4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements

Key Takeaways

  • Required input to an operation is its required good output divided by (1 − scrap fraction), applied backward from the last operation to the first.

  • The number of machines needed is F = S × Q ÷ (E × H × R), where S is standard hours per unit, Q is units processed per period, E is efficiency, H is available hours per machine, and R is reliability or availability.

  • Fractional machine results are rounded up unless overtime, subcontracting, or a shared machine can cover the fraction; the rounding decision is part of the capacity plan.

  • Operators required equal total standard labor hours divided by (available hours per worker × efficiency), then increased for absenteeism.

  • Setup time consumes capacity: machine hours per period = setups × setup time + units × run time, so smaller lots raise machine requirements unless setups are reduced.

Last updated: October 2026

4.3 Capacity Analysis: Machine and Personnel Requirements

Facilities planning starts with a capacity question: how many machines and people does the production plan require? The answer sets the floor space in the space-requirement models, the number of material handling moves, and the budget. The NCEES specification lists "calculation of personnel requirements" and "calculation of machine requirements" under capacity analysis.


1. Step One: Work Backward Through Scrap

Every operation loses some units to scrap. To deliver OkO_k good units from operation kk with scrap fraction dkd_k, the operation must start with:

Ik=Ok1−dkI_k = \frac{O_k}{1 - d_k}

The input to operation kk is the required output of operation k−1k - 1, so the calculation runs backward from the final operation.

Example: A plant must ship 1,000 good shafts per day. The routing has three operations:

OperationScrap rateRequired good outputRequired input
30 Grind5%1,0001,000 ÷ 0.95 = 1,052.6
20 Mill2%1,052.61,052.6 ÷ 0.98 = 1,074.1
10 Turn4%1,074.11,074.1 ÷ 0.96 = 1,118.9

The plant must start about 1,119 blanks per day. The overall yield is 0.96×0.98×0.95=0.8940.96 \times 0.98 \times 0.95 = 0.894, and 1,000/0.894=1,1191{,}000 / 0.894 = 1{,}119 gives the same answer. Note that you divide by (1−d)(1 - d); multiplying 1,000 by 1.05 understates the need, because 5% of the larger input is also lost.


2. Step Two: Machine Requirements

A common facilities-planning form of the machine requirement is:

F=S⋅QE⋅H⋅RF = \frac{S \cdot Q}{E \cdot H \cdot R}

SymbolMeaning
FFNumber of machines required (before rounding)
SSStandard time per unit (hours)
QQUnits the operation must process per period (its input, from Step 1)
EEEfficiency: actual performance relative to standard
HHHours available per machine per period (shifts × hours per shift)
RRReliability: the fraction of available time the machine is not down for failures

Example (Operation 20, milling): S=0.12S = 0.12 hr per unit, Q=1,074.1Q = 1{,}074.1 units per day, E=0.90E = 0.90, two 8-hour shifts so H=16H = 16 hr, and R=0.95R = 0.95:

F=0.12×1,074.10.90×16×0.95=128.913.68=9.42 machinesF = \frac{0.12 \times 1{,}074.1}{0.90 \times 16 \times 0.95} = \frac{128.9}{13.68} = 9.42 \text{ machines}

Rounding. Ten machines cover the load with about 6% spare capacity. Nine machines would need roughly 6% overtime or a third shift on some machines. On an exam, round up unless the problem allows overtime or subcontracting. In design work, compare the cost of a tenth machine against overtime premiums.

Including Setup Time

When an operation runs several products or lots, setups consume machine time:

Machine hours required=∑j(nj⋅tsetup,j+Qj⋅trun,j)\text{Machine hours required} = \sum_j \left( n_j \cdot t_{\text{setup},j} + Q_j \cdot t_{\text{run},j} \right)

where njn_j is the number of setups for product jj in the period. Divide by E⋅H⋅RE \cdot H \cdot R to get machines. Cutting lot sizes in half doubles the number of setups. Without setup reduction, smaller lots increase the machines required, which is the capacity side of the JIT tradeoff.

Example: A press runs two parts per week. Part X needs 4 setups of 1.5 hr and 6,000 pieces at 0.01 hr each. Part Y needs 6 setups of 2 hr and 3,000 pieces at 0.02 hr each. Machine hours =4(1.5)+60+6(2)+60=138= 4(1.5) + 60 + 6(2) + 60 = 138 hours. With H=80H = 80 hr per week, E=0.95E = 0.95, and R=0.92R = 0.92, F=138/69.9=1.97F = 138 / 69.9 = 1.97, so two presses are needed.


3. Step Three: Personnel Requirements

Direct Labor for Manual Operations

Operators=∑(units×standard hours per unit)productive hours per worker×efficiency×11−absenteeism\text{Operators} = \frac{\sum (\text{units} \times \text{standard hours per unit})}{\text{productive hours per worker} \times \text{efficiency}} \times \frac{1}{1 - \text{absenteeism}}

Example: A manual assembly area must build 1,200 units per day at a standard of 0.40 hr per unit (allowances already included). Each worker has 7.5 productive hours per shift and works at 95% efficiency, and absenteeism averages 5%.

1,200×0.407.5×0.95=4807.125=67.4 workers present,67.40.95=70.9⇒71 on the roster\frac{1{,}200 \times 0.40}{7.5 \times 0.95} = \frac{480}{7.125} = 67.4 \text{ workers present}, \qquad \frac{67.4}{0.95} = 70.9 \Rightarrow 71 \text{ on the roster}

Machine Operators

For automated equipment, staffing depends on how many machines one person can tend. That comes from worker–machine (man–machine) analysis, covered in the methods engineering chapter. If each operator can tend three machines, ten mills need four operators per shift (10 ÷ 3 rounded up), not ten.

Indirect and Support Staff

Material handlers, setup technicians, inspectors, and maintenance staff are sized from their own workloads: moves per shift times minutes per move, setups per week times setup hours, and so on. Support staffing is often checked against ratios from comparable plants.


4. Capacity Concepts That Tie It Together

  • Design capacity is the maximum output under ideal conditions. Effective capacity allows for setups, maintenance, and product mix. Actual output is what is achieved.
  • A capacity cushion (planned spare capacity) protects against demand variability and breakdowns. Queueing theory shows that waiting time rises sharply as utilization nears 100%, so do not plan machines at 100% load.
  • The machine count for each operation reveals the bottleneck: the operation with the highest load relative to its capacity sets plant throughput.
MistakeCorrect approach
Using shipped quantity at every operationUse the input each operation must process, after downstream scrap
Multiplying by (1+d)(1 + d) for scrapDivide by (1−d)(1 - d)
Ignoring setup hoursAdd setups × setup time to run time
Rounding 9.42 machines down to 9Round up unless overtime or outsourcing is allowed
Forgetting absenteeismDivide workers present by (1−absenteeism rate)(1 - \text{absenteeism rate})
Test Your Knowledge

A product passes through two operations: stamping (scrap 6%) followed by painting (scrap 3%). The plan requires 2,000 good painted parts per week. How many blanks must enter stamping each week?

A

2,180

B

2,200

C

2,194

D

2,120

Test Your Knowledge

An operation must process 3,600 units per week at a standard time of 0.05 hr per unit. Each machine is scheduled 80 hours per week, operates at 92% efficiency, and has 90% reliability. How many machines are required?

A

2 machines

B

3 machines

C

4 machines

D

5 machines

Test Your Knowledge

An assembly area requires 960 standard hours of manual work per day. Workers have 7.5 productive hours per shift at 100% efficiency, and absenteeism averages 4%. How many workers should be on the roster?

A

128

B

134

C

133

D

139

Sections you finish are checked off in the contents.