ICC B1 Residential Cheat Sheet

Code Administration

4%of exam

Project AdminPermitsReportsCOStop Work

Building Planning

8%of exam

Unit SeparationSite LocationRoom DimensionsEgress WindowsStairs

Footings and Foundations

16%of exam

FootingsFoundation WallsAnchor BoltsDrainageBackfill

Floor Construction

14%of exam

JoistsBearingNotchingSubflooringCrawlspaces

Wall Construction

27%of exam

StudsHeadersBracingFireblockingWRB

Roof and Ceiling

14%of exam

AtticsRaftersTrussesSheathingFlashing

Public Safety

17%of exam

EgressHandrailsGuardsAlarmsSafety Glazing

Quick Facts

Exam
B1
Credential
Residential Building Inspector
Questions
60
Time
2 hours
Format
Open book
Scope
IRC dwellings
Pass
75 scaled
Provider
ICC

Permit vs CO

Permit

  • Starts legal work
  • Before construction
  • Scope approval

CO

  • Allows occupancy
  • After final
  • Use approval

Start work vs occupy

Inspection Picker

  1. Missing approved plansStop review(Baseline absent)
  2. Unlisted productAHJ approval(Alternative path)
  3. Work concealedInspection required(Verify first)
  4. Unsafe conditionStop work(Immediate risk)
  5. Defect foundCorrection notice(Document fix)
  6. Final compliantCO(Occupancy)
  7. Question asks scopeIRC chapter(Find authority)
  8. Local conflictJurisdiction rule(Local controls)

Project Admin

AHJ
Code authority
Approved plans
Inspection baseline
Permit
Work authorization
Inspection report
Field record
Correction notice
Defect direction
Stop work
Unsafe halt
CO
Occupancy approval

Building Planning

Townhouse limit
Three stories
Unit separation
Rated assembly
Site plan
Location check
Grade slope
Drain from foundation
Flood elevation
Local/FEMA check
Room area
Minimum floor area
Light/vent
Opening compliance

Anchor Bolts

Half, seven, six, twelve

1/2 in bolt7 in embed6 ft spacing12 in ends

Dampproof vs Waterproof

Dampproof

  • Moisture resistance
  • Damp soil
  • Basic coating

Waterproof

  • Water pressure
  • Hydrostatic risk
  • Stronger system

Dampness vs water pressure

Code Table Picker

  1. Footing sizeSoil/load table
  2. Foundation wallBackfill table
  3. Joist spanSpan table
  4. Header sizeHeader table
  5. Rafter spanRafter table
  6. Sheathing fastenersFastening schedule
  7. Concrete strengthWeathering table
  8. Roof coveringSlope table

Foundation Core

Frost depth
Below frost line
Footing width
Use load table
Footing drains
Basement/crawlspace drainage
Wall thickness
Backfill-driven table
Unbalanced fill
Wall design cue
Dampproofing
Moisture resistance
Waterproofing
Hydrostatic protection
Backfill brace
Support before fill

Concrete and Anchors

Slab thickness
3-1/2 in
Base course
4 in fill
Concrete strength
Weathering table
Anchor diameter
1/2 in min
Anchor embed
7 in min
Anchor spacing
6 ft max
End distance
12 in max
Lap splice
40 bar diameters

Joist Cuts

Thirds rule cuts, two-inch edge

1/3 maxNo middle notches2 in edgeCheck engineered

Bearing vs Span

Bearing

  • Support length
  • Load transfer
  • End condition

Span

  • Clear distance
  • Table lookup
  • Species/load dependent

Resting length vs distance

Floor Framing

Lumber grade
Marking required
Joist span
Species/grade table
Wood bearing
1-1/2 in
Masonry bearing
3 in
Notch depth
1/3 max
Middle third
No notches
Bored holes
2 in edge
Sill plate
Preservative-treated

Floor Systems

Engineered joists
Manufacturer drawings
Subfloor
Thickness/span grade
Decking
Fastener schedule
Crawl access
Opening required
Crawl vent
Screened ventilation
Draftstops
Concealed-space blocks
Decay risk
Moisture contact

Bracing vs Sheathing

Bracing

  • Lateral resistance
  • Wall line
  • Load path

Sheathing

  • Panel material
  • Thickness/fasteners
  • May brace

Function vs material

Wall Framing

Stud spacing
Table condition
Load path
Loads to foundation
Header span
Opening/load table
Steel studs
Marking compliance
Wall bracing
Lateral resistance
Fireblocking
Vertical fire stops
Garage separation
Gypsum barrier
Safety glazing
Label required

Wall Coverings

WRB
Water-resistive barrier
Sheathing
Thickness/fasteners
Veneer support
Anchorage/backing
Siding clearance
Above grade
Stucco lath
Fastened support
Shower walls
Approved finish
Masonry grout
Where required
Mortar joints
Thickness check

Rafter vs Truss

Rafter

  • Field framed
  • Span table
  • Collar ties

Truss

  • Engineered assembly
  • Approved drawings
  • No field cuts

Prescriptive vs engineered

Roof and Ceiling

Attic access
Opening required
Attic vent
Net free area
Rafter span
Species/load table
Rafter bearing
Support required
Collar ties
Uplift restraint
Trusses
Approved drawings
Roof sheathing
8d schedule
Flashing
Water diversion
Roof slope
Covering limit
Chimney clearance
Combustible separation

Egress Window

20 wide, 24 high, 44 sill

20 in width24 in height44 in sill5.7 sq ft

Guard vs Handrail

Guard

  • Fall prevention
  • Open side
  • Sphere limits

Handrail

  • Grip support
  • Along stair
  • Height range

Block fall vs grip

Safety Picker

  1. Sleeping roomEERO(Escape/rescue)
  2. Open side highGuard(Fall risk)
  3. Stair walkingHandrail(Graspable)
  4. Bedroom levelSmoke alarm
  5. Fuel applianceCO alarm
  6. Garage attachedCO alarm
  7. Hazardous glazingSafety glazing
  8. Concealed chaseFireblocking

Egress and Stairs

Hall width
36 in
Max riser
7-3/4 in
Min tread
10 in
Headroom
6 ft 8 in
Max flight
12 ft 3 in
Landing depth
36 in
EERO sill
44 in max
EERO area
5.7 sq ft

Stair Numbers

Seven-three-quarter up, ten across

Riser maxTread minHeadroom 6-8Flight 12-3

Public Safety

Smoke alarms
Bedrooms/levels
CO alarms
Fuel/garage trigger
Cooking offset
10 ft preferred
Deck guard
Over 30 in
Guard height
36 in surface
Stair guard
34 in min
Baluster opening
4 in sphere
Triangle opening
6 in sphere
Handrail grip
Graspable profile

Common Traps

Grade vs normal EERO

Grade allows 5.0 Above needs 5.7

Stair guard vs deck guard

Stair guard 34 Deck guard 36

Wood vs masonry bearing

Wood bearing 1-1/2 Masonry bearing 3

Permit vs inspection

Permit authorizes work Inspection verifies work

Rafter vs truss cuts

Rafters table-driven Trusses need approval

Dampproof vs drain

Coating resists moisture Drain relieves water

Last Minute

  1. 1.Weights: 4,8,16,14,27,14,17
  2. 2.B1: 60 questions, 2 hours
  3. 3.Open book: know tables
  4. 4.IRC scope: dwellings/townhouses/accessory
  5. 5.EERO: 20x24, 44 sill
  6. 6.Stairs: 7-3/4 riser, 10 tread
  7. 7.Anchor bolts: 1/2, 7, 6
  8. 8.Joists: no middle-third notches
  9. 9.Guards: 30 trigger, 36 high
  10. 10.Final compliant: issue CO
Same family resources

Explore More ICC Certifications

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.