8.6 Cofferdams, Underpinning & Adjacent Infrastructure Effects
Key Takeaways
- Cellular cofferdams develop stability primarily from the shear strength and unit weight of the cell fill, not from cantilever bending of the sheet piles alone.
- Unwatered cofferdams on permeable foundations must satisfy piping/uplift FS = i_cr / i_exit, commonly targeting FS ≥ 1.5 at the embedded toe exit gradient.
- Underpinning options—needle-and-pit, piled, jet-grout, and micropile systems—are selected from residual capacity needs, access constraints, and settlement tolerance of the supported structure.
- Adjacent excavation and underpinning settlement risk is managed by monitoring angular distortion and keeping induced movements within serviceability limits for nearby foundations and utilities.
Cofferdam Types and Function
A cofferdam is a temporary watertight (or substantially water-resistant) enclosure that permits excavation, foundation construction, or repair work to proceed in the dry, typically at a bridge pier, waterfront structure, or below-grade facility with a high groundwater table.
- Braced sheet-pile cofferdams: Single-wall interlocking steel sheet piles driven around the work area and internally braced with walers and struts (or externally anchored), analogous in structural behavior to a braced excavation but designed additionally for hydrostatic and wave/current loading on the exposed wall.
- Cellular cofferdams: Used for larger, deeper, or open-water applications (e.g., dry docks, large pier foundations) where internal bracing is impractical. Interlocking sheet piles are driven into circular cells (independent, self-stable circular cells connected by smaller connecting arcs) or diaphragm cells (straight diaphragm walls connecting circular arcs, used for elongated footprints), then filled with compacted granular material. Stability derives from the cell fill's internal friction and unit weight resisting overturning and sliding — much like a gravity retaining structure — while sheet-pile interlock tension must be checked against manufacturer allowable interlock strength.
- Double-wall cofferdams: Two parallel rows of sheet piles tied together and filled with granular soil between them, used where a single cellular cofferdam's minimum practical diameter cannot fit the site.
Unwatering and Bottom Stability
Once enclosed, the cofferdam interior is pumped dry ("unwatered"). Two geotechnical failure modes govern bottom stability when a hydraulic head differential exists across the embedded sheet-pile toe:
Piping/heave beneath the toe: Seepage flows beneath and around the embedded sheet-pile cutoff from the high-head (river/bay) side toward the low-head (dry excavation) side. If the upward exit gradient at the excavation-side toe approaches the soil's critical gradient, a "sand boil" or general heave/piping failure can occur, rapidly flooding the enclosure. A simplified screening check uses:
with the exit gradient approximated for a single sheet-pile cutoff of embedment depth $D$ beneath the excavation base and differential head $\Delta h$ as $i_{exit} \approx \Delta h / (2D)$ (a simplified flow-net approximation; project-specific work uses a full flow-net or seepage software solution). A minimum $FS \ge 1.5$ is typically targeted; if the check fails, embedment is increased, relief wells are installed on the dry side to reduce excess head, or a positive cutoff into an underlying low-permeability stratum is pursued.
General basal heave (cohesive soils): Where the cofferdam bottom is in soft clay, unrelieved weight of the retained soil/water column outside the cofferdam can push the excavation bottom upward, following the same bearing-capacity-based heave mechanism used for deep braced excavations — checked against the retained soil's undrained shear strength and the excavation depth/width geometry.
Underpinning Methods
Underpinning transfers an existing foundation's load path to a new, deeper, or higher-capacity bearing element, typically to permit adjacent excavation, correct settlement/distress, or accommodate increased loads.
| Method | Mechanism | Typical Use Case |
|---|---|---|
| Pit (needle-and-pit) underpinning | Sequential hand-excavated pits beneath the existing footing, poured in short alternating sections (traditional "pin and pit" sequencing) down to a new, deeper bearing level | Shallow to moderate depth increases; masonry/light structures; limited equipment access |
| Piled underpinning | New piles (mini-piles, driven or drilled) installed adjacent to or through the existing footing, with needle beams or brackets transferring load from the footing to the new piles | Larger load transfer; deeper competent strata; can be installed with minimal excavation |
| Jet grouting | High-pressure grout jets erode and mix native soil in place, forming grout-soil columns beneath or around the footing that both improve ground and directly support load | Soft/loose soils, tight access, need for combined support + groundwater cutoff |
| Micropiles | Small-diameter ($100$–$300\text{ mm}$), high-capacity drilled and grouted piles, installable with low-headroom, low-vibration equipment | Historic/sensitive structures, restricted access basements, seismic retrofit underpinning |
Settlement Risk to Adjacent Infrastructure
Nearby excavation, dewatering, cofferdam installation, or underpinning sequencing can induce settlement in adjacent structures through ground loss (sheet-pile installation/extraction, jet-grout spoil return), stress relief (excavation unloading), or dewatering-induced consolidation. Risk is managed by:
- Defining a zone of influence around the work (often approximated as extending outward from the excavation base at roughly $1\text{H}{:}1\text{V}$, refined per project soil conditions) and identifying all structures/utilities within it.
- Establishing angular distortion and differential settlement limits for each affected structure — commonly $1/500$ for masonry-bearing-wall structures and looser limits (e.g., $1/300$) for steel/concrete frames — as monitoring "alert" and "limit" thresholds, not just a post-construction check.
- Continuous instrumentation: precise optical/laser survey of settlement points, tiltmeters on facades, crack monitors across existing distress, and (for dewatering-driven risk) piezometers to confirm drawdown stays within predicted limits.
- Sequencing underpinning or jet-grout work in short, alternating, non-adjacent segments to avoid simultaneously de-supporting long lengths of an existing footing.
Worked Numerical Example: Cofferdam Piping Factor of Safety
Problem Statement A braced sheet-pile cofferdam is installed for a bridge pier footing in a river with a design differential head of $\Delta h = 6\text{ m}$ between the river water surface and the dry excavation floor. The sheet piles are embedded $D = 4\text{ m}$ below the excavation base into a medium-dense sand with $G_s = 2.65$ and void ratio $e = 0.60$. Evaluate the factor of safety against piping at the toe.
Solution
Step 1 — Critical hydraulic gradient:
Step 2 — Approximate exit gradient at the toe:
Step 3 — Factor of safety:
Step 4 — Evaluate: $FS = 1.37$ is below the typical target of $1.5$, indicating an unacceptable piping risk at the design embedment. Increasing embedment to $D = 5\text{ m}$ reduces $i_{exit}$ to $6/(2\times5) = 0.60$, raising $FS$ to $1.03/0.60 = 1.72 \ge 1.5$ — an acceptable design revision — or, alternatively, relief wells could be installed on the excavation side to lower the effective differential head.
An unwatered sheet-pile cofferdam has differential head H = 6.0 m and sheet-pile embedment D = 4.0 m below the excavation grade in a pervious sand with i_cr = 1.03. Using the approximate exit-gradient screen i_exit ≈ H/(2D), what is the factor of safety against piping?
Which statement best distinguishes a cellular cofferdam from a simple cantilever sheet-pile wall?
An existing building footing must be deepened beneath a live column with limited headroom and strict settlement limits for adjacent slabs. Which underpinning approach is often preferred?