4.3 Three-Phase Transformer Connections, Phase Shifts & Paralleling

Key Takeaways

  • The four primary three-phase transformer configurations (Delta-Delta, Wye-Wye, Delta-Wye, Wye-Delta) exhibit unique voltage ratios, third-harmonic containment mechanisms, and grounding capabilities.
  • In an Open-Delta (V-V) bank formed by removing one unit from a Delta-Delta bank, the maximum continuous three-phase power capacity is reduced to 57.7% (1 / sqrt(3)) of the original bank rating, or 86.6% of the sum of the two remaining single-phase units.
  • Wye-Wye (Y-Y) configurations without a tertiary delta winding suffer from neutral point instability, severe third-harmonic voltage distortion (due to lack of a closed circulating path for third-harmonic magnetizing currents), and phase-to-ground overvoltages under unbalanced loading.
  • Standard ANSI/IEEE Delta-Wye (Δ-Y) step-up and Wye-Delta (Y-Δ) step-down connections introduce a 30° phase displacement, where the low-voltage (LV) line-to-line voltage lags the high-voltage (HV) line-to-line voltage by 30° (standard Dyn1 convention).
  • Paralleling transformers requires identical turns ratios, identical frequency, identical vector group / phase angle displacement (0° cannot parallel with 30°), identical polarity, and inversely proportional per-unit impedances on their own bases to ensure proportional load sharing without circulating currents.
Last updated: August 2026

4.3 Three-Phase Transformer Connections, Phase Shifts & Paralleling

Executive Overview: Three-phase transformers serve as the foundational junctions of high-voltage transmission, sub-transmission, and commercial distribution networks. Whether realized as a monolithic three-phase core-and-coil assembly or as a bank of three individual single-phase transformers, the selected winding configuration (Delta or Wye) dictates system grounding, fault current magnitude, harmonic propagation, and phase angle displacement. On the NCEES PE Power examination, engineers must master the operational characteristics of standard connections, evaluate Open-Delta emergency capacity, interpret ANSI/IEEE $30^\circ$ phase shifts, and execute multi-transformer parallel load sharing calculations.


1. Operational Analysis of Standard Three-Phase Connections

THE FOUR PRIMARY THREE-PHASE TRANSFORMER TOPOLOGIES:

1. DELTA-DELTA (Δ-Δ)                   2. WYE-WYE (Y-Y)
      A o---+                               A o---( ( (---+ 
            |                                             |
          ( ( (                                         ( ( ( 
          ( ( (                                         ( ( ( 
            |                                             | 
      B o---+                               B o---( ( (---+--- N (Neutral)
            |                                             | 
          ( ( (                                         ( ( ( 
          ( ( (                                         ( ( ( 
            |                                             | 
      C o---+                               C o---( ( (---+

3. DELTA-WYE (Δ-Y)                     4. WYE-DELTA (Y-Δ)
      Primary (Δ)     Secondary (Y)               Primary (Y)     Secondary (Δ)
      A o---+           a o---( ( (                 A o---( ( (         a o---+
            |                     |                               |           |
          ( ( (                 ( ( (                           ( ( (       ( ( (
            |           b o---( ( (---+-- n (Neutral)             |           |
      B o---+                     |                 B o---( ( (---+     b o---+
            |                   ( ( (                             |           |
          ( ( (                   |                             ( ( (       ( ( (
            |           c o---( ( (                 C o---( ( (---+           |
      C o---+                                                           c o---+

Comprehensive Configuration Comparison

ConnectionVoltage Ratio ($V_{LL,1} / V_{LL,2}$)Standard Phase ShiftKey Engineering AdvantagesCritical Disadvantages / Limitations
Delta-Delta ($\Delta$-$\Delta$)$a = \frac{N_1}{N_2}$$0^\circ$- Traps 3rd harmonics in closed delta.<br>- High current capacity.<br>- Continues operating in Open-Delta if 1 unit fails.- No neutral point available for system grounding.<br>- Higher insulation cost for high-voltage transmission.
Wye-Wye ($\text{Y}$-$\text{Y}$)$a = \frac{N_1}{N_2}$$0^\circ$- Reduced insulation stress ($V_{ph} = V_{LL}/\sqrt{3}$).<br>- Provides neutral for grounding on both sides.- Severe 3rd harmonic voltage distortion.<br>- Neutral instability under unbalanced loads without tertiary delta.
Delta-Wye ($\Delta$-$\text{Y}$)$\frac{a}{\sqrt{3}} = \frac{N_1}{\sqrt{3} N_2}$$30^\circ$ (LV lags HV)- Industry Standard Step-Up at Generators.<br>- Industry Standard Step-Down for Distribution.<br>- Solid neutral for 4-wire loads ($480\text{Y}/277\text{ V}$).- $30^\circ$ phase shift prevents direct paralleling with $\Delta$-$\Delta$ or $\text{Y}$-$\text{Y}$ banks.
Wye-Delta ($\text{Y}$-$\Delta$)$\sqrt{3} a = \frac{\sqrt{3} N_1}{N_2}$$30^\circ$ (LV lags HV)- Standard Transmission Substation Step-Down.<br>- Grounded neutral on HV transmission side.- $30^\circ$ phase displacement.<br>- Unbalanced loads can cause circulating currents in delta secondary.

2. The Open-Delta (V-V) Connection & Derivation

If one single-phase transformer in a balanced three-phase Delta-Delta bank suffers a dielectric failure or requires maintenance, the defective unit can be removed, allowing the remaining two transformers to operate in the Open-Delta (or V-V) configuration to maintain three-phase service.

OPEN-DELTA (V-V) BANK SCHEMATIC:
          Line A o----------------+-----------------------o Line a
                                  |                       
                                ( ( ( Unit A-B            
                                ( ( ( (Phase V_ab)        
                                  |                       
          Line B o----------------+-----------------------o Line b
                                  |                       
                                ( ( ( Unit B-C            
                                ( ( ( (Phase V_bc)        
                                  |                       
          Line C o----------------+-----------------------o Line c
                 [ Unit C-A Removed / Disconnected ]

Mathematical Derivation of Power Capacity

In a standard Delta-Delta bank of three identical single-phase transformers of rating $S_{unit} = V_{ph} I_{ph}$: SΔΔ=3VphIph=3SunitS_{\Delta-\Delta} = 3 V_{ph} I_{ph} = 3 S_{unit} When converted to Open-Delta, the line voltage remains $V_L = V_{ph}$, but the line current flowing into the load is limited by the continuous current rating of the transformer windings ($I_{L,\max} = I_{ph,rated}$): SVV=3VLIL,max=3VphIph=3SunitS_{V-V} = \sqrt{3} V_L I_{L,\max} = \sqrt{3} V_{ph} I_{ph} = \sqrt{3} S_{unit}

  1. Capacity relative to the original 3-unit $\Delta$-$\Delta$ bank: SVVSΔΔ=3Sunit3Sunit=130.57735    57.74%\frac{S_{V-V}}{S_{\Delta-\Delta}} = \frac{\sqrt{3} S_{unit}}{3 S_{unit}} = \frac{1}{\sqrt{3}} \approx 0.57735 \implies 57.74\%
  2. Bank Utilization Factor relative to the 2 remaining units: Utilization Factor=SVV2Sunit=3Sunit2Sunit=320.86603    86.60%\text{Utilization Factor} = \frac{S_{V-V}}{2 S_{unit}} = \frac{\sqrt{3} S_{unit}}{2 S_{unit}} = \frac{\sqrt{3}}{2} \approx 0.86603 \implies 86.60\%

Operating Power Factors of the Two Open-Delta Units

Even when supplying a balanced three-phase load at power factor $\cos\theta$:

  • Unit 1 operates at power factor: $PF_1 = \cos(\theta - 30^\circ)$
  • Unit 2 operates at power factor: $PF_2 = \cos(\theta + 30^\circ)$

Exam Trap: At a load power factor of $0.866$ lagging ($\theta = 30^\circ$), Unit 1 operates at unity power factor ($PF_1 = \cos(0^\circ) = 1.0$), while Unit 2 operates at $PF_2 = \cos(60^\circ) = 0.50$ lagging, delivering only half the real power of Unit 1 despite carrying identical current magnitudes!


3. Harmonic Dynamics & The Role of Tertiary Delta Windings

Because the magnetic $B-H$ magnetization curve of transformer iron is non-linear, maintaining a sinusoidal core flux requires a non-sinusoidal magnetizing current containing a pronounced third-harmonic ($180\text{ Hz}$ in 60 Hz systems) component ($I_{3h} \approx 30% - 40%$ of fundamental magnetizing current).

THIRD-HARMONIC CIRCULATING PATH IN TERTIARY DELTA:
                 Wye Primary             Tertiary Delta (3rd Harmonic Trap)         Wye Secondary
              A o---( ( (---+                      +----( ( (----+                     a o---( ( (---+
                            |                      |    Phase a3 |                                   |
              B o---( ( (---+--- N                 |             |                     b o---( ( (---+--- n
                            |                      +----( ( (----+                                   |
              C o---( ( (---+                      |    Phase b3 |                     c o---( ( (---+
                                                   |             |
                                                   +----( ( (----+ 
                                                        Phase c3   
                                                *I_3h circulates inside closed Δ!

Third-Harmonic Phenomenon in Wye-Wye Systems

  1. In a 3-wire ungrounded Wye-Wye bank, third-harmonic currents cannot flow because they are co-phasal (zero-sequence) and sum to $3 I_{3h} \ne 0$ at the isolated neutral, violating KCL.
  2. Suppressing the third-harmonic magnetizing current forces the core magnetic flux $\phi(t)$ to become flat-topped, which by Faraday's Law induces severe third-harmonic voltages ($e = -N d\phi/dt$) in the phase windings.
  3. These harmonic voltages cause the neutral point to oscillate at $180\text{ Hz}$ with peak phase-to-ground voltages exceeding $\sqrt{3}$ times normal, subjecting winding insulation to destructive dielectric overstresses and generating severe telecommunication interference.

The Tertiary Delta Solution

Large high-voltage transmission Wye-Wye autotransformers and power transformers incorporate a closed Tertiary Delta Winding (typically rated at $13.8\text{ kV}$ and $33%$ of main MVA capacity). The closed delta provides a short-circuit zero-impedance circulating path for third-harmonic currents ($I_{3h}$), trapping them inside the mesh, restoring sinusoidal core flux, stabilizing the system neutral, and providing an auxiliary station service bus.


4. Phase Shift Standards & Vector Group Classifications

Standard three-phase transformer connections introduce systematic phase angle displacements between primary and secondary terminals.

ANSI/IEEE vs. IEC Standard Phase Displacement

  • ANSI/IEEE C57.12 Standard: For Delta-Wye and Wye-Delta transformers, the high-voltage (HV) line-to-line voltage leads the low-voltage (LV) line-to-line voltage by $30^\circ$ (or equivalently, the LV voltage lags the HV voltage by $30^\circ$).
  • Vector Group Clock Notation (IEC 60076):
    • High-Voltage phasor is fixed at the 12 o'clock ($0^\circ$) reference position.
    • Low-Voltage phasor position corresponds to the clock hour hand (each hour represents a $30^\circ$ lag):
      • Dyn1 / Yd1: LV is at 1 o'clock $\implies$ LV lags HV by $1 \times 30^\circ = 30^\circ$ (ANSI/IEEE Standard).
      • Dyn11 / Yd11: LV is at 11 o'clock $\implies$ LV leads HV by $30^\circ$ (lags by $330^\circ$).
      • Dd0 / Yy0: LV is at 12 o'clock $\implies 0^\circ$ phase shift.
      • Dd6 / Yy6: LV is at 6 o'clock $\implies 180^\circ$ phase shift (inverted polarity).
VECTOR GROUP CLOCK FACE DISPLACEMENT:
                              12 (0° / 360°)
                               [ Dd0 / Yy0 ]
                                     ^
                   11 (30° Lead)     |     1 (30° Lag)
                  [ Dyn11 / Yd11 ]   |    [ Dyn1 / Yd1 ] <--- ANSI/IEEE Standard!
                           \         |         /
                            \        |        /
                             \       |       /
               9 (90° Lead)   +------+------+   3 (90° Lag)
                                     |
                                     |
                                     v
                                [ Dd6 / Yy6 ]
                                6 (180° Shift)

5. Parallel Operation of Three-Phase Transformers

To expand substation capacity or improve service reliability, transformers are frequently connected in parallel across common primary and secondary buses.

PARALLEL TRANSFORMER INSTALLATION SCHEMATIC:
                     Primary High-Voltage Bus (V1)
       o---------------------------+---------------------------o
                                   |                           
                         +---------+---------+                 
                         |                   |                 
                   Transformer A       Transformer B           
                   [ S_rA, Z_puA ]     [ S_rB, Z_puB ]         
                         |                   |                 
                         +---------+---------+                 
                                   |                           
       o---------------------------+---------------------------o
                     Secondary Low-Voltage Bus (V2)
                                   |
                                   v Load (S_load)

Mandatory Conditions for Parallel Operation

To prevent catastrophic short-circuits, circulating currents, or severe thermal overloading, parallel transformers must satisfy the following criteria:

  1. Identical Voltage Ratios and Turns Ratios: Nominal primary and secondary voltage ratings must match exactly.
  2. Identical Frequency: Must operate on the same system frequency ($60\text{ Hz}$).
  3. Identical Vector Group and Phase Displacement: A $0^\circ$ bank (e.g., $\Delta$-$\Delta$) CANNOT be paralleled with a $30^\circ$ bank (e.g., $\Delta$-$\text{Y}$). Paralleling across a $30^\circ$ phase displacement creates a net terminal voltage difference $\Delta V = 2 V_{rated} \sin(15^\circ) = 0.5176 V_{rated}$, driving catastrophic short-circuit currents through the windings.
  4. Identical Polarity: Relative polarities of matching phases must align ($H_1$ to $H_1$, $X_1$ to $X_1$).
  5. Proportional Per-Unit Impedances ($Z_{pu}$): Per-unit impedances on their own individual MVA bases must be equal ($Z_{pu,A} = Z_{pu,B}$ on their respective bases) so that each transformer shares total load in exact proportion to its rated capacity.
  6. Equal $X/R$ Ratios: Prevents phase angle differences between branch currents, ensuring currents add algebraically rather than in quadrature.

Mathematical Formulation of Parallel Load Sharing

When two transformers $A$ and $B$ operate in parallel feeding a common total complex load $\mathbf{S}_{load}$:

SA=Sload×YAYA+YB=Sload×ZBZA+ZB\mathbf{S}_A = \mathbf{S}_{load} \times \frac{\mathbf{Y}_A}{\mathbf{Y}_A + \mathbf{Y}_B} = \mathbf{S}_{load} \times \frac{\mathbf{Z}_B}{\mathbf{Z}_A + \mathbf{Z}_B}

Expressing in per-unit impedances referred to a common system base $S_{base}$:

Zpu,A,sys=Zpu,A,own×(SbaseSrated,A),Zpu,B,sys=Zpu,B,own×(SbaseSrated,B)\mathbf{Z}_{pu,A,\text{sys}} = \mathbf{Z}_{pu,A,\text{own}} \times \left(\frac{S_{base}}{S_{rated,A}}\right), \quad \mathbf{Z}_{pu,B,\text{sys}} = \mathbf{Z}_{pu,B,\text{own}} \times \left(\frac{S_{base}}{S_{rated,B}}\right) SA=Sload×Srated,A/Zpu,A,ownSrated,AZpu,A,own+Srated,BZpu,B,own\mathbf{S}_A = \mathbf{S}_{load} \times \frac{\mathbf{S}_{rated,A} / \mathbf{Z}_{pu,A,\text{own}}}{\frac{\mathbf{S}_{rated,A}}{\mathbf{Z}_{pu,A,\text{own}}} + \frac{\mathbf{S}_{rated,B}}{\mathbf{Z}_{pu,B,\text{own}}}}

Circulating Current from Voltage Mismatch

If secondary no-load voltages $\mathbf{V}_A$ and $\mathbf{V}B$ differ (due to tap mismatch or ratio error), a continuous **circulating current $\mathbf{I}{circ}$** circulates around the local secondary loop even at zero external load:

Icirc=VAVBZA,Ω+ZB,Ω\mathbf{I}_{circ} = \frac{\mathbf{V}_A - \mathbf{V}_B}{\mathbf{Z}_{A,\Omega} + \mathbf{Z}_{B,\Omega}}

This current superimposes onto load current, thermally overloading one unit while underutilizing the other.


6. Comprehensive Step-by-Step Worked Mathematical Example

Problem Scenario

Two three-phase, $13.8\text{ kV} / 480\text{ V}$ (line-to-line), $60\text{ Hz}$, Delta-Delta transformers are connected in parallel to supply a shared balanced three-phase industrial load of $1200\text{ kVA}$ at $0.85$ power factor lagging:

  • Transformer A: $800\text{ kVA}, \quad Z_{pu,A} = 0.045\angle 75^\circ\text{ pu}$ (on its own $800\text{ kVA}$ base)
  • Transformer B: $500\text{ kVA}, \quad Z_{pu,B} = 0.055\angle 65^\circ\text{ pu}$ (on its own $500\text{ kVA}$ base)

Calculate:

  1. The per-unit impedances of both transformers on a common system base of $S_{base} = 1000\text{ kVA}$.
  2. The complex power delivered by Transformer A ($\mathbf{S}_A$) and Transformer B ($\mathbf{S}_B$).
  3. The percent loading of each transformer and verify whether either unit is thermally overloaded.
  4. The maximum total load the parallel bank can supply without overloading either transformer.
  5. The no-load circulating current ($I_{circ}$) in the secondary circuit if Transformer A is tapped to deliver $485\text{ V}$ and Transformer B delivers $475\text{ V}$.
=========================================================================================
CALCULATION WORKFLOW & DETAILED STEP-BY-STEP SOLUTION:
=========================================================================================

Step 1: Convert Transformer Impedances to Common 1000 kVA Base
  Z_pu,A,sys = Z_pu,A * (S_base / S_rated,A) 
             = (0.045 /_ 75°) * (1000 / 800) 
             = 0.045 * 1.25 /_ 75°
             = 0.05625 /_ 75° pu

  Z_pu,B,sys = Z_pu,B * (S_base / S_rated,B)
             = (0.055 /_ 65°) * (1000 / 500)
             = 0.055 * 2.00 /_ 65°
             = 0.11000 /_ 65° pu

Step 2: Compute Admittances and Total Parallel Admittance
  Y_pu,A = 1 / Z_pu,A,sys = 1 / (0.05625 /_ 75°) = 17.7778 /_ -75° pu
         = 17.7778 * (cos(-75°) + j*sin(-75°))
         = 4.6012 - j17.1720 pu

  Y_pu,B = 1 / Z_pu,B,sys = 1 / (0.11000 /_ 65°) = 9.0909 /_ -65° pu
         = 9.0909 * (cos(-65°) + j*sin(-65°))
         = 3.8419 - j8.2392 pu

  Y_total = Y_pu,A + Y_pu,B
          = (4.6012 + 3.8419) - j(17.1720 + 8.2392)
          = 8.4431 - j25.4112 pu
  Polar Form of Y_total:
    |Y_total| = sqrt( 8.4431^2 + (-25.4112)^2 ) = sqrt( 71.2859 + 645.7291 ) = sqrt( 717.015 ) = 26.7771 pu
    theta_Y = arctan( -25.4112 / 8.4431 ) = -71.621°
    Y_total = 26.7771 /_ -71.621° pu

Step 3: Calculate Load Apportionment (S_load = 1200 kVA /_ 31.788°)
  Transformer A Load Sharing:
    S_A = S_load * ( Y_pu,A / Y_total )
        = (1200 /_ 31.788°) * [ (17.7778 /_ -75.0°) / (26.7771 /_ -71.621°) ]
        = 1200 * (17.7778 / 26.7771) /_ (31.788° - 75.0° + 71.621°)
        = 1200 * 0.663918 /_ 28.409°
        = 796.70 /_ 28.409° kVA
    Real Power A: P_A = 796.70 * cos(28.409°) = 700.7 kW (PF = 0.8796 lag)
    Reactive Power A: Q_A = 796.70 * sin(28.409°) = 379.0 kVAR

  Transformer B Load Sharing:
    S_B = S_load * ( Y_pu,B / Y_total )
        = (1200 /_ 31.788°) * [ (9.0909 /_ -65.0°) / (26.7771 /_ -71.621°) ]
        = 1200 * (9.0909 / 26.7771) /_ (31.788° - 65.0° + 71.621°)
        = 1200 * 0.339503 /_ 38.409°
        = 407.40 /_ 38.409° kVA
    Real Power B: P_B = 407.40 * cos(38.409°) = 319.3 kW (PF = 0.7836 lag)
    Reactive Power B: Q_B = 407.40 * sin(38.409°) = 253.1 kVAR

  Verification:
    P_total = 700.7 + 319.3 = 1020.0 kW = 1200 * 0.85 (CONFIRMED)
    Q_total = 379.0 + 253.1 = 632.1 kVAR = 1200 * sin(31.788°) (CONFIRMED)

Step 4: Check Transformer Capacity Loading
  Transformer A Loading: (796.70 kVA / 800.0 kVA) * 100% = 99.59%  (SAFE - Operating at 99.6% capacity)
  Transformer B Loading: (407.40 kVA / 500.0 kVA) * 100% = 81.48%  (SAFE - Operating at 81.5% capacity)
  Neither unit is overloaded!

Step 5: Compute Maximum Permissible Bank Load
  Transformer A reaches 100.0% full rating (800.0 kVA) first.
  S_load,max = 800.0 kVA / 0.663918 = 1204.97 kVA approx 1205 kVA
  (Note: The parallel bank can only supply 1205 kVA, less than the sum 800 + 500 = 1300 kVA, due to impedance mismatch!)

Step 6: Compute No-Load Secondary Circulating Current
  Secondary Line-to-Neutral Voltage Difference:
    V_an,A = 485 V / sqrt(3) = 280.015 V
    V_an,B = 475 V / sqrt(3) = 274.242 V
    Delta_V_LN = 280.015 - 274.242 = 5.773 V

  Ohmic Base Impedance (LV side, 480V, 1000 kVA base):
    Z_base,LV = (480)^2 / 1,000,000 = 0.2304 ohms

  Ohmic Impedances:
    Z_A,ohms = 0.05625 * 0.2304 /_ 75° = 0.01296 /_ 75° ohms = 0.00335 + j0.01252 ohms
    Z_B,ohms = 0.11000 * 0.2304 /_ 65° = 0.02534 /_ 65° ohms = 0.01071 + j0.02297 ohms
    Z_loop = Z_A,ohms + Z_B,ohms = 0.01406 + j0.03549 ohms = 0.03817 /_ 68.39° ohms

  Circulating Current Magnitude:
    I_circ = Delta_V_LN / |Z_loop| = 5.773 V / 0.03817 ohms = 151.25 A
=========================================================================================

7. Common Exam Traps & Tactical Pitfalls

  • Simple Summation of Parallel Capacities: Assuming two parallel transformers of ratings $S_A$ and $S_B$ can deliver $S_A + S_B$ without verifying per-unit impedance matching. If per-unit impedances differ, the lower per-unit impedance transformer carries disproportionate load and overloads before the other reaches full capacity.
  • Direct Addition of Impedances on Different Bases: Adding or comparing per-unit impedances without first converting them to a single common system MVA base.
  • Open-Delta Capacity Multiplier Confusion: Mixing up the $57.7%$ capacity factor ($1/\sqrt{3}$ of the original 3-unit bank) with the $86.6%$ utilization factor ($\sqrt{3}/2$ of the sum of the two remaining units).
  • Ignoring Phase Displacement in Paralleling: Attempting to parallel a Delta-Wye transformer ($30^\circ$ shift) with a Delta-Delta transformer ($0^\circ$ shift). The resulting $30^\circ$ voltage mismatch creates an instantaneous destructive short circuit.
Loading diagram...
Three-Phase Paralleling Verification and Load Sharing Logic
Test Your Knowledge

A three-phase Delta-Delta transformer bank consisting of three identical 50 kVA single-phase transformers supplies a balanced 150 kVA three-phase load. If one transformer fails and is completely removed to operate the system in Open-Delta (V-V), what is the maximum continuous balanced three-phase load the bank can deliver without overloading the remaining units?

A
B
C
D
Test Your Knowledge

An electrical engineer attempts to connect a 13.8 kV / 480 V Delta-Delta (Dd0) transformer in parallel with a 13.8 kV / 480 V Delta-Wye (Dyn1) transformer. Which statement correctly identifies the electrical consequence of this connection?

A
B
C
D
Test Your Knowledge

Two three-phase transformers, Transformer A (1000 kVA, Z_pu = 0.040 pu on 1000 kVA base) and Transformer B (500 kVA, Z_pu = 0.050 pu on 500 kVA base), operate in parallel to supply a 1200 kVA balanced load. Assuming identical X/R ratios, how much load is carried by Transformer A?

A
B
C
D