome vs Benefit

Output

  • The deliverable itself
  • Built by the project
  • Handed over at closure

Outcome

  • Result of using output
  • Changed way of working
  • Leads to a benefit

Benefit is measurable improvement

Roles + Three Interests

Executive
Business interest; owns business case
Senior user
User interest; owns benefits
Senior supplier
Supplier interest; provides resources
Project board
Executive, senior user, supplier
Project manager
Daily management; one person
Team manager
Delivers agreed work packages
Project assurance
Independent check for board
Project support
Administration, tools, records
Change authority
Decides requests for change

Quality Assurance vs Control

Quality assurance

  • Independent of the project
  • Checks the process
  • Organizational responsibility

Quality control

  • Inside the project
  • Checks the products
  • Tests, reviews, inspections

Process versus product

Four Organizational Levels

Business layer
Commissions project; sets tolerances
Directing
Project board authorizes stages
Managing
Project manager runs stage
Delivering
Team manager builds products
Mandate comes from
Business layer
Appoints the executive
Business layer

Project Assurance vs Support

Project assurance

  • Independent of project manager
  • Project board accountable
  • Business, user, supplier views

Project support

  • Serves the project manager
  • Administration and tools
  • Optional role

Independent check versus administration

Plans + Planning Technique

Project plan
Board baseline for project
Stage plan
Detailed plan per stage
Team plan
Optional, for work packages
Exception plan
Replaces plan after breach
Planning horizon
How far detail is realistic
Project product description
Defines what project delivers
Product breakdown structure
Hierarchy of required products
Product flow diagram
Sequence and dependencies
Work package description
Agreed work for team
Minimum stages
Initiation plus one delivery

Event-driven vs Time-driven

Event-driven

  • Triggered by an occurrence
  • Stage end or exception
  • End stage report

Time-driven

  • At set intervals
  • Weekly or monthly
  • Checkpoint and highlight reports

Trigger versus timetable

Quality Terms

User quality expectations
What the user expects
Acceptance criteria
Prioritized measurable acceptance list
Quality specifications
Measurable detail per product
Quality planning
Define criteria and methods
Quality control
Test, inspect, review products
Quality assurance
Independent of project team
Quality register
Diary of quality events
Product description
Purpose, composition, quality criteria

Risk Terms

Risk
Uncertain event affecting objectives
Threat
Risk with negative impact
Opportunity
Risk with positive impact
Risk appetite
Willingness to take risk
Risk tolerance
Measurable escalation threshold
Risk budget
Money for risk responses
Risk exposure
Combined effect of risks
Risk owner
Manages and monitors risk
Risk action owner
Carries out the response
Cause, event, effect
How risks are described

Risk Response Types

Avoid
Remove the threat entirely
Exploit
Make opportunity happen
Reduce
Lower probability or impact
Enhance
Raise probability or impact
Transfer
Move impact to another
Share
Split gain and pain
Accept
Take no action now
Prepare contingent plans
Act only if triggered

Issue Types + Change

Request for change
Proposal to alter baseline
Off-specification
Product misses quality specification
Problem
Immediate negative impact
Concern
Timing and impact unassessed
Business opportunity
Unexpected positive possibility
Project baseline
Approved versions under control
Change budget
Funds approved changes
Change authority
Board or delegated decider

Progress Controls

Tolerance
Permitted deviation before escalation
Exception
Forecast breach of tolerance
Forecast
Projected outcome versus plan
Time-driven control
Happens at set intervals
Event-driven control
Triggered by an event
Tolerance areas
The seven performance aspects
Escalation route
Up one management level

Process Order

SU DP IP CS MP SB CP

SU: starting upDP: directing (throughout)IP: initiatingCS: controlling a stageMP: managing product deliverySB: stage boundaryCP: closing a project

Which Process Applies?

  1. Mandate just receivedStarting up a project(Pre-project)
  2. Board must authorizeDirecting a project(Runs throughout)
  3. Baseline the projectInitiating a project(Produces the PID)
  4. Daily stage workControlling a stage(Project manager)
  5. Team is building productsManaging product delivery(Team manager)
  6. Stage nearly finishedManaging a stage boundary(Next stage plan)
  7. Tolerance forecast breachedManaging a stage boundary(Exception plan)
  8. Products acceptedClosing a project(End project report)

Seven Processes: Purpose

Starting up a project
Check project is worthwhile
Directing a project
Board decides and controls
Initiating a project
Build solid project foundations
Controlling a stage
Assign, monitor, correct work
Managing product delivery
Team builds agreed products
Managing a stage boundary
Plan next stage, report
Closing a project
Confirm acceptance, hand over

Process Triggers + Outputs

Project mandate
Triggers starting up
Project brief
Output of starting up
Initiation stage plan
Approved before initiating
PID
Output of initiating
Work package
Controlling stage to delivery
Exception report
Board may request replan
End stage report
Output of stage boundary
End project report
Output of closing

Common Traps

Practices, not themes

Version 7 says practices Version 6 said themes

Five elements, not four

Version 7 adds people Version 6 had four

Seven aspects, not six

Version 7 adds sustainability Version 6 had six

Brief is not PID

Brief precedes initiation PID baselines the project

Issue is not exception

Issue already happened Exception is forecast breach

Appetite is not tolerance

Appetite is willingness Tolerance is measurable limit

Assurance is not support

Assurance checks independently Support administers for manager

Registers sit in log

Version 7 uses project log Version 6 kept them separate

Pass mark is 60%

Version 7 needs 36 Version 6 needed 33

Adoption is not control

Change management moves people Change control protects baselines

Last Minute

  1. 1.60 questions; 60 minutes; 36 pass
  2. 2.Closed book; no negative marking
  3. 3.Practices = 60% of exam
  4. 4.People = 14%; processes = 15%
  5. 5.Practices not themes (version 7)
  6. 6.Elements = 5; aspects = 7
  7. 7.Sustainability = seventh performance aspect
  8. 8.Project log holds six records
  9. 9.Brief = pre-project; PID = baseline
  10. 10.Executive owns the business case
  11. 11.Senior user owns the benefits
  12. 12.Tolerance = limit; exception = breach
  13. 13.QA independent; QC tests products
  14. 14.Manage by stages: minimum two
  15. 15.Tailor everything except the principles
Same family resources

Explore More PRINCE2 Certifications