Principles in Context
10%of exam
People Management
9%of exam
Practices in Context
51%of exam
Processes in Context
30%of exam
Quick Facts
- Exam owner
- PeopleCert
- Qualification
- Project Management Practitioner Version 7
- Standard time
- 150 minutes
- Questions
- 56 questions and sub-questions
- Available marks
- 70 marks
- Pass mark
- 42 of 70 marks (60%)
- Question types
- Scenario-based standard and matching
- Open-book reference
- Official Version 7 book
- Entry requirement
- One accepted certification
Principles Recall
Justify, learn, assign, stage, delegate, define, tailor.
Stages vs Exception
Manage by stages
- Set management decision points
- Review before further commitment
Manage by exception
- Set limits on delegated authority
- Escalate forecast tolerance breaches
Stage gates and forecast breaches differ
Tailoring Decisions
- Small low-risk project→Simplify management products(Keep required controls)
- Existing corporate reports fit→Reuse reporting format(Keep necessary decision information)
- Limited delivery staff→Consider combining team management roles(Project manager can lead team)
- Using iterative delivery→Align governance with delivery cadence(Keep stage decisions explicit)
- Business justification no longer holds→Seek direction on closure(Review options and viability)
Seven Principles
- Ensure continued business justification
- Recheck the case for investment
- Learn from experience
- Seek, record and apply lessons
- Define roles, responsibilities and relationships
- Agree accountability and stakeholder relationships
- Manage by stages
- Plan and control by stage
- Manage by exception
- Delegate authority within agreed tolerances
- Focus on products
- Agree outputs and quality first
- Tailor to suit the project
- Adapt controls to project context
Adoption vs Change Control
Change management approach
- Addresses organizational transition
- Supports people adopting the outcome
Issue management approach
- Defines issue handling
- Controls changes to approved baselines
Guide adoption and govern baseline changes
People Decisions
- Users resist a new workflow→Plan adoption and support(Change management approach)
- Stakeholders get conflicting updates→Agree channels and feedback loops(Communication management approach)
- Hybrid team lacks trust→Create shared working agreements(Adapt collaboration to locations)
- Team lacks a critical skill→Close the skills gap(Train or bring in expertise)
People and Teams
- Project ecosystem
- People and relationships shaping delivery
- Organizational ecosystem
- Wider network around the project
- Stakeholders
- Include people affected by outcomes
- Leadership
- Influence people toward shared goals
- Management
- Coordinate work and resources
- Team capability
- Identify skills and address gaps
- Cultural intelligence
- Work across different cultures
- Team cohesion
- Build trust across locations
People Management Approaches
- Change management approach
- Plan transition to target state
- Communication management approach
- Define channels, cadence and feedback
- Change impact
- Identify affected groups and needs
- Adoption
- Embed new ways of working
- Two-way communication
- Share information and seek feedback
Seven Performance Targets
Time and cost, scope and quality, benefits, risk, sustainability.
Acceptance vs Quality Specifications
Acceptance criteria
- Apply to overall project product
- Guide user acceptance
Quality specifications
- Apply to individual products
- Guide product quality checks
Identify what is being judged
Tolerance Decisions
- Forecast stays within delegated tolerance→Take authorized corrective action(Keep routine reporting)
- Work package tolerance forecast exceeded→Team manager raises an issue(Inform project manager)
- Stage tolerance forecast exceeded→Project manager escalates to board(Issue report then exception report)
- Project tolerance forecast exceeded→Board escalates to business layer(Seek decision)
- Board requests stage exception plan→Prepare through stage boundary(Even during final stage)
- Exception plan gains authorization→Use the replacement baseline(For the affected plan)
Business Case
- Investment test
- Desirable, viable and achievable
- Business case
- Costs, benefits and associated risks
- Outline business case
- Early justification in project brief
- Full business case
- Basis for project authorization
- Benefits management approach
- Actions and reviews for benefits
- Sustainability management approach
- Project and product lifecycle controls
- Output
- Deliverable produced by work
- Outcome
- Change enabled by outputs
- Benefit
- Measurable improvement from an outcome
- Dis-benefit
- Measurable decline from an outcome
Risk Technique Recall
Identify, assess, plan, implement. Communicate throughout.
Risk vs Issue
Risk
- Uncertain event affecting objectives
- Record threats and opportunities
Issue
- Event requiring management action
- Assess impact and baseline implications
Check whether the event has occurred
Record and Report Picker
- Possible future supplier failure→Risk register(Assign a risk owner)
- Supplier already missed commitment→Issue register(Assess the impact)
- Approved product specification missed→Off-specification(Assess before any concession)
- Stakeholder proposes baseline change→Request for change(Assess impact and authority)
- Need inspection schedule and results→Quality register(Track checks and outcomes)
- Need product approval status→Product register(Check the deliverable record)
- Routine work package update→Checkpoint report(Team manager to project manager)
- Routine board progress update→Highlight report(Project manager to project board)
Organization
- Business layer
- Sets project-level tolerances and commissions
- Project board
- Directs and authorizes the project
- Project executive
- Owns the business caseBusiness
- Senior user
- Represents users and specifies benefitsUser
- Senior supplier
- Represents suppliers and technical integritySupplier
- Project manager
- Manages day-to-day within delegated authority
- Team manager
- Delivers agreed work packages
- Project assurance
- Independent oversight for project board
- Project support
- Provides administrative and tool support
- Commercial management approach
- Sets how suppliers are managed
Risk Owner vs Action Owner
Risk owner
- Oversees one risk
- Monitors the overall response
Risk action owner
- Owns assigned response actions
- Executes the agreed actions
Assign oversight and actions explicitly
Plans
- Product-based planning
- Define deliverables before scheduling activities
- Product breakdown structure
- Hierarchy of products
- Product flow diagram
- Sequence and dependencies of products
- Project product description
- Overall expectations and acceptance criteria
- Project plan
- High-level whole-project view
- Stage plan
- Detailed control of one stage
- Team plan
- Optional team delivery plan
- Work package description
- Agreed products, constraints and reporting
- Exception plan
- Replaces affected plan once authorized
Exception Report vs Exception Plan
Exception report
- Explains forecast tolerance breach
- Presents impacts and options
Exception plan
- Prepared when requested
- Replaces plan only after authorization
Escalate first, then replan if requested
Quality
- Product description
- Individual product specifications and checks
- Acceptance criteria
- Conditions for accepting project product
- Quality specification
- Measurable standard for a product
- Quality management approach
- Standards, methods and responsibilities
- Quality planning
- Define specifications and checks
- Quality control
- Check products against agreed specifications
- Quality assurance
- Independent checks on quality arrangements
- Product register
- Tracks deliverables and approval status
- Quality register
- Tracks quality activities and results
Risk
- Risk register
- Tracks threats and opportunitiesProject log
- Risk management approach
- Defines procedures, thresholds and responsibilitiesPID
- Risk owner
- Oversees the response to risk
- Risk action owner
- Performs assigned response actions
- Probability
- Chance the risk occurs
- Impact
- Effect if the risk occurs
- Proximity
- How soon risk might occur
- Velocity
- How quickly effects emerge
- Risk appetite
- Risk business will accept
- Risk tolerance
- Measurable limit on risk
- Contingent plan
- Response prepared for risk materialization
Issues
- Issue management approach
- Defines issue and change controlsPID
- Issue register
- Tracks formal issues and decisionsProject log
- Issue report
- Assesses impact and recommends action
- Change authority
- Decides changes within delegated limits
- Request for change
- Proposal to modify a baseline
- Off-specification
- Product will miss agreed specifications
- Problem
- Immediate negative impact
- Concern
- Timing and impact need assessment
- External event
- Outside event that may affect project
- Business opportunity
- Unplanned favorable development
Progress
- Checkpoint report
- Team manager to project manager
- Highlight report
- Project manager to project board
- End stage report
- Stage performance for board review
- End project report
- Project performance against baselines
- Exception report
- Escalates forecast breach with options
- Lessons log
- Record lessons as they emerge
- Lessons report
- Share lessons for reuse
- Daily log
- Informal notes and actionsProject log
- Digital and data management approach
- Data handling through project lifecyclePID
- Time-driven control
- At agreed reporting intervals
- Event-driven control
- Triggered by a specific event
- Stage tolerances
- Board delegates to project manager
- Work package tolerances
- Project manager delegates to team
Work Package Recall
Project manager authorizes, team accepts, executes, evaluates, notifies.
Stage Boundary vs Closure
Managing a stage boundary
- Review stage and justification
- Prepare next stage or exception plan
Closing a project
- Confirm acceptance and handover
- Evaluate project and request closure
Board authorizes the next move
Process Picker
- Mandate received, viability untested→Starting up a project(Assemble project brief)
- Initiation authorized, baselines needed→Initiating a project(Assemble initiation documentation)
- Stage approval or strategic direction→Directing a project(Board decision)
- Project manager assigns work→Controlling a stage(Authorize work package)
- Team accepts and delivers work→Managing product delivery(Notify completion)
- Next stage plan needs preparing→Managing a stage boundary(Request board authorization)
- Final product ready for handover→Closing a project(Confirm user acceptance)
- Board directs premature closure→Closing a project(Arrange orderly handover)
Seven Processes
- Starting up a project
- Screen viability before initiating
- Directing a project
- Board authorizes and gives direction
- Initiating a project
- Establish baselines before project authorization
- Controlling a stage
- Assign, monitor and correct work
- Managing product delivery
- Team accepts, executes, delivers work
- Managing a stage boundary
- Evaluate stage and plan ahead
- Closing a project
- Confirm acceptance and request closure
Delivery Control vs Delivery
Controlling a stage
- Project manager authorizes work
- Receives completed work packages
Managing product delivery
- Team manager accepts work
- Notifies project manager of completion
Project manager assigns, team manager delivers
Process Outputs
- Project mandate
- Business trigger for starting up
- Project brief
- Basis for authorizing initiation
- Initiation stage plan
- Plans work needed for initiation
- Project initiation documentation (PID)
- Basis for authorizing the project
- Next stage plan
- Supports next stage authorization
- Updated business case
- Rechecks justification at stage boundary
- Follow-on action recommendations
- Hand over unresolved risks and issues
- Post-project benefit reviews
- Schedule in benefits management approach
- Tailoring decisions
- Record in project initiation documentation
Common Traps
Question Count and Scoring
56 questions and sub-questions ≠ 70 available marks
Forecast Triggers Escalation
Forecast tolerance breach ≠ Already exceeded tolerance
Controls Can Be Tailored
Adapt reporting to context ≠ Drop a principle
Approval Changes the Baseline
Exception plan proposed ≠ Exception plan authorized
Keep Governance Accountable
Executive owns business case ≠ Project manager manages daily work
Registers Serve Different Purposes
Product register tracks deliverables ≠ Quality register tracks checks
Project Closure Is Authorized
Manager requests closure ≠ Board authorizes closure
Benefits Follow Use
Product handed over ≠ Benefit realized
Last Minute
- 1.Use the official Version 7 book
- 2.Apply the method to scenario facts
- 3.Identify the active process first
- 4.Find who holds decision authority
- 5.Escalate forecast breaches promptly
- 6.Check sustainability alongside other targets
- 7.Board authorizes initiation and project separately
- 8.Distinguish checkpoint from highlight reports
- 9.Planned closure: confirm project product acceptance
- 10.Schedule post-project benefit reviews
- 11.Keep all seven principles when tailoring