All Practice Exams

100+ Free NEBOSH Construction Practice Questions

NEBOSH Health and Safety Management for Construction (UK) practice questions are available now; exam metadata is being verified.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free

Loading questions...

2026 Statistics

Key Facts: NEBOSH Construction Exam

45%

Provisional pass standard for the Unit CN1 open-book assessment

NEBOSH

48 hours

Window to download, complete and submit the scenario-based digital exam

NEBOSH

13

Syllabus elements, from CDM management foundations to physical and psychological health

NEBOSH CN syllabus guide

70 + 40 hours

Minimum taught hours plus recommended private study before sitting CN1

NEBOSH

SCQF Level 7

Qualification level (comparable to RQF Level 4), carrying 12 SCQF credit points

NEBOSH / SQA Accreditation

~10 minutes

Length of the online closing interview that verifies the work is the candidate's own

NEBOSH

50 working days

Typical wait for emailed results after the examination date

NEBOSH

The NEBOSH Health and Safety Management for Construction (UK) is aimed at site managers, contracts managers, construction health and safety advisors and workers with safety responsibilities. Study requires a minimum of 70 taught hours plus around 40 hours of private study with a NEBOSH Learning Partner. The single assessment, Unit CN1, is an open-book digital exam based on a realistic construction scenario: you download the paper at 11am UK time and have 48 hours to submit a series of applied tasks, followed by a roughly 10-minute closing interview that confirms the work is your own. The provisional pass standard is 45% and results arrive within about 50 working days. Content tracks CDM 2015 - client, principal designer and principal contractor duties, construction phase plans and the health and safety file - then the practical hazard elements: excavation and demolition, mobile plant, work at height, work equipment, electricity, fire, and occupational health from silica and asbestos to noise, vibration and stress. Passing supports the CSCS Academically Qualified Person card route. Question-style practice like this bank builds the fast rule recall that makes the open-book tasks manageable.

Sample NEBOSH Construction Practice Questions

Try these sample questions to test your NEBOSH Construction exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1Under the Construction (Design and Management) Regulations 2015, a construction project must be notified to the HSE (form F10) when the work is scheduled to:
A.Last longer than 30 working days with more than 20 workers working simultaneously at any point, or exceed 500 person-days
B.Last longer than 40 working days or involve more than 10 workers at any time
C.Involve more than one contractor working on site at the same time
D.Have a contract value exceeding 1 million pounds
Explanation: CDM 2015 regulation 6 sets the notification thresholds: more than 30 working days with more than 20 workers simultaneously at any point, or more than 500 person-days of construction work.
2On a notifiable commercial project under CDM 2015, which duty holder is responsible for submitting the F10 notification to the HSE?
A.The principal contractor
B.The principal designer
C.The client
D.The lead designer
Explanation: Regulation 6 of CDM 2015 places the duty to notify the HSE as soon as practicable before the construction phase begins on the client (the notice must be displayed on site).
3A client is planning an office refurbishment that will involve a demolition contractor, an M&E contractor and a fit-out contractor. Under CDM 2015 the client must:
A.Notify the HSE because three contractors automatically makes the project notifiable
B.Appoint, in writing, a principal designer and a principal contractor because more than one contractor will be involved
C.Appoint only a principal contractor, since design work has already been completed
D.Allow the contractors to agree among themselves who will coordinate health and safety
Explanation: CDM 2015 regulation 5 requires the client to appoint a principal designer and a principal contractor in writing whenever it is foreseeable that more than one contractor will work on a project.
4On a project involving several contractors, who is responsible for drawing up the construction phase plan before the construction phase begins?
A.The client, because they commission the project
B.The principal designer, because they control pre-construction information
C.Each contractor for their own work package
D.The principal contractor
Explanation: Under CDM 2015 regulation 12, the principal contractor must draw up the construction phase plan (or arrange for it to be drawn up) before setting up the construction site; a plan is required for every project.
5What is the primary purpose of the health and safety file required under CDM 2015 for projects involving more than one contractor?
A.To record accidents and near misses that occurred during the construction phase
B.To provide information needed to ensure health and safety during future construction, maintenance, refurbishment or demolition of the structure
C.To demonstrate to the HSE that the principal contractor managed the construction phase competently
D.To list the training records and competence cards of all workers employed on the project
Explanation: The health and safety file, prepared by the principal designer and handed to the client at project completion, contains information (such as residual hazards, as-built drawings and locations of services) needed for safe future work on the structure.
6Which duty holder must provide pre-construction information, such as existing asbestos surveys and drawings showing buried services, to designers and contractors?
A.The client
B.The principal contractor
C.The HSE
D.The site supervisor
Explanation: CDM 2015 regulation 4 requires the client to provide pre-construction information as soon as practicable to every designer and contractor appointed or being considered for appointment.
7A homeowner engages a builder and two specialist contractors to construct a house extension. How are the CDM 2015 client duties handled for this domestic client?
A.Domestic projects are exempt from CDM 2015 so no client duties apply
B.The homeowner must attend CDM awareness training before work can start
C.The client duties are normally carried out by the principal contractor (or contractor), unless the principal designer agrees in writing to take them on
D.The local authority building control officer automatically assumes the client duties
Explanation: Under CDM 2015 regulation 7, a domestic client's duties pass by default to the contractor (single contractor) or principal contractor (multiple contractors), though the principal designer can take them on by written agreement.
8Under CDM 2015, what is the primary health and safety duty of a designer when preparing a design for a new structure?
A.To supervise contractors to make sure the design is built safely
B.To apply the general principles of prevention, eliminating foreseeable risks where possible and reducing those that remain
C.To prepare the construction phase plan covering the design elements
D.To carry out site inductions for workers affected by the design
Explanation: CDM 2015 regulation 9 requires designers to take account of the general principles of prevention: eliminate foreseeable health and safety risks through design choices, reduce risks that cannot be eliminated, and provide information about remaining risks.
9Schedule 2 of CDM 2015 sets minimum welfare requirements that must be available on site from the start of the construction phase. Which set of facilities reflects these requirements?
A.Toilets, a first-aid room, a canteen serving hot food and on-site parking
B.Drinking water and toilets only, with washing facilities provided once the project exceeds 30 days
C.A rest area and drying room, with sanitary facilities required only on notifiable projects
D.Suitable toilets, washing facilities with hot and cold (or warm) running water, drinking water, changing/drying facilities and rest facilities
Explanation: Schedule 2 of CDM 2015 requires sanitary conveniences, washing facilities including hot and cold or warm running water, drinking water, changing rooms with drying facilities where special clothing is worn, and rest facilities, available throughout the construction phase.
10A demolition site borders a public footpath and dust and debris could affect passers-by. Which section of the Health and Safety at Work etc. Act 1974 places a duty on the employer to protect these members of the public?
A.Section 2
B.Section 7
C.Section 3
D.Section 8
Explanation: Section 3 of HSWA 1974 requires employers to conduct their undertaking so that persons not in their employment, including the public, are not exposed to risks to their health or safety.