7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate

Key Takeaways

  • Labor cost equals estimated hours times the wage rate plus labor burden (employer payroll taxes, workers' compensation, and benefits).

  • Access and "other" costs include dumpsters and disposal fees, hoists or boom delivery, fall protection setup, permits, and protection of landscaping and property.

  • Overhead is covered by pricing to a target gross margin. Selling price equals total direct cost divided by (1 minus the target margin).

  • Unit prices for concealed conditions, such as deck replacement per sheet, keep the base price firm and give the owner an agreed price for hidden damage.

  • The estimate becomes the contract only when it is written, signed, and states the specifications, cost, work, and materials under R 338.1533, with the licensing statement for lien rights.

Last updated: September 2026

Building the Labor Estimate

  1. Break the job into tasks: tear-off (per layer), deck repair, dry-in (ice barrier and underlayment), drip edge, shingles, valleys, flashing (walls, chimney, penetrations), ventilation, ridge, and cleanup.
  2. Apply production rates from your own job history, such as squares per crew-day for tear-off and for installation, adjusted for slope, height, access, cut-up areas, and weather season. Steep and high roofs slow production and need more fall-protection setup.
  3. Convert to hours and multiply by the crew's wage rates.
  4. Add labor burden: employer Social Security and Medicare (7.65%), FUTA, Michigan unemployment tax, workers' compensation (a large cost for roofing classifications), and benefits.

Example: A reroof is estimated at 96 crew-hours. The average wage is $26 per hour, and labor burden is 30% of wages.

Labor=96×26×1.30=3,244.80\text{Labor} = 96 \times 26 \times 1.30 = 3{,}244.80

Factors That Change Production

Adjust your production rates for conditions the walk-through revealed:

  • Slope and height. Roofs steeper than about 8:12 need roof brackets or staging and slower, more careful movement. Two-story eaves add ladder and hoisting time.
  • Layers and deck. Each extra layer adds tear-off time and disposal weight. Board decks with gaps may need overlay sheathing.
  • Complexity. Valleys, dormers, skylights, and short runs between hips cut production far more than open planes do.
  • Access. Long carries from the truck, landscaping that blocks the drop zone, or no boom-truck access all add labor.
  • Season. Michigan's cold months slow self-adhered membrane and sealant work, and daylight is shorter. Summer heat needs more breaks.

Subcontractors

List each subcontracted scope as its own line, such as gutter replacement, chimney masonry repair, skylight replacement by a glazing contractor, or a PV removal and reinstall by a licensed electrician. Get written quotes. Confirm licenses where the work requires them, and collect insurance certificates, because an uninsured subcontractor's injured worker can become your workers' compensation claim (MCL 418.171).

Access, Equipment, and Other Direct Costs

ItemExamples
Access and loadingRooftop boom delivery, ladder hoist or conveyor rental, extra ladders, scaffold or roof jacks
Fall protectionAnchors (often left in place or replaced), lifelines, guardrail systems, and setup time
DisposalDumpster rental, hauling, and landfill fees by weight. Lead or asbestos debris is handled separately
Permits and inspectionsLocal permit fee
ProtectionTarps, plywood for condensers and driveways, and magnetic sweeping
MaterialsFrom the takeoff (Section 7.4), including sales or use tax, which in Michigan is the contractor's cost
Warranty costsManufacturer registration fees and a reserve for workmanship callbacks

Overhead and Profit

Overhead is the cost of running the business: office, vehicles, insurance, estimator time, licensing, advertising. Price each job to recover its share of overhead and a profit.

Selling price=Total direct cost1−target gross margin\text{Selling price} = \frac{\text{Total direct cost}}{1 - \text{target gross margin}}

Example: Direct costs are materials $7,800, labor $3,245, disposal and delivery $950, and permit $180, a total of $12,175. The company targets a 30% gross margin to cover 20% overhead and 10% net profit.

12,1751−0.30=12,1750.70=17,392.86\frac{12{,}175}{1 - 0.30} = \frac{12{,}175}{0.70} = 17{,}392.86

Marking up the cost by 30% instead would give $15,827.50, only a 23.1% margin. That is enough for overhead but leaves just 3.1% profit.

Presenting the Estimate

A professional proposal lists:

  • the exact scope: layers removed, deck inspection, ice barrier coverage past the wall line, underlayment type, drip edge, flashing replacement, ventilation, cleanup;
  • specifications: shingle brand and line, ASTM wind and impact ratings, nail count and type, metal types and gauges;
  • unit prices for concealed conditions, such as "$85 per 4-by-8 sheet of 7/16-inch OSB replaced, installed";
  • allowances, if any, and exclusions such as interior repairs, chimney masonry, and gutters unless listed;
  • the price, the payment schedule (a deposit, progress payments, and final, never the full job in advance), and the start and completion window;
  • permits, insurance, and warranty statements.

When accepted, the proposal must become a written, signed agreement that clearly states the specifications, cost, type and amount of work, and type and quality of materials (R 338.1533). It must include your license information (MCL 339.2404a) and, for lien rights on a home, the statement that residential builders and M&A contractors must be licensed, with your license number (MCL 570.1114). For in-home sales, attach the Home Solicitation Sales Act notices (Section 3.4).

Checking the Estimate

Before sending the proposal:

  • Compare the price per square to your recent similar jobs. Check the slope factor, waste, and layer count. Confirm the ice barrier courses for the overhang and slope.
  • Confirm the crew size and schedule are realistic for the season.
  • After the job, compare actual labor hours and material use with the estimate, and update your production rates. Job costing is how estimates improve.

One Business and Law Estimating Question

PSI assigns one Business and Law question to "estimating pertaining to residential building." Expect it to test the same skills as this chapter: quantities, unit conversions, and the difference between markup and margin.

Test Your Knowledge

A job needs 120 labor hours at an average wage of $25 per hour, and the company's labor burden is 28% of wages. What is the burdened labor cost?

A

$3,000

B

$3,280

C

$3,840

D

$4,200

Test Your Knowledge

Total direct costs for a reroof are $14,000, and the contractor needs a 30% gross margin. What is the selling price?

A

$18,200

B

$20,000

C

$19,600

D

$21,000

Test Your Knowledge

Why do many Michigan roofers include a unit price for deck replacement in the original contract?

A

Michigan law caps deck replacement at a fixed number of sheets

B

It lets the contractor avoid writing change orders

C

It sets an agreed, written price for concealed damage, which is then documented with a quantity change order

D

It lets the contractor skip the permit when decking is replaced