Under the Construction (Design and Management) Regulations 2015, a construction project must be notified to the HSE (form F10) when the work is scheduled to:
Cdm Management Foundations
Question · Easy
On a notifiable commercial project under CDM 2015, which duty holder is responsible for submitting the F10 notification to the HSE?
A client is planning an office refurbishment that will involve a demolition contractor, an M&E contractor and a fit-out contractor. Under CDM 2015 the client must:
Question · Medium
On a project involving several contractors, who is responsible for drawing up the construction phase plan before the construction phase begins?
What is the primary purpose of the health and safety file required under CDM 2015 for projects involving more than one contractor?
Question · Hard
Which duty holder must provide pre-construction information, such as existing asbestos surveys and drawings showing buried services, to designers and contractors?
A homeowner engages a builder and two specialist contractors to construct a house extension. How are the CDM 2015 client duties handled for this domestic client?
Under CDM 2015, what is the primary health and safety duty of a designer when preparing a design for a new structure?
Schedule 2 of CDM 2015 sets minimum welfare requirements that must be available on site from the start of the construction phase. Which set of facilities reflects these requirements?
A demolition site borders a public footpath and dust and debris could affect passers-by. Which section of the Health and Safety at Work etc. Act 1974 places a duty on the employer to protect these members of the public?
Under section 7 of the Health and Safety at Work etc. Act 1974, employees on a construction site must:
Under the Management of Health and Safety at Work Regulations 1999, an employer must record the significant findings of risk assessments when:
In the HSE's five-step approach to risk assessment, what should the assessor do immediately after identifying the hazards of a groundworks task?
Workers are exposed to silica dust when chasing brick walls for cable runs. Applying the general hierarchy of control, which option should be considered FIRST?
Which combination of indicators would most strongly suggest a NEGATIVE health and safety culture on a construction site?
A principal contractor wants to improve the health and safety culture across its sites. Which single action is likely to have the greatest long-term influence?
Why is the reporting and investigation of near misses important on a construction site?
In the HSG65 'Plan, Do, Check, Act' model of health and safety management, active monitoring such as site inspections and audits belongs to which stage?
Which feature is essential to an effective permit-to-work system for hot work on a refurbishment site?
When developing a safe system of work for a complex steel-erection task, why should the workers who will carry out the task be involved?
Halfway through excavating footings, the ground conditions change from firm clay to waterlogged sand, which the method statement did not anticipate. What should the site manager do FIRST?
In accordance with BS 5975, what is the role of a temporary works coordinator (TWC) on a construction project?
Which subject matter MUST a site induction cover to be effective for new starters on a specific construction site?
A bricklayer fractures a wrist (not a specified injury) in a fall and is unable to perform their normal work for nine consecutive days, not counting the day of the accident. Under RIDDOR 2013 the responsible person must:
An HSE inspector visits a site and finds workers in an unsupported 3-metre-deep trench in loose ground. Which enforcement action is the inspector most likely to take, and why?
Under regulation 22 of CDM 2015, when must a supported excavation be inspected by a competent person?
Excavation Demolition
A competent person inspects a supported excavation at the start of every shift. What are the written reporting requirements for these inspections under CDM 2015?
Before breaking ground for a new drainage run, what is the correct approach to locating buried services in accordance with HSG47?
A buried low-voltage electricity cable has been located and marked crossing a trench line. Which digging practice is correct when working near the cable?
Trench support is to be installed in a 2.5-metre-deep excavation in soft ground. What is the correct principle for installing the support?
Why must excavated spoil be stored well back from the edge of an excavation?
Dumpers will be tipping fill material into an excavation. Which control prevents the vehicles from falling into the excavation?
A 3-metre-deep excavation is planned alongside the strip foundations of an occupied two-storey building. What is the principal structural hazard, and what should be done before digging starts?
Under regulation 20 of CDM 2015, the demolition or dismantling of a structure must be:
Before a 1970s factory building is demolished, what type of asbestos survey is required under the Control of Asbestos Regulations 2012 and HSG264?
Why is remote mechanical demolition using a high-reach excavator generally preferred over hand demolition for a multi-storey structure?
Deliberate controlled collapse using pre-weakening and explosives is being considered for a redundant concrete silo. Which condition is essential for this demolition method?
Apart from asbestos, what key information should a pre-demolition structural survey and site investigation establish before work begins on an old industrial building?
A demolition site is bounded by a busy high street. Which combination of measures best protects members of the public passing the site?
Most construction transport fatalities involve workers being struck by moving or reversing site vehicles. Which planning measure tackles this risk at source?
Mobile Plant Vehicles
What is the most effective way to protect pedestrians from site vehicles on a large construction site?
Where reversing of delivery vehicles cannot be avoided, which requirements apply to the signaller (banksman) who directs them?
Several fatalities have been caused by excavator buckets detaching from semi-automatic quick hitches. What must the operator do to prevent this failure?
Which combination of controls best protects the operator of a forward-tipping dumper from death or injury in an overturn?
A telehandler will place pallets of blocks onto a scaffold loading bay. Which practice is essential for the machine's stability?
How should a principal contractor verify that a newly arrived 360-degree excavator operator may operate plant on site?
Visibility aids such as mirrors, CCTV cameras and proximity detection are fitted to site dumpers and excavators primarily to:
Who should carry out the daily pre-use checks of a site dumper, and what should they cover?