15.1 Anchor Bolt Layouts, Base Plate Details & Embed Schedules

Key Takeaways

  • Use the structural foundation plan to find the assembly, then read the anchor and base plate details for the steel grade, dimensions and reference elevations.

  • Where specified, ACI 117-10 Section 2.3.4 sets a ±1/2-inch top elevation tolerance and horizontal limits for individual rods that depend on the diameter.

  • Measure top elevation from the project datum, projection from the actual top of concrete and effective embedment to the applicable load-transfer surface.

  • Build the projection stack from the concrete surface to the nut’s outside face. Count the plate’s support gap once and check thread engagement and any specified protrusion separately.

  • Verify the approved anchor and embed layout before concealment. Record and refer out-of-tolerance conditions through the project’s discrepancy process.

Last updated: November 2026

15.1 Anchor Bolt Layouts, Base Plate Details & Embed Schedules

Start with the foundation plan, the column mark and the grid intersection. Follow the detail callout to the anchor assembly and the base plate section. The plan locates the assembly. The schedule identifies the required rod, plate or embed type. The section shows what the plan view cannot, including the elevation of the concrete, the bearing surface of the plate and the depth below the concrete surface. On a 47P exhibit, check which dimension applies to each of those surfaces before selecting an answer.

1. Verify the rod and the plate as a matched assembly

ASTM F1554 identifies anchor rod grades 36, 55 and 105 by their minimum yield strength in ksi. If the approved schedule requires weldable Grade 55, check for the specified S1 supplementary requirement in the material documentation. If a detail calls for Grade 105, identify it by the approved material documentation and refer any proposed welding or heating for design review. The number by itself describes a strength grade and does not authorize a field modification.

Check rod diameter, length and thread length separately. Match the base plate hole pattern, plate washer and nut to the approved detail. The AISC Steel Construction Manual gives recommended maximum anchor rod hole sizes and associated washer details for accommodating rod placement variation. The approved assembly may call for smaller holes or particular washers. A rod can satisfy its setting tolerance while still conflicting with a hole or washer in the specified assembly. Document the two checks separately. If the plate cannot be seated, refer the mismatch through the discrepancy process. Do not enlarge the holes, bend the rod or substitute a washer on the inspector’s authority.

2. Check setting tolerances and projection separately

Read the project’s referenced standard and any tighter limits on the approved embedment detail. Under ACI 117-10 Sections 2.3.4.1 and 2.3.4.2, the top elevation of each anchor bolt may vary by ±1/2 inch from the specified elevation. Individual horizontal centerline deviation is limited as follows.

Anchor rod diameterMaximum horizontal deviation
3/4 or 7/8 inch1/4 inch
1, 1-1/4 or 1-1/2 inches3/8 inch
1-3/4, 2 or 2-1/2 inches1/2 inch

For steel erection where AISC 303-22 applies, Section 7.5.1 uses the same numerical limits and checks horizontal deviation anywhere along the exposed projection. Section 7.5.2 requires the axis to be perpendicular to the theoretical bearing surface unless the contract documents specify otherwise. If a rod leans, checking the centerline at its top and near the concrete surface helps identify a conflict that a single measurement can miss.

Set up the survey from the project grids and benchmark. Compare each rod with its specified position, then verify the plate fit separately. The top elevation is a coordinate on the project datum. Projection equals the rod top elevation minus the actual concrete top elevation. If the concrete top is 1/4 inch high while the rod top is on its specified elevation, the projection is 1/4 inch shorter than it would have been at the specified concrete elevation.

3. Work through the base plate stack

The example detail shows a 1-1/2-inch distance from top of concrete to the underside of the base plate, a 1-3/4-inch base plate, a 3/8-inch top washer and a 1-inch nut. Any leveling hardware within the 1-1/2-inch gap is already included in that distance. The rod has eight threads per inch. The drawing shows 1/2 inch of nominal protrusion beyond the nut and requires at least two exposed full threads. Assume the threaded portion reaches through the nut and the rod end has no incomplete threads in the dimensions used below.

Datum or dimensionInches above concrete
Underside of base plate1.500
Top of base plate3.250
Top of washer3.625
Outer face of nut4.625
Nominal rod top5.125

Each thread pitch is 1/8 inch, so two pitches occupy 1/4 inch. The shortest projection that provides the specified protrusion in this example is 4.625 + 0.250 = 4.875 inches. Compare the actual projection to this minimum and the actual top elevation to the specified top elevation. For this survey, the concrete top is at its specified datum, so elevation changes correspond to projection changes.

RodMeasured projectionDeviation from specified top elevationExposed length beyond nut
A5.375 in.+0.250 in.0.750 in.
B5.0625 in.−0.0625 in.0.4375 in.
C4.625 in.−0.500 in.0.000 in.

A and B meet both numerical checks. C is at the elevation tolerance boundary but misses the specified protrusion. A nut that reaches the rod end may still engage its threads fully, depending on the usable threads and actual hardware. For C, the measured deficiency is the specified exposed thread length. Document the deficiency and obtain a disposition. When reading another detail, use its own nut, washer, bearing gap and thread requirements. Do not assume the sample two-thread requirement applies to every anchor assembly.

4. Distinguish embedment, projection and rod length

For a cast-in headed rod, ACI 318-19 Chapter 2 and Fig. R2.1 measure effective embedment depth to the head’s bearing contact surface. In the sketch, that surface faces the exposed end of the rod. For a hooked rod or post-installed anchor, use the geometry and embedment specified for that system. Chapter 17 design provisions distinguish the different mechanisms for load transfer and applicable failure modes.

Top of rod                    ───┐
                                 │ projection
Actual top of concrete        ───┼───┐
                                 │   │ effective embedment
Bearing face of cast-in head  ──┬┴┬──┘
                                └─┘

If the head is 1/2 inch thick and the head’s far face lies 13 inches below the surface in this example, the bearing face is 12-1/2 inches below the surface. With a 5-1/8-inch projection, the rod’s overall length is 18-1/8 inches. Record the two depths with their respective datums. One number cannot substitute for the other.

5. Read miscellaneous embed schedules and confirm installation

For an embed plate, match the piece mark to the detail. Check the plate orientation and elevation relative to the concrete face, the pattern and size of welded anchors, and the required distance from edges and adjacent reinforcing steel. For a cast-in anchor with attachments or anchor reinforcement, ACI 318-19 Section 26.7.2(a) requires secure positioning in the forms and orientation as detailed, with consolidation around the anchor and anchor reinforcement during placement. A braced template with dimensions taken from the approved layout is one way to control anchor movement. Confirm that the template can maintain the specified position during discharge and consolidation and that concrete can reach under the plate and around the anchors.

Before concealment, measure and record the location, top elevation, projection and applicable embedment dimensions. Verify inaccessible attachments and clearances at this stage. If the work shifts, identify the affected anchor mark and document the measured location, discrepancy, notification and disposition. In a steel erection application, OSHA 29 CFR 1926.755(b) requires approval from the project structural engineer of record for repair, replacement or field modification of column anchor rods, and written notification from the controlling contractor to the steel erector before column erection.

Test Your Knowledge

Which document evidence establishes that the ASTM F1554 Grade 55 rods supplied for a welded detail meet the specified weldability requirement?

A

A photograph of the finished concrete surface

B

The rod’s measured projection above the base plate

C

Material documentation identifying Grade 55 and the specified S1 supplement

D

A certificate for the concrete mixture’s compressive strength

Test Your Knowledge

The base plate underside is 1-1/2 inches above concrete. The plate is 1-3/4 inches thick, the top washer is 3/8 inch thick and the nut is 1 inch thick. The detail requires two exposed full threads at eight threads per inch. Assuming usable threads throughout, what minimum projection is needed?

A

4-5/8 inches

B

4-7/8 inches

C

5-1/8 inches

D

6-3/8 inches

Test Your Knowledge

What is the purpose of the recommended oversized anchor rod holes in base plates discussed in AISC 303-22 commentary?

A

They accommodate expected setting variation when used with the detailed hardware.

B

They remove the need to verify the rod centerline against the embedment layout.

C

They make the same washer appropriate for every hole diameter.

D

They authorize the installer to enlarge any field hole that interferes with erection.

Test Your Knowledge

The concrete top matches its specified elevation. The rod top is 1/2 inch below its specified elevation and exactly flush with the outer nut face. What follows if ACI 117-10 applies and the detail requires two exposed full threads?

A

The elevation is out of tolerance, and the protrusion requirement is met.

B

Both criteria are met because the nut is flush with the rod.

C

Both criteria are exceeded because the vertical tolerance is ±1/4 inch.

D

The elevation is at its tolerance limit, and the protrusion requirement is unmet.