PRINCE2 Project Management Practitioner Cheat Sheet

Quick Facts

Exam owner
PeopleCert
Qualification
Project Management Practitioner Version 7
Standard time
150 minutes
Questions
56 questions and sub-questions
Available marks
70 marks
Pass mark
42 of 70 marks (60%)
Question types
Scenario-based standard and matching
Open-book reference
Official Version 7 book
Entry requirement
One accepted certification

Principles Recall

Justify, learn, assign, stage, delegate, define, tailor.

InvestmentLessonsRoles and relationshipsManagement stagesTolerancesProductsProject context

Stages vs Exception

Manage by stages

  • Set management decision points
  • Review before further commitment

Manage by exception

  • Set limits on delegated authority
  • Escalate forecast tolerance breaches

Stage gates and forecast breaches differ

Tailoring Decisions

  1. Small low-risk project→Simplify management products(Keep required controls)
  2. Existing corporate reports fit→Reuse reporting format(Keep necessary decision information)
  3. Limited delivery staff→Consider combining team management roles(Project manager can lead team)
  4. Using iterative delivery→Align governance with delivery cadence(Keep stage decisions explicit)
  5. Business justification no longer holds→Seek direction on closure(Review options and viability)

Seven Principles

Ensure continued business justification
Recheck the case for investment
Learn from experience
Seek, record and apply lessons
Define roles, responsibilities and relationships
Agree accountability and stakeholder relationships
Manage by stages
Plan and control by stage
Manage by exception
Delegate authority within agreed tolerances
Focus on products
Agree outputs and quality first
Tailor to suit the project
Adapt controls to project context

Adoption vs Change Control

Change management approach

  • Addresses organizational transition
  • Supports people adopting the outcome

Issue management approach

  • Defines issue handling
  • Controls changes to approved baselines

Guide adoption and govern baseline changes

People Decisions

  1. Users resist a new workflow→Plan adoption and support(Change management approach)
  2. Stakeholders get conflicting updates→Agree channels and feedback loops(Communication management approach)
  3. Hybrid team lacks trust→Create shared working agreements(Adapt collaboration to locations)
  4. Team lacks a critical skill→Close the skills gap(Train or bring in expertise)

People and Teams

Project ecosystem
People and relationships shaping delivery
Organizational ecosystem
Wider network around the project
Stakeholders
Include people affected by outcomes
Leadership
Influence people toward shared goals
Management
Coordinate work and resources
Team capability
Identify skills and address gaps
Cultural intelligence
Work across different cultures
Team cohesion
Build trust across locations

People Management Approaches

Change management approach
Plan transition to target state
Communication management approach
Define channels, cadence and feedback
Change impact
Identify affected groups and needs
Adoption
Embed new ways of working
Two-way communication
Share information and seek feedback

Seven Performance Targets

Time and cost, scope and quality, benefits, risk, sustainability.

TimeCostScopeQualityBenefitsRiskSustainability

Acceptance vs Quality Specifications

Acceptance criteria

  • Apply to overall project product
  • Guide user acceptance

Quality specifications

  • Apply to individual products
  • Guide product quality checks

Identify what is being judged

Tolerance Decisions

  1. Forecast stays within delegated tolerance→Take authorized corrective action(Keep routine reporting)
  2. Work package tolerance forecast exceeded→Team manager raises an issue(Inform project manager)
  3. Stage tolerance forecast exceeded→Project manager escalates to board(Issue report then exception report)
  4. Project tolerance forecast exceeded→Board escalates to business layer(Seek decision)
  5. Board requests stage exception plan→Prepare through stage boundary(Even during final stage)
  6. Exception plan gains authorization→Use the replacement baseline(For the affected plan)

Business Case

Investment test
Desirable, viable and achievable
Business case
Costs, benefits and associated risks
Outline business case
Early justification in project brief
Full business case
Basis for project authorization
Benefits management approach
Actions and reviews for benefits
Sustainability management approach
Project and product lifecycle controls
Output
Deliverable produced by work
Outcome
Change enabled by outputs
Benefit
Measurable improvement from an outcome
Dis-benefit
Measurable decline from an outcome

Risk Technique Recall

Identify, assess, plan, implement. Communicate throughout.

Find uncertaintyPrioritize risksChoose responsesCarry out actionsKeep stakeholders informed

Risk vs Issue

Risk

  • Uncertain event affecting objectives
  • Record threats and opportunities

Issue

  • Event requiring management action
  • Assess impact and baseline implications

Check whether the event has occurred

Record and Report Picker

  1. Possible future supplier failure→Risk register(Assign a risk owner)
  2. Supplier already missed commitment→Issue register(Assess the impact)
  3. Approved product specification missed→Off-specification(Assess before any concession)
  4. Stakeholder proposes baseline change→Request for change(Assess impact and authority)
  5. Need inspection schedule and results→Quality register(Track checks and outcomes)
  6. Need product approval status→Product register(Check the deliverable record)
  7. Routine work package update→Checkpoint report(Team manager to project manager)
  8. Routine board progress update→Highlight report(Project manager to project board)

Organization

Business layer
Sets project-level tolerances and commissions
Project board
Directs and authorizes the project
Project executive
Owns the business caseBusiness
Senior user
Represents users and specifies benefitsUser
Senior supplier
Represents suppliers and technical integritySupplier
Project manager
Manages day-to-day within delegated authority
Team manager
Delivers agreed work packages
Project assurance
Independent oversight for project board
Project support
Provides administrative and tool support
Commercial management approach
Sets how suppliers are managed

Risk Owner vs Action Owner

Risk owner

  • Oversees one risk
  • Monitors the overall response

Risk action owner

  • Owns assigned response actions
  • Executes the agreed actions

Assign oversight and actions explicitly

Plans

Product-based planning
Define deliverables before scheduling activities
Product breakdown structure
Hierarchy of products
Product flow diagram
Sequence and dependencies of products
Project product description
Overall expectations and acceptance criteria
Project plan
High-level whole-project view
Stage plan
Detailed control of one stage
Team plan
Optional team delivery plan
Work package description
Agreed products, constraints and reporting
Exception plan
Replaces affected plan once authorized

Exception Report vs Exception Plan

Exception report

  • Explains forecast tolerance breach
  • Presents impacts and options

Exception plan

  • Prepared when requested
  • Replaces plan only after authorization

Escalate first, then replan if requested

Quality

Product description
Individual product specifications and checks
Acceptance criteria
Conditions for accepting project product
Quality specification
Measurable standard for a product
Quality management approach
Standards, methods and responsibilities
Quality planning
Define specifications and checks
Quality control
Check products against agreed specifications
Quality assurance
Independent checks on quality arrangements
Product register
Tracks deliverables and approval status
Quality register
Tracks quality activities and results

Risk

Risk register
Tracks threats and opportunitiesProject log
Risk management approach
Defines procedures, thresholds and responsibilitiesPID
Risk owner
Oversees the response to risk
Risk action owner
Performs assigned response actions
Probability
Chance the risk occurs
Impact
Effect if the risk occurs
Proximity
How soon risk might occur
Velocity
How quickly effects emerge
Risk appetite
Risk business will accept
Risk tolerance
Measurable limit on risk
Contingent plan
Response prepared for risk materialization

Issues

Issue management approach
Defines issue and change controlsPID
Issue register
Tracks formal issues and decisionsProject log
Issue report
Assesses impact and recommends action
Change authority
Decides changes within delegated limits
Request for change
Proposal to modify a baseline
Off-specification
Product will miss agreed specifications
Problem
Immediate negative impact
Concern
Timing and impact need assessment
External event
Outside event that may affect project
Business opportunity
Unplanned favorable development

Progress

Checkpoint report
Team manager to project manager
Highlight report
Project manager to project board
End stage report
Stage performance for board review
End project report
Project performance against baselines
Exception report
Escalates forecast breach with options
Lessons log
Record lessons as they emerge
Lessons report
Share lessons for reuse
Daily log
Informal notes and actionsProject log
Digital and data management approach
Data handling through project lifecyclePID
Time-driven control
At agreed reporting intervals
Event-driven control
Triggered by a specific event
Stage tolerances
Board delegates to project manager
Work package tolerances
Project manager delegates to team

Work Package Recall

Project manager authorizes, team accepts, executes, evaluates, notifies.

Authorize work packageAccept work packageExecute work packageEvaluate work packageNotify completion

Stage Boundary vs Closure

Managing a stage boundary

  • Review stage and justification
  • Prepare next stage or exception plan

Closing a project

  • Confirm acceptance and handover
  • Evaluate project and request closure

Board authorizes the next move

Process Picker

  1. Mandate received, viability untested→Starting up a project(Assemble project brief)
  2. Initiation authorized, baselines needed→Initiating a project(Assemble initiation documentation)
  3. Stage approval or strategic direction→Directing a project(Board decision)
  4. Project manager assigns work→Controlling a stage(Authorize work package)
  5. Team accepts and delivers work→Managing product delivery(Notify completion)
  6. Next stage plan needs preparing→Managing a stage boundary(Request board authorization)
  7. Final product ready for handover→Closing a project(Confirm user acceptance)
  8. Board directs premature closure→Closing a project(Arrange orderly handover)

Seven Processes

Starting up a project
Screen viability before initiating
Directing a project
Board authorizes and gives direction
Initiating a project
Establish baselines before project authorization
Controlling a stage
Assign, monitor and correct work
Managing product delivery
Team accepts, executes, delivers work
Managing a stage boundary
Evaluate stage and plan ahead
Closing a project
Confirm acceptance and request closure

Delivery Control vs Delivery

Controlling a stage

  • Project manager authorizes work
  • Receives completed work packages

Managing product delivery

  • Team manager accepts work
  • Notifies project manager of completion

Project manager assigns, team manager delivers

Process Outputs

Project mandate
Business trigger for starting up
Project brief
Basis for authorizing initiation
Initiation stage plan
Plans work needed for initiation
Project initiation documentation (PID)
Basis for authorizing the project
Next stage plan
Supports next stage authorization
Updated business case
Rechecks justification at stage boundary
Follow-on action recommendations
Hand over unresolved risks and issues
Post-project benefit reviews
Schedule in benefits management approach
Tailoring decisions
Record in project initiation documentation

Common Traps

Question Count and Scoring

56 questions and sub-questions ≠ 70 available marks

Forecast Triggers Escalation

Forecast tolerance breach ≠ Already exceeded tolerance

Controls Can Be Tailored

Adapt reporting to context ≠ Drop a principle

Approval Changes the Baseline

Exception plan proposed ≠ Exception plan authorized

Keep Governance Accountable

Executive owns business case ≠ Project manager manages daily work

Registers Serve Different Purposes

Product register tracks deliverables ≠ Quality register tracks checks

Project Closure Is Authorized

Manager requests closure ≠ Board authorizes closure

Benefits Follow Use

Product handed over ≠ Benefit realized

Last Minute

  1. 1.Use the official Version 7 book
  2. 2.Apply the method to scenario facts
  3. 3.Identify the active process first
  4. 4.Find who holds decision authority
  5. 5.Escalate forecast breaches promptly
  6. 6.Check sustainability alongside other targets
  7. 7.Board authorizes initiation and project separately
  8. 8.Distinguish checkpoint from highlight reports
  9. 9.Planned closure: confirm project product acceptance
  10. 10.Schedule post-project benefit reviews
  11. 11.Keep all seven principles when tailoring